Question

In: Operations Management

A project has just completed its 87th task of a total of 150 tasks in its...

A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming the remaining work will be completed as budgeted? Is this likely?

a. CV =

b. SV =

c. SPI =

d. CPI =

e. EAC =

Solutions

Expert Solution

Project cost control is nothing but the process by which the status of the project is monitored so that the project costs are updated and changes to the cost baseline are managed. Project cost control include: -

  • Factors that result in changes to the authorized cost baseline are influenced.
  • To ensure all change request are managed in timely manner.
  • To ensure the cost expenditure is less than authorized funding.
  • Monitoring cost performance
  • Monitoring work performance
  • Expected cost overrun are kept in acceptable limits.


Related Solutions

Assume that for this project to be completed, five independent tasks must be completed. These tasks...
Assume that for this project to be completed, five independent tasks must be completed. These tasks are proceeding in parallel by five different subcontractors. To keep it simple, let's assume that each task takes between 1 and 5 months to complete (uniformly distributed, i.e. equally likely to take any amount of time between 1 and 5 months). So, the mean time to complete each task is 3 months and the probability of any given task taking 3 months or longer...
A project consists of two tasks. Task A is scheduled to begin at the start of...
A project consists of two tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 2 and finish at the end of Week 3. The budgeted cost for Task A is $80,000, and for Task B is $40,000. 1. Creat a cost loaded for this project: Round the number to the closest integer number and input it without...
Use Word to create a task list with a minimum of 25 tasks for the project...
Use Word to create a task list with a minimum of 25 tasks for the project plan. The tasks should be in the format of verb then noun. Deliverable headings should be nouns. The list should be a complete plan to build a local area network in an office.
describe a project list two task that may be performed in parallel and two tasks that...
describe a project list two task that may be performed in parallel and two tasks that need to be performed sequeooontially
A successful cloning project of Dimetrodon has just been completed that resulted in several live and...
A successful cloning project of Dimetrodon has just been completed that resulted in several live and reproducing specimens of dimetrodons. Since Dimetrodons are early "stem-mammal members", a non-mammal that gave rise to the mammalian lineage, no one knows how it goes through development, similar to fish, amphibians, chickens, reptiles, mammals, or a new unique process altogether. You have been designed to lead the project to determine how gastrulation occurs in dimetrodons. You have decided to approach the problem by locating...
Assume Maple Corp. has just completed the third year of its existence (year 3).
 Assume Maple Corp. has just completed the third year of its existence (year 3). The table below indicates Maple's ending book inventory for each year and the additional $263A costs it was required to include in its ending inventory. Maple immediately expensed these costs for book purposes. In year 2, Maple sold all of its year 1 ending inventory, and in year 3 it sold all of its year 2 ending inventory. Required: a. What book-tax difference associated with its inventory did...
harley, an american based manufacturer of bicycles, has just completed its demand forecast for their newest...
harley, an american based manufacturer of bicycles, has just completed its demand forecast for their newest mountain-bike frame OEXI 7500. The forecast for the next 5 months is given below. Month    Demand Jan             225 Feb            200 Mar           250 Apr            225 May           850 The company employs 15 workers that work on no other frame but OEXI 7500. Each new employee must be trained before he/she can work. It costs $750 to train a new worker. Assume that training occurs instantaneously. Once trained, a new worker can produce...
Flaherty, Inc., has just completed its first year of operations. The unit costs on a normal...
Flaherty, Inc., has just completed its first year of operations. The unit costs on a normal costing basis are as follows: Manufacturing costs (per unit): Direct materials (2 lbs. @ 1.45): $2.90 Direct labor (0.4 hr. @ 16.00): $6.40 Variable overhead (0.4 hr. @ 5.00): $2.00 Fixed overhead (0.4 hr. @ 7.00): $2.80 Total: $14.10 Selling and administrative costs: Variable: $1.90 per unit Fixed: $221,500 During the year, the company had the following activity: Units produced: 26,000 Units sold: 23,400...
Illusions Inc. just completed its second year of operations and has a deferred tax asset of?...
Illusions Inc. just completed its second year of operations and has a deferred tax asset of? $47,500 related to a net operating loss of? $125,000 from the previous year. In the current year Illusions generates? $400,000 in revenues and incurs? $250,000 in expenses. There are no permanent or temporary? book-tax differences. Assuming the same tax rate as last? year, what amount will Illusions record for Income Tax Payable in the current? year?
QUESTION I Project Background You have just completed a postgraduate diploma in project management and are...
QUESTION I Project Background You have just completed a postgraduate diploma in project management and are currently registered for a master’s degree where you have to carry out a mini research on customer care in your organization. Develop a project proposal on the planning, execution, analysis and reporting of the research. All processes planned for should be finalized within 6 months from the 4th august 2018. GENERAL PROJECT TASK The following needs to be done: You know:  How to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT