Question

In: Operations Management

A firm has established a distribution network for the supply of a raw material critical to...

A firm has established a distribution network for the supply of a raw material critical to its manufacturing. Currently there are two origins for this material, which must be shipped to three manufacturing plants. The current network has the following characteristics:



Costs

plant 1

plant 2

plant 3

supply

raw material source 1

$6

$8

$9

400

raw material source 2

$4

$7

$3

600

demand

500

500

500

supply < demand






The firm has identified two potential sites for a third raw material source; these are identified as Candidate A and Candidate B. From A, the costs to ship would be $9 to Plant 1, $10 to Plant 2, and $12 to Plant 3. From B, these costs would be $11, $14, and $8. The new source, wherever it is located, will have a capacity of 500 units. Solve with the transportation method. Which site should be selected?

site should be selected?

Solutions

Expert Solution

Hi,

Please find answer as below.

If you like the answer, please up vote.

Answer

I have used excel solver to solve the problem. I have attached the snapshot of Input data, formulas and constraints used along with the optimal solution.

Candidate A is selected to minimize the cost.

1. Snapshot of Input Data

2. Snapshot of Formulas used

3. Snapshot of Constraints used

4. Snapshot of Optimal Solution


Related Solutions

Research about "supply network for company raw material". 12 pages.
Research about "supply network for company raw material". 12 pages.
Two chemical companies can supply a raw material. The concentration of an element in this material...
Two chemical companies can supply a raw material. The concentration of an element in this material is important. A random sample with 9 observations from company 1 yields a sample mean of 12.6 and a sample standard deviation of 2.7, and another sample with 11 observations from company 2 yields a sample mean of 14.5 and a sample standard deviation of 5.5. Is there a sufficient evidence to conclude that the variance of company 1 is less than variance of...
Personal selling likely to be MOST important when: - the distribution network is well established (as...
Personal selling likely to be MOST important when: - the distribution network is well established (as opposed to poorly established). - prices are negotiable (instead of fixed list prices) because of industry competition. - the product is simple (as opposed to complex), requiring no demonstration. - the target market is composed of thousands of small customers (as opposed to 50 large customers). Kay was widely recognized in her firm and the industry as a superb leader and sales manager. The...
2. A firm is considering the delivery times of two raw material suppliers, A and B....
2. A firm is considering the delivery times of two raw material suppliers, A and B. The firm is basically satisfied with supplier A; however, if the firm finds the mean delivery time of supplier B is less than the mean delivery time of supplier A, the firm will begin purchasing raw materials from supplier B (meaning, switch from supplier A to supplier B). Independent samples (assume equal population variances) show the following sample data for the delivery times of...
Suppose that a manufacturer has an ongoing need for silver as a raw material in the...
Suppose that a manufacturer has an ongoing need for silver as a raw material in the production process, and is concerned about the risk of the price of silver going up. The firm is considering two hedging choices: futures contracts and option contracts. Suppose that the firm decides to hedge using futures contracts. Should it buy or sell futures contracts? Explain.
Suppose that a manufacturer has an ongoing need for silver as a raw material in the...
Suppose that a manufacturer has an ongoing need for silver as a raw material in the production process, and is concerned about the risk of the price of silver going up. The firm is considering two hedging choices: futures contracts and option contracts. (i) Suppose that the firm decides to hedge using futures contracts. Should it buy or sell futures contracts? Explain. (ii) Suppose that the firm decides to hedge using option contracts. Should it use call or put options?...
Sven Broker, an analyst with an established brokerage firm, comments: “The critical number I look at...
Sven Broker, an analyst with an established brokerage firm, comments: “The critical number I look at for any company is operating cash flow. If cash flows are less than earnings, I consider the company to be a poor performer and a poor investment prospect.” Do you agree with this assessment? Why or why not?
The Koski Company has established standards as follows: Direct material                               &nb
The Koski Company has established standards as follows: Direct material                                                     3 pounds @ P4/pound = P12 per unit Direct labor                                                           2 hours @ P8/hour = P16 per unit Variable overhead                                              2 hours @ P5/hour = $10 per unit Actual production figures for the past year were as follows: Units produced                                                                                    500 Direct material used                                                                           1,600 pounds Direct material purchased (3,000 pounds)                                    $12,300 Direct labor cost (950 hours)                                                             $ 7,790 Variable overhead cost incurred                                     ...
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
What is the critical path of the network?
What is the critical path of the network?