Question

In: Finance

Machine A: This project costs $10 million. The expected net cash flows are $4 million per...

Machine A: This project costs $10 million. The expected net cash flows are $4 million per year for 4 years, when is to be replaced. Machine B: It costs $15 million, and has expected cash flows of $3.5 per year for 8 years, when it will be replaced. The cost of capital is 10%. Machine prices are expected to stay steady as production efficiencies are expected to offset inflation. Evaluate these projects. a. Calculate NPV, IRR, Replacement Chain, and Equivalent Annual Annuity. b. Which project should be company accept?

Solutions

Expert Solution

NPV = PV of Cash Inflows - PV of Cash Outflows

Machine A:

Year CF (in M) PVF @10% Disc CF
0 $ -10.00 1.0000 $ -10.00
1 $      4.00 0.9091 $      3.64
2 $      4.00 0.8264 $      3.31
3 $      4.00 0.7513 $      3.01
4 $      4.00 0.6830 $      2.73
NPV

$      2.68

Machine B:

Year CF (in M) PVF @10% Disc CF
0 $ -15.00 1.0000 $ -15.00
1 $      3.50 0.9091 $      3.18
2 $      3.50 0.8264 $      2.89
3 $      3.50 0.7513 $      2.63
4 $      3.50 0.6830 $      2.39
5 $      3.50 0.6209 $      2.17
6 $      3.50 0.5645 $      1.98
7 $      3.50 0.5132 $      1.80
8 $      3.50 0.4665 $      1.63
NPV $      3.67

IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash Outflows.

Machine A:

Year CF PVF @21% Disc CF PVF @22% Disc CF
0 $ -10.00 1.0000 $ -10.00 1.0000 $ -10.00
1 $      4.00 0.8264 $      3.31 0.8197 $      3.28
2 $      4.00 0.6830 $      2.73 0.6719 $      2.69
3 $      4.00 0.5645 $      2.26 0.5507 $      2.20
4 $      4.00 0.4665 $      1.87 0.4514 $      1.81
NPV $      0.16 $    -0.03

IRR = Rate at which least +ve NPV + [ NPV at that rate / change in NPV due to 1% inc in disc rate ] * 1%

= 21% + [ 0.16 / 0.19 ] * 1%

= 21% + 0.86%

= 21.86%

Machine B:

Year CF PVF @16% Disc CF PVF @17% Disc CF
0 $ -15.00 1.0000 $ -15.00 1.0000 $ -15.00
1 $      3.50 0.8621 $      3.02 0.8547 $      2.99
2 $      3.50 0.7432 $      2.60 0.7305 $      2.56
3 $      3.50 0.6407 $      2.24 0.6244 $      2.19
4 $      3.50 0.5523 $      1.93 0.5337 $      1.87
5 $      3.50 0.4761 $      1.67 0.4561 $      1.60
6 $      3.50 0.4104 $      1.44 0.3898 $      1.36
7 $      3.50 0.3538 $      1.24 0.3332 $      1.17
8 $      3.50 0.3050 $      1.07 0.2848 $      1.00
NPV $      0.20 $    -0.27

IRR = Rate at which least +ve NPV + [ NPV at that rate / change in NPV due to 1% inc in disc rate ] * 1%

= 16 % + [ 0.20 / 0.48 ] * 1%

= 16% + 0.42%

= 16.42%

Equivalent Annual Annuity:

NPV / PVAF(r%,n)

Machine A:

Equivalent Annuity = NPV / PVAF (r%,n)

= $ 2.68 / PVAF (10%, 4)

= $ 2.68 / 3.1699

= $ 0.8455 M

Machine B:

Equivalent Annuity = NPV / PVAF (r%,n)

= $ 3.67 / PVAF (10%, 8)

= $ 3.67 / 5.3349

= $ 0.6879 M

Part B:

Machine A is selected as Equivalent Annuity CF is more .


Related Solutions

10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for...
10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $41,000 and its expected cash flows would be $8,550 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project L, since the NPVL > NPVS. c. Project S, since the...
swf is considering a project that is expected to generate real cash flows of $10 million...
swf is considering a project that is expected to generate real cash flows of $10 million at the end of each year for 5 years. the intial outlay/investment required is $25 million. a nominal discount rate of 9.2% is appropriate for the risk level. inflation is 5% 1. you are company's financial analyst. the CFO has asked you to calculate the NPV using a schedule of future nominal cash flows. 2. justify the NPV will remain the same while rearranging...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years. Project Q costs $30,000 and is expected to produce cash flows of $9,250 per year for five years. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?
A project has an initial cost of $40,000, expected net cash flows of $9,000 per year...
A project has an initial cost of $40,000, expected net cash flows of $9,000 per year for 7 years, and a cost of capital of 11% Calculate in excel NPV, IRR, PB, DPB?
A company project has an initial cost of $40,000, expected net cash flows of $9,000 per...
A company project has an initial cost of $40,000, expected net cash flows of $9,000 per year for 7 years. The company has a target capital structure of 10% short term debt at an interest rate of 6.0%, 50% long term debt at an interest rate of 9.0%, and 40% equity with a cost of 18%. The company’s tax rate is 28%. a. What is the WACC to be used when evaluating this project? b. What is the projects NPV,...
A project requires a $2,000 investment. The net cash flows are $350 per year for 10...
A project requires a $2,000 investment. The net cash flows are $350 per year for 10 years. The opportunity cost of capital (RA) is 12%. The company intends to finance the project with $1,000 of interest-bearing debt and $1,000 of equity. The interest rate is 8%. The corporate tax rate is equal to 30%. The company must repay the principal in equal annual installments over 5 years. a. Calculate the adjusted net present value (APV). b. Starting with your answer...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) modified internal rate of return (MIRR). The firm’s required rate of return is 14 percent. If the projects are independent, which project (s) should be selected? If...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
The Renn project costs $26,000, and its expected net cash inflows are $7,800 per year for...
The Renn project costs $26,000, and its expected net cash inflows are $7,800 per year for 8 years. What is the project's payback period? What is the project's net present value (NPV), profitability index (PI), and internal rate of return (IRR) assuming a cost of capital of 10%? Calculate the project's modified internal rate of return (MIRR) assuming a cost of capital of 10%. What is the payback period of the Renn project?
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Both Projects S and L, since both projects have NPV's > 0. c....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT