Question

In: Finance

A project has the following cash flows. This project is of average risk and the WACC...

A project has the following cash flows. This project is of average risk and the WACC is 0.1. Find the Net Present Value. Round your answer to two decimal places.

Year 0 Year 1 Year 2 Year 3

Cash Flow -$91 $50 $40 $7

Solutions

Expert Solution

rate 10.0000% 10%
Cash flows Year Discounted CF= cash flows/(1+rate)^year Cumulative cash flow
                   (91.00) 0                                   (91.00)                                (91.00)
                   50.000 1                                     45.45                                (45.55)
                   40.000 2                                     33.06                                (12.49)
                     7.000 3                                        5.26                                  (7.23)

NPV = -7.23


Related Solutions

1. Laketown Enterprises is considering a project that has the following cash flows. It’s WACC is...
1. Laketown Enterprises is considering a project that has the following cash flows. It’s WACC is 10%. Year 0, 1, 2, and 3 Cash flows are $950, $500, $400, and $300, respectively. a. What is the project’s payback period? b. What is the project’s NPV? c. What is the project’s IRR? d. What is the project’s discounted payback period? 2. Cole Trucking, the company you work for, is considering a new project whose data are shown below. What is the...
An analyst identifies the following cash flows for an average-risk project: • Year 0 -$5,000 •...
An analyst identifies the following cash flows for an average-risk project: • Year 0 -$5,000 • Year 1-2 $1,900 • Year 3 $2,500 • Year 4 $2,000 22. If the company’s cost of capital is 12%, the project’s discounted payback period is closest to: * A. 2.5 years B. 3.0 years C. 3.9 years D. None of the above 23. If the company’s cost of capital is 12%, the project’s Modified Internal Rate of Return is closest to: * A....
A project has the following cash flows:
A project has the following cash flows:YearCash Flow0–$16,60017,30028,60037,100   a.What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)b.What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)c.What is the NPV at a discount rate of 19 percent? (A negative answer should be indicated by a minus sign. Do...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $ 39,500 1 – 18,500 2 – 29,500    What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)      IRR %    What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $64,000 1 –30,000 2 –48,000    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 12 percent?    c. NPV at 0 percent?    d. NPV at 24 percent?
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
Rocket Inc. is considering a project that has the following cash flow and WACC data. WACC:...
Rocket Inc. is considering a project that has the following cash flow and WACC data. WACC: 10.00% Year 0    1 2 3 4 Cash flows -$1,000 $510 $440 $425 $405 What is the project's payback?    What is the project's discounted payback?    Is the project worthwhile to undertake? (Would you undertake the project?) Why?
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. 6. A project has the following...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
You are considering a project that has the following cash flow and WACC data. What is...
You are considering a project that has the following cash flow and WACC data. What is the project’s NPV? WACC: 9.00% Year: 0 1 2 3 4 5 Cash flows: –$1,000 $300 $300 $300 $300 $300 Select one: a. 150.62 b. 176.4 c. 166.90 d. 143.90
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT