Question

In: Finance

A project has the following cash flows:

A project has the following cash flows:

  

Year Cash Flow
0 $ 39,500
1 18,500
2 29,500

  

What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

  

  IRR %

  

What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

  NPV $   

    

What is the NPV of the project if the required return is 0 percent? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign.)

  

  NPV $   

   

What is the NPV of the project if the required return is 22 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

  NPV $   

Solutions

Expert Solution

What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Year Cash Flow
0 39500
1 -18500
2 -29500
IRR 12.95%

Using IRR Excel Funtion

What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Year Cash Flow PV factor 11% PV
0 39500 1 39500
1 -18500 0.900900901 -16666.7
2 -29500 0.811622433 -23942.9
NPV -1109.53

What is the NPV of the project if the required return is 0 percent? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign.)

Year Cash Flow PV factor 0% PV
0 39500 1.0000 39500
1 -18500 1.0000 -18500
2 -29500 1.0000 -29500
NPV -8500

What is the NPV of the project if the required return is 22 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Year Cash Flow PV factor22% PV
0 39500 1.0000 39500
1 -18500 0.8197 -15163.9
2 -29500 0.6719 -19819.9
NPV 4516.125

Related Solutions

A project has the following cash flows:
A project has the following cash flows:YearCash Flow0–$16,60017,30028,60037,100   a.What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)b.What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)c.What is the NPV at a discount rate of 19 percent? (A negative answer should be indicated by a minus sign. Do...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $64,000 1 –30,000 2 –48,000    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 12 percent?    c. NPV at 0 percent?    d. NPV at 24 percent?
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. 6. A project has the following...
A project has the following cash flows. This project is of average risk and the WACC...
A project has the following cash flows. This project is of average risk and the WACC is 0.1. Find the Net Present Value. Round your answer to two decimal places. Year 0 Year 1 Year 2 Year 3 Cash Flow -$91 $50 $40 $7
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
Dax Systems is considering a project that has the following cash flows for Project X and...
Dax Systems is considering a project that has the following cash flows for Project X and Y. What is the PI of X, using the new method? Cost of Capital = 10% Year Project X Project Y 0 -$1,000 -$2,000 1 $500 $1,400 2 $500 $800 3 $500 $400 0.243 0.201 0.545 0.920 0.117
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT