In: Finance
A project has the following cash flows. This project is of average risk and the WACC is 0.1. Find the Net Present Value. Round your answer to two decimal places.
Year 0 Year 1 Year 2 Year 3
Cash Flow -$91 $50 $40 $7
rate | 10.0000% | 10% | |
Cash flows | Year | Discounted CF= cash flows/(1+rate)^year | Cumulative cash flow |
(91.00) | 0 | (91.00) | (91.00) |
50.000 | 1 | 45.45 | (45.55) |
40.000 | 2 | 33.06 | (12.49) |
7.000 | 3 | 5.26 | (7.23) |
NPV = -7.23