Question

In: Finance

A project has the following cash flows:

A project has the following cash flows:

  

Year Cash Flow
0 $ 39,500
1 18,500
2 29,500

  

What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

  

  IRR %

  

What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

  NPV $   

    

What is the NPV of the project if the required return is 0 percent? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign.)

  

  NPV $   

   

What is the NPV of the project if the required return is 22 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

  NPV $   

Solutions

Expert Solution

What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Year Cash Flow
0 39500
1 -18500
2 -29500
IRR 12.95%

Using IRR Excel Funtion

What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Year Cash Flow PV factor 11% PV
0 39500 1 39500
1 -18500 0.900900901 -16666.7
2 -29500 0.811622433 -23942.9
NPV -1109.53

What is the NPV of the project if the required return is 0 percent? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign.)

Year Cash Flow PV factor 0% PV
0 39500 1.0000 39500
1 -18500 1.0000 -18500
2 -29500 1.0000 -29500
NPV -8500

What is the NPV of the project if the required return is 22 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Year Cash Flow PV factor22% PV
0 39500 1.0000 39500
1 -18500 0.8197 -15163.9
2 -29500 0.6719 -19819.9
NPV 4516.125

Related Solutions

A project has the following cash flows:
A project has the following cash flows:YearCash Flow0–$16,60017,30028,60037,100   a.What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)b.What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)c.What is the NPV at a discount rate of 19 percent? (A negative answer should be indicated by a minus sign. Do...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $64,000 1 –30,000 2 –48,000    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 12 percent?    c. NPV at 0 percent?    d. NPV at 24 percent?
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. 6. A project has the following...
A project has the following cash flows. This project is of average risk and the WACC...
A project has the following cash flows. This project is of average risk and the WACC is 0.1. Find the Net Present Value. Round your answer to two decimal places. Year 0 Year 1 Year 2 Year 3 Cash Flow -$91 $50 $40 $7
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
A project has the following cash flows : C0                           C1         &nb
A project has the following cash flows : C0                           C1                           C2 +6,750                   +4,500                   -18,000 Calculate the NPV of the project for a discount rate of i) 0% ii)33%   iii) 50% and iv) 100%. Which discount rate provides the largest NPV?                 a)            0%                 b)            33%                 c)            50%                 d)            100%
Dax Systems is considering a project that has the following cash flows for Project X and...
Dax Systems is considering a project that has the following cash flows for Project X and Y. What is the PI of X, using the new method? Cost of Capital = 10% Year Project X Project Y 0 -$1,000 -$2,000 1 $500 $1,400 2 $500 $800 3 $500 $400 0.243 0.201 0.545 0.920 0.117
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT