In: Operations Management
1.
The first unit took 10 hours and the fourth unit 8.1 hours. What is the improvement rate?
2.
T1 = 1000, Learning rate = 80%.
It will take _____________ hours to make the first 15 units?
3. The learning curve may not be permanent; it can be disrupted by changes in process, personnel, or product.
TRUE OR FALSE
1)
Time taken by first unit, T1 = 10 hours
Time taken by fourth unit, T4 = 8.1 hours
Using learning curve equation, Tn = T1*r(ln(n)/ln(2)), where r is the improvement or learning rate
T4 = T1*r(ln(4)/ln(2))
T4/T1 = r(ln(4)/ln(2))
T4/T1 = r2
Improvement or learning rate, r = (T4/T1)^(1/2)
= (8.1/10)^(1/2)
= 90 %
---------------------------------------------------
2)
T1 = 1000
Learning rate , r = 80%
Time for each unit is computed by learning curve equation Tn = T1*r(ln(n)/ln(2)),
Calculations are shown in Excel as follows:
EXCEL FORMULA:
-----------------------------------------------------------------
3)
TRUE
The learning or improvement rate may be disrupted by changes in process, personnel, or product. These are subjective factors, which can influence the learning rate.