In: Operations Management
first unit of a product took 900 hour to build and learning curve 90%. how long will it take to make the first 3 units
Total Time for n units = Time for 1st unit*Total time factor at Learning rate % for n units
Total time for 3 units = 900*Total time factor at 90% learning rate for 3 units
= 900*2.746
= 2471.40 hours