Question

In: Operations Management

PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers....

PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in weeks), predecessors, and costs included:

Activity   Normal Time (weeks)   Crashed Time (weeks)   Normal Cost   Crashed Cost   Predecessor(s)  
A 2 1 $1,350 $1,950 -
B 7 5 $1,250 $2,610 -
C 5 4 $800 $1,300 B
D 3 2 $2,100 $3,000 A
E 4 3 $630 $1,150 B
F 2 1 $560 $1,350 E
G 8 6 $550 $740 C, D, F

What is the critical path of the project?

A-D-G

B-C-G

B-E-F-G

If you wanted to shorten the overall duration of the project, which activity would you crash first?

G

B

C

E

What would be the weekly crashing cost of the activity you selected in the previous question? (Display your answer to two decimal places.)

   

Crash the project by 3 weeks. What is the total cost of crashing the project (just the additional cost, not total project cost)? (Display your answer to two decimal places.)

   

Solutions

Expert Solution

Based on the given data, we find the crash cost per week for each activity as shown below:

The formula for calculating crash cost per day is shown in the table.

Based on the predecessor relationship, we prepare the project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly LFT & LST are calculated during backward pass.

There are multiple paths in the diagram:

A-D-G

B-C-G

B-E-F-G

Out of the above paths, path B-E-F-G is the longest path and has 0 slack. Hence, this is the critical path.

To reduce project duration, we have to crash activities on the critical path first:

As seen from the above table, we start with crashing activities with minimum crash cost per week to have a minimum cost impact.

Step-1: We crash activity G as it has the lowest crash cost. We crash G by 2 weeks which is the maximum possible. Additional cost = No. of weeks crashed * crash cost per week = 2*95 = $190

Step-2: Next, we crash activity E as it has the lowest crash cost. We crash E by 1 week which is the maximum possible. Additional cost = No. of weeks crashed * crash cost per week = 1*520 = $520

Revised network diagram is shown below:

As seen from above, we have reduced project duration to 18 weeks from 21 weeks. We have crashed it by 3 weeks as required.

Total additional cost = Additional cost in Step-1 + Additional cost in Step-2 = 190 + 520 = $710

Hence, we get answers as:

Question: What is the critical path of the project? Answer: B-E-F-G

Question: If you wanted to shorten the overall duration of the project, which activity would you crash first?

Answer: G

Question: What would be the weekly crashing cost of the activity you selected in the previous question?

Answer: $95.00

Question: Crash the project by 3 weeks. What is the total cost of crashing the project (just the additional cost, not total project cost)?

Answer: $710

_______________________________________________________________________________________

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

The Boeing CEO recently predicted that a major US airline would go out of business before...
The Boeing CEO recently predicted that a major US airline would go out of business before the end of the year. Please analyze the change in demand and result that is occurring in the airline industry today. (a) Graph and explain this as if it were a perfectly competitive increasing cost industry, with the industry graph on the left and the individual firm on the right. (b) Have the industry start in long-run equilibrium (at points A and a) and...
Stanford Company has contracted to build for the City of New London a new courthouse. The...
Stanford Company has contracted to build for the City of New London a new courthouse. The estimated cost of the project is $6,000,000, and the contract price is $9,000,000. The courthouse took three years to complete as follows:                                                 2018                       2019                       2020 Costs to date                      $1,500,000           $4,000,000           $6,200,000 Cost to complete             $4,500,000           $2,200,000           $0 Amounts billed to date $1,400,000           $5,800,000           $9,000,000 Amounts collected to date                                              $1,300,000           $4,300,000           $9,000,000 Determine the gross profit to be recognized for                                          2018                          ...
Stanford Company has contracted to build for the City of New London a new courthouse. The...
Stanford Company has contracted to build for the City of New London a new courthouse. The estimated cost of the project is $6,000,000, and the contract price is $9,000,000. The courthouse took three years to complete as follows:                                                 2018                       2019                       2020 Costs to date                      $1,500,000           $4,000,000           $6,200,000 Cost to complete             $4,500,000           $2,200,000           $0 Amounts billed to date $1,400,000           $5,800,000           $9,000,000 Amounts collected to date                                              $1,300,000           $4,300,000           $9,000,000 Determine the gross profit to be recognized for                                          2018                          ...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of completion is July 1, 2023. The building cost is estimated to be $20,000,000 and will be billed at $24,000,000. The following data relate to the construction period: 2020 2021 2022 2023 Cost to date 5,500,000 10,000,000 13,500,000 20,000,000 Estimated cost to complete 14,500,000 10,000,000 6,500,000 -0- Progress billings to date 3,000,000 9,000,000 14,000,000 24,000,000 Cash...
The PM Computer Company makes build-to-order (BTO) computers at its distribution center year round. The following...
The PM Computer Company makes build-to-order (BTO) computers at its distribution center year round. The following table shows the average value (in $ millions) of component parts, work-in-process, and ?nished computers at the DC for the past four years. years 1 2 3 4 Component parts $20.5 27.8 30.8 37.3 Work-in-process 4.2 6.7 7.1 9.5 Finished computers 3.6 7.2 8.6 10.1 Cost of goods sold 226 345 517 680 a. Determine the number of inventory turns and the days of...
Why US Financial Institutions need to Manage Risk “and role of Federal government to build confidence...
Why US Financial Institutions need to Manage Risk “and role of Federal government to build confidence in financial institutions
The UAE government is going to build a bridge between two of its islands in the...
The UAE government is going to build a bridge between two of its islands in the Arabian Gulf Sea to allow the residences of these two islands to communicate with each other’s and with the rest of the country. The government will sign a long time contract with the biggest international company in this field to be responsible for this project. The government will pay an initial cost of 100,000,000 Dhs, a major re-design to fix any bugs in the...
OTR Trucking Company runs a fleet of​ long-haul trucks and has recently expanded into the​ Midwest,...
OTR Trucking Company runs a fleet of​ long-haul trucks and has recently expanded into the​ Midwest, where it has decided to build a maintenance facility. This project will require an initial cash outlay of $ 19.5million and will generate annual cash inflows of​$3.8million per year for Years 1 through 3. In Year​ 4, the project will provide a net negative cash flow of ​$4.5million due to anticipated expansion of and repairs to the facility. During Years 5 through​ 10, the...
Brown Oil Company transports gasoline to its distributors by truck.  The company recently contracted to supply gasoline...
Brown Oil Company transports gasoline to its distributors by truck.  The company recently contracted to supply gasoline distributors in southern Ohio, and it has $1,600,000 available to spend on the necessary expansion of its fleet of gasoline tank trucks (e.g. capital expenditures).   Three models of gasoline tank trucks are available:   Truck Model Monthly Truck Capacity (Gallons) Purchase Cost Monthly Operating Cost, including Depreciation Sub 100 75000 $200,000 $1,550 Oiler J 62500 $160,000 $1,425 Texan 30000 $100,000 $1,350 The company estimates that the...
(Calculating MIRR) OTR Trucking Company runs a fleet of​ long-haul trucks and has recently expanded into...
(Calculating MIRR) OTR Trucking Company runs a fleet of​ long-haul trucks and has recently expanded into the​ Midwest, where it has decided to build a maintenance facility. This project will require an initial cash outlay of $ 18.5 million and will generate annual cash inflows of ​$4.8 million per year for Years 1 through 3. In Year​ 4, the project will provide a net negative cash flow of ​$5.5 million due to anticipated expansion of and repairs to the facility....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT