Question

In: Finance

Dax Systems is considering a project that has the following cash flows for Project X and...

Dax Systems is considering a project that has the following cash flows for Project X and Y. What is the PI of X, using the new method? Cost of Capital = 10% Year Project X Project Y 0 -$1,000 -$2,000 1 $500 $1,400 2 $500 $800 3 $500 $400 0.243 0.201 0.545 0.920 0.117

Solutions

Expert Solution

Statement showing Cash flows
Particulars Time PVf 10% Amount PV
Cash Outflows                            -                          1.00             (1,000.00)             (1,000.00)
PV of Cash outflows = PVCO             (1,000.00)
Cash inflows                        1.00                   0.9091                   500.00                   454.55
Cash inflows                        2.00                   0.8264                   500.00                   413.22
Cash inflows                        3.00                   0.7513                   500.00                   375.66
PV of Cash Inflows =PVCI               1,243.43
PI = PVCI/PVCO                        1.24

Related Solutions

Alpha Systems Ltd. is considering a project with a cost of $160,000 and cash flows of...
Alpha Systems Ltd. is considering a project with a cost of $160,000 and cash flows of $32,500 per year for the eight-year life of the project (a) If the risk-free are is 8% and the risk premium is 4%, should the project be accepted? (b) Suppose the firm used a firm-wide opportunity cost of capital approach. If the opportunity cost of capital is 16% and the risk premium is the same, should the project be accepted?
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
Consider the following project X: Project X costs $1300 and has cash flows of $477, $111,...
Consider the following project X: Project X costs $1300 and has cash flows of $477, $111, $452, $268, $526 in each of the next 5 years. WACC=8.75%. A) Draw the timeline for projects X B) Calculate the project NPV, IRR, payback period E) Plot NPV profiles for the project. Identify project IRRs on the graph.
You are considering two projects with the following cash flows: Project Y Project X Year 1...
You are considering two projects with the following cash flows: Project Y Project X Year 1 $9,500 $6,000 Year 2 $9,000 $6,900 Year 3 $6,900 $9,000 Year 4 $6,000 $9,500 Which one of the following statements is true concerning the two projects given a positive discount rate? A. Project Y has both a higher present value and a higher future value than project X. B. Both projects have the same future value at the end of year 4. C. Project...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
A project has the following cash flows:
A project has the following cash flows:YearCash Flow0–$16,60017,30028,60037,100   a.What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)b.What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)c.What is the NPV at a discount rate of 19 percent? (A negative answer should be indicated by a minus sign. Do...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $ 39,500 1 – 18,500 2 – 29,500    What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)      IRR %    What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $64,000 1 –30,000 2 –48,000    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 12 percent?    c. NPV at 0 percent?    d. NPV at 24 percent?
Shannon Industries is considering a project that has the following cash flows :    Year CF...
Shannon Industries is considering a project that has the following cash flows :    Year CF 0 -6240 1 1980 2 3750 3 ? 4 1000 The project has a payback of 2.25 years. The firm’s cost of capital is 9.3 percent. What is the project’s net present value (NPV)?
Braun Industries is considering an investment project that has the following cash flows:                           &nbs
Braun Industries is considering an investment project that has the following cash flows:                                                                                                     Project                                                    Year                                     Cash Flows                                                           0                                             -$641                                                       1                                              $421                                                       2                                              $407                                                       3                                              $490 The company’s WACC is 10.5 percent.  What is the project’s payback, internal rate of return (IRR), and net present value (NPV)?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT