Question

In: Operations Management

A project consists of two tasks. Task A is scheduled to begin at the start of...

A project consists of two tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 2 and finish at the end of Week 3. The budgeted cost for Task A is $80,000, and for Task B is $40,000.

1. Creat a cost loaded for this project:

Round the number to the closest integer number and input it without "$" and ',' signs.

Cost at Week 1:

Cost at Week 2:

Cost at Week 3:

Cost at Week 4:

2. At the end of the second week Task A is 50% complete, and Task B is 25% complete. Calculate the following items:

BCWS :

BCWP :

3. What is the schedule performance index for the project at the end of the second week (Round decimal numbers to 2 decimal places. If it is less than 1, write it in the following format: 0.xx)?

4. The actual cost of the work performed at the end of the second week is $40,000. Determine the cost performance index for the project (Round decimal numbers to 2 decimal places. If it is less than 1, write it in the following format: 0.xx).

Solutions

Expert Solution

TAsk A - Start w1 and End W4

A, Each Week cost = 80,000/4 = 20,000

Task B , Start W2 and End W3, Duration 2 week

B, Each week Cost = 40,000/2 = 20,000

W1 W2 w3 W4
Task A 20000 20000 20000 20000
Task B 20000 20000
Cost 20000 40000 40000 20000

Cost

W1 = 20000

W2 = 40000

W3 = 40000

W4 = 20000

2.

At end of Week 2

Planed A Completion = 50%

Planned B completion = 50%

Planned cost of A = 40,000

Planned Cost of B = 20,000

BCWS, Budgeted cost of work schedule or also called Planned value(PV) = Planned cost of A + Planned Cost of B = 40,000+20,000 = 60,000

Actual completion of A = 50%

Actual Completion of B = 25%

So, Budgeted cost for work performed (BCWP) also known as Earned value = Budgest cost of work performed

Budgest cost of work performed , A= 50%*80000 = 40,000

Budgest cost of work performed,B = 25%*40000 = 10,000

Total BCWP = 50,000

3. Schedule Performance Index ,SPI =BCWP/ BCWS = EV/PV = 50,000/60,000 = 5/6 = 0.833

4. Actual Cost of work performed in w2,AC = 40,000

Cost Performance Index, CPI = BCWP/Actual cost = EV/AC =50,000/40000= 5/4 = 1.25


Related Solutions

describe a project list two task that may be performed in parallel and two tasks that...
describe a project list two task that may be performed in parallel and two tasks that need to be performed sequeooontially
discuss in details scheduled discard tasks
discuss in details scheduled discard tasks
Use Word to create a task list with a minimum of 25 tasks for the project...
Use Word to create a task list with a minimum of 25 tasks for the project plan. The tasks should be in the format of verb then noun. Deliverable headings should be nouns. The list should be a complete plan to build a local area network in an office.
Begin by creating a Java project with one class – Addition. Start with the class Addition...
Begin by creating a Java project with one class – Addition. Start with the class Addition as shown in Figure 12.2. This program uses dialog boxes for I/O to get two integers and display the result of adding them together. The program should run “as is”. Change the program so that it gets and adds two doubles instead of integers. When that is working get a third double using a dialog box. Add the three doubles together, and display the...
Make a small example that shows that a particular set of tasks can be scheduled by...
Make a small example that shows that a particular set of tasks can be scheduled by the ad hoc method and NOT by DM. short answer please
Think about how the structure of tasks affect leaders' behaviors. They are task autonomy, task feedback,...
Think about how the structure of tasks affect leaders' behaviors. They are task autonomy, task feedback, task structure, and task interdependence. It also sees most problems, as defined by Ronald Heifitz, as either technical or adaptive. Describe how you as a leader (or another leader who you've observed) used this analysis in effectively dealing with an organizational challenge. Which of the variables related to the problem's definition and how was it handled, either as a technical problem or an adaptive...
Task Task Time (seconds) Tasks that must Precede A 50 -- B 40 -- C 20...
Task Task Time (seconds) Tasks that must Precede A 50 -- B 40 -- C 20 A D 45 C E 20 C F 25 D G 10 E H 35 B,F,G The above tasks must be performed on an assembly line in the sequence and times specified. The workstation cycle time is 72 seconds. Using the longest task time to balance the assembly line, the first workstation include, the second workstation include , the third workstation include , and...
java code: adds a new regular task, delete a task , show all tasks, and show...
java code: adds a new regular task, delete a task , show all tasks, and show regular tasks, mark a task as important (possibly through ID), complete task, show all completed tasks, show important tasks. I also need a UML diagram for the code update: The "task" is like something in a to do list. example) task 1. name: get carrots important: no completed: yes. you can run my code as an example if needed
CHAPTER 2-3 2.14 A construction job is comprised of two tasks, which we will call ''task...
CHAPTER 2-3 2.14 A construction job is comprised of two tasks, which we will call ''task A" and "task B." The two tasks are initiated simultaneously and their completion times are uncertain. The entire construction job is completed as soon as both tasks are completed. The possible outcomes for the completion times of task A and task B, and the associated probabilities, are given in Table 2.28. TABLE 2.28 Probabilities of time to completion of tasks A and B. Time...
A patient with CD20 POSITIVE , non -Hodgkin lymphoma is scheduled to begin rituximab. The nurse...
A patient with CD20 POSITIVE , non -Hodgkin lymphoma is scheduled to begin rituximab. The nurse knows
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT