Question

In: Finance

With the ground broken for the construction of its new home (the Nicol Building), the Sprott...

With the ground broken for the construction of its new home (the Nicol Building), the Sprott School of Business needs someone to supply it with 250 customized computers per year for the next 5 years, and you have decided to bid on the contract. It will cost you $125,000 to install the equipment necessary to start production. The equipment will be depreciated at 30 percent (class 10), and you estimate that it can be salvaged for 20.00% (of the original cost) at the end of the 5- year contract. Your fixed production costs will be $50,000 per year, and your variable production costs should be $600 per computer. You also need an initial investment in net working capital of $13,000. Assuming that your tax rate is 34 percent and you require a 12 percent return on your investment:

  1. a) What is the depreciation tax shield in the third year of this project?

  2. b) What is the present value of the CCA tax shield?

  3. c) What is the minimum price that your company should bid per single computer?

Assuming you believe that Sprott School of Business will pay $975.00 per customized computer, what is the NPV of this project? Should you submit a bid given this new information?

Solutions

Expert Solution

  1. The depreciation tax shield

first we need to find the depreciation of the third year

Depreciation schedule

year

opening balance

Depreciation (30%)

closing balance

1

                     125,000

                           37,500

                     87,500

2

                        87,500

                           26,250

                     61,250

3

                        61,250

                           18,375

                     42,875

4

                        42,875

                           12,863

                     30,013

5

                        30,013

                             9,004

                     21,009

depreciation tax shield for the 3rd year is:

depreciation for 3rd year

                           18,375

tax rate =

34%

tax shield = dep. * tax rate

                      $       6,248

                                 

  1. PV of the CCA tax shield

PV of tax shield =(C-Spv)[(d*t)/(k+d)] * [(1+0.5k)/(1+k)]

c= cost od asset =

125,000

Spv = present value of salvage value

salvage value= 20% * 125000=

25,000

Present value =

Future value/ (1+r)^n

PV of salvage value =

=25000/(1+0.12)^5 =14815.67

d= depreciation rate =

30.00%

t= tax rate =

34%

k= cost of capital=

12%

=

(125000-14815.67)((0.30*0.34)/(0.12+0.30)) * ((1+0.5*0.12)/(1+0.12))

=110814.33(0.102/0.42)*(1.06/1.12)

=25470.33

So the PV of tax shield= $25,470.33

  1. Now, the maximum they should pay is:

We need to calculate the total cost of the computers to estimate the break even value where they will incur no loss

This will be trial and error where we will see the rate at which the NVP will be closest to 0

Because the situation where NPV is 0 will be where the cost of the project is recovered and it will be the minimum rate

If we keep the rate as $1000

years

Particulars

0

1

2

3

4

5

initial cost

125000

net working cap required

13000

total initial requirement

138000

sales (250*1000)

250,000

250,000

250,000

250,000

250,000

fixed cost

-50,000

-50,000

-50,000

-50,000

-50,000

Depreciation

-37,500

-26,250

-18,375

-12,863

-9,004

variable cost= 250*600

-150,000

-150,000

-150,000

-150,000

-150,000

salvage value recovered

25,000

EBT

12,500

23,750

31,625

37,138

65,996

tax= EBT*34%

4,250

8,075

10,753

12,627

22,439

Net profit

8,250

15,675

20,873

24,511

43,558

Discount factor

(1/(1+r%)^n

for r= 12%
1/(1+12%)^n

1/(1+0.12)^1

1/(1+0.12)^2

1/(1+0.12)^3

1/(1+0.12)^4

1/(1+0.12)^5

DF

0.89

0.80

0.71

0.64

0.57

PV of the profit =

DF* net profit

-138000

7,366.07

12,496.01

14,856.63

15,577.02

24,715.71

NPV= sum total = -62988.55

Which is less than 0, so we will increase the rates.

By keeping the rate as $1100

years

particulars

0

1

2

3

4

5

initial cost

125000

net working cap required

13000

total initial requirement

138000

sales (250*975)

275,000

275,000

275,000

275,000

275,000

fixed cost

-50,000

-50,000

-50,000

-50,000

-50,000

Depreciation

-37,500

-26,250

-18,375

-12,863

-9,004

variable cost= 250*600

-150,000

-150,000

-150,000

-150,000

-150,000

salvage value recovered

25,000

EBT

37,500

48,750

56,625

62,138

90,996

tax= EBT*34%

12,750

16,575

19,253

21,127

30,939

Net profit

24,750

32,175

37,373

41,011

60,058

Discount factor (1/(1+r%)^n

for r= 12%
1/(1+11%)^n

1/(1+0.12)^1

1/(1+0.12)^2

1/(1+0.12)^3

1/(1+0.12)^4

1/(1+0.12)^5

DF

0.89

0.80

0.71

0.64

0.57

PV of the profit = DF* net profit

-138000

22,098.21

25,649.71

26,601.01

26,063.07

34,078.25

NPV= -3509.7

So we keep is closer to $1100, as $1106, the NPV= $59 so we can assume that if we keep the price as $1106, the cost is covered.

  1. Now if the price is $975

years

particulars

0

1

2

3

4

5

initial cost

125000

net working cap required

13000

total initial requirement

138000

sales (250*975)

243,750

243,750

243,750

243,750

243,750

fixed cost

-50,000

-50,000

-50,000

-50,000

-50,000

Depreciation

-37,500

-26,250

-18,375

-12,863

-9,004

variable cost= 250*600

-150,000

-150,000

-150,000

-150,000

-150,000

salvage value recovered

25,000

EBT

6,250

17,500

25,375

30,888

59,746

tax= EBT*34%

2,125

5,950

8,628

10,502

20,314

Net profit

4,125

11,550

16,748

20,386

39,433

Discount factor (1/(1+r%)^n

for r= 12%
1/(1+11%)^n

1/(1+0.12)^1

1/(1+0.12)^2

1/(1+0.12)^3

1/(1+0.12)^4

1/(1+0.12)^5

DF

0.89

0.80

0.71

0.64

0.57

PV of the profit = DF* net profit

-138000

3,683.04

9,207.59

11,920.54

12,955.51

22,375.07

NPV= -77858.25

Which shows loss for the company and so the company should not accept this proposal.


Related Solutions

A company made the following expenditures in connection with the construction of its new building: Architect’s...
A company made the following expenditures in connection with the construction of its new building: Architect’s fees for the new building $25,000 Cash paid for land and run-down building on the land 425,000 Removal of old building 17,500 Salvage from sale of old building materials 6,000 Construction survey to site the new building 3,500 Legal fees for title search 4,500 Excavation for basement construction 45,500 Machinery purchased for operations 250,000 Storage charges on machinery because building was not ready when...
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
UVW began construction of a new office building on March 1, Y1. On the day construction...
UVW began construction of a new office building on March 1, Y1. On the day construction began, UVW borrowed $240,000 at 7% and immediately spent it on the project. An additional payment of $60,000 was also made on the day construction began. Additional expenditures of $75,000 were made on May 1 and August 31. Construction was complete and the building was placed in service on December 31, Y1. In addition to the $240,000 borrowed to finance the project, UVW also...
At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures...
At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures during 2018 were as follows: January 1                     $400,000 May 1                          150,000 July 1                         300,000   December 31               100,000    Heinz has the following debts outstanding during 2018; the bonds payable is directly related to the construction projects; none of the others are related to the construction project. Liability Annual Percent Loan Amount Notes Payable 4% $200,000 Bonds Payable 6% $400,000 Mortgage Payable 5% $300,000
Option 1: Building a new refinery The construction and installation of a new refinery will cost...
Option 1: Building a new refinery The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources’ current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the...
Option 1: Building a new refinery The construction and installation of a new refinery will cost...
Option 1: Building a new refinery The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources’ current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the...
Question: Building a new refinery The construction and installation of a new refinery will cost $22...
Question: Building a new refinery The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources' current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the fleet...
Shawn Van​ Dike, a construction industry​ consultant, wrote on a home building​ site:    Brains do some...
Shawn Van​ Dike, a construction industry​ consultant, wrote on a home building​ site:    Brains do some pretty funny things when making a buying decision. If you understand your​ customers' brain​ activities, then you can use this knowledge to help increase your sales and deliver on value...​ There's an old question in advertising.​ "How do you sell a​ $2,000 watch? Put it next to a​ $10,000 watch." This is an example of price anchoring. ​Source: Shawn Van​ Dike, "The Psychology of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT