In: Finance
With the ground broken for the construction of its new home (the Nicol Building), the Sprott School of Business needs someone to supply it with 250 customized computers per year for the next 5 years, and you have decided to bid on the contract. It will cost you $125,000 to install the equipment necessary to start production. The equipment will be depreciated at 30 percent (class 10), and you estimate that it can be salvaged for 20.00% (of the original cost) at the end of the 5- year contract. Your fixed production costs will be $50,000 per year, and your variable production costs should be $600 per computer. You also need an initial investment in net working capital of $13,000. Assuming that your tax rate is 34 percent and you require a 12 percent return on your investment:
a) What is the depreciation tax shield in the third year of this project?
b) What is the present value of the CCA tax shield?
c) What is the minimum price that your company should bid per single computer?
Assuming you believe that Sprott School of Business will pay $975.00 per customized computer, what is the NPV of this project? Should you submit a bid given this new information?
first we need to find the depreciation of the third year
Depreciation schedule |
|||
year |
opening balance |
Depreciation (30%) |
closing balance |
1 |
125,000 |
37,500 |
87,500 |
2 |
87,500 |
26,250 |
61,250 |
3 |
61,250 |
18,375 |
42,875 |
4 |
42,875 |
12,863 |
30,013 |
5 |
30,013 |
9,004 |
21,009 |
depreciation tax shield for the 3rd year is: |
|
depreciation for 3rd year |
18,375 |
tax rate = |
34% |
tax shield = dep. * tax rate |
$ 6,248 |
PV of tax shield =(C-Spv)[(d*t)/(k+d)] * [(1+0.5k)/(1+k)] |
|
c= cost od asset = |
125,000 |
Spv = present value of salvage value |
|
salvage value= 20% * 125000= |
25,000 |
Present value = |
Future value/ (1+r)^n |
PV of salvage value = |
=25000/(1+0.12)^5 =14815.67 |
d= depreciation rate = |
30.00% |
t= tax rate = |
34% |
k= cost of capital= |
12% |
= |
(125000-14815.67)((0.30*0.34)/(0.12+0.30)) * ((1+0.5*0.12)/(1+0.12)) |
=110814.33(0.102/0.42)*(1.06/1.12) |
|
=25470.33 |
So the PV of tax shield= $25,470.33
We need to calculate the total cost of the computers to estimate the break even value where they will incur no loss
This will be trial and error where we will see the rate at which the NVP will be closest to 0
Because the situation where NPV is 0 will be where the cost of the project is recovered and it will be the minimum rate
If we keep the rate as $1000
years |
||||||
Particulars |
0 |
1 |
2 |
3 |
4 |
5 |
initial cost |
125000 |
|||||
net working cap required |
13000 |
|||||
total initial requirement |
138000 |
|||||
sales (250*1000) |
250,000 |
250,000 |
250,000 |
250,000 |
250,000 |
|
fixed cost |
-50,000 |
-50,000 |
-50,000 |
-50,000 |
-50,000 |
|
Depreciation |
-37,500 |
-26,250 |
-18,375 |
-12,863 |
-9,004 |
|
variable cost= 250*600 |
-150,000 |
-150,000 |
-150,000 |
-150,000 |
-150,000 |
|
salvage value recovered |
25,000 |
|||||
EBT |
12,500 |
23,750 |
31,625 |
37,138 |
65,996 |
|
tax= EBT*34% |
4,250 |
8,075 |
10,753 |
12,627 |
22,439 |
|
Net profit |
8,250 |
15,675 |
20,873 |
24,511 |
43,558 |
|
Discount factor (1/(1+r%)^n |
for r= 12% |
1/(1+0.12)^1 |
1/(1+0.12)^2 |
1/(1+0.12)^3 |
1/(1+0.12)^4 |
1/(1+0.12)^5 |
DF |
0.89 |
0.80 |
0.71 |
0.64 |
0.57 |
|
PV of the profit = DF* net profit |
-138000 |
7,366.07 |
12,496.01 |
14,856.63 |
15,577.02 |
24,715.71 |
NPV= sum total = -62988.55
Which is less than 0, so we will increase the rates.
By keeping the rate as $1100
years |
||||||
particulars |
0 |
1 |
2 |
3 |
4 |
5 |
initial cost |
125000 |
|||||
net working cap required |
13000 |
|||||
total initial requirement |
138000 |
|||||
sales (250*975) |
275,000 |
275,000 |
275,000 |
275,000 |
275,000 |
|
fixed cost |
-50,000 |
-50,000 |
-50,000 |
-50,000 |
-50,000 |
|
Depreciation |
-37,500 |
-26,250 |
-18,375 |
-12,863 |
-9,004 |
|
variable cost= 250*600 |
-150,000 |
-150,000 |
-150,000 |
-150,000 |
-150,000 |
|
salvage value recovered |
25,000 |
|||||
EBT |
37,500 |
48,750 |
56,625 |
62,138 |
90,996 |
|
tax= EBT*34% |
12,750 |
16,575 |
19,253 |
21,127 |
30,939 |
|
Net profit |
24,750 |
32,175 |
37,373 |
41,011 |
60,058 |
|
Discount factor (1/(1+r%)^n |
for r= 12% |
1/(1+0.12)^1 |
1/(1+0.12)^2 |
1/(1+0.12)^3 |
1/(1+0.12)^4 |
1/(1+0.12)^5 |
DF |
0.89 |
0.80 |
0.71 |
0.64 |
0.57 |
|
PV of the profit = DF* net profit |
-138000 |
22,098.21 |
25,649.71 |
26,601.01 |
26,063.07 |
34,078.25 |
NPV= -3509.7
So we keep is closer to $1100, as $1106, the NPV= $59 so we can assume that if we keep the price as $1106, the cost is covered.
years |
||||||
particulars |
0 |
1 |
2 |
3 |
4 |
5 |
initial cost |
125000 |
|||||
net working cap required |
13000 |
|||||
total initial requirement |
138000 |
|||||
sales (250*975) |
243,750 |
243,750 |
243,750 |
243,750 |
243,750 |
|
fixed cost |
-50,000 |
-50,000 |
-50,000 |
-50,000 |
-50,000 |
|
Depreciation |
-37,500 |
-26,250 |
-18,375 |
-12,863 |
-9,004 |
|
variable cost= 250*600 |
-150,000 |
-150,000 |
-150,000 |
-150,000 |
-150,000 |
|
salvage value recovered |
25,000 |
|||||
EBT |
6,250 |
17,500 |
25,375 |
30,888 |
59,746 |
|
tax= EBT*34% |
2,125 |
5,950 |
8,628 |
10,502 |
20,314 |
|
Net profit |
4,125 |
11,550 |
16,748 |
20,386 |
39,433 |
|
Discount factor (1/(1+r%)^n |
for r= 12% |
1/(1+0.12)^1 |
1/(1+0.12)^2 |
1/(1+0.12)^3 |
1/(1+0.12)^4 |
1/(1+0.12)^5 |
DF |
0.89 |
0.80 |
0.71 |
0.64 |
0.57 |
|
PV of the profit = DF* net profit |
-138000 |
3,683.04 |
9,207.59 |
11,920.54 |
12,955.51 |
22,375.07 |
NPV= -77858.25
Which shows loss for the company and so the company should not accept this proposal.