Question

In: Operations Management

Table below contains information about an environmental clean-up project in the township of Hiles. Shorten the...

Table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.

Table 1 - Environmental Project Data

Activity

Normal Time (weeks)

Crash Time (weeks)

Cost to Crash

($ per week)

Immediate Predecessor(s)

A

7

6

200

None

B

12

9

250

None

C

7

6

250

A

D

6

5

300

A

E

1

1

-

B

F

1

1

-

C, D

G

3

1

200

D, E

H

3

2

350

F

I

2

2

-

G

Solutions

Expert Solution

Network Diagram:

Activity Normal Time Crash time Time can be decreased Cost to crash per week
A 7 6 1 200
B 12 9 3 250
C 7 6 1 250
D 6 5 1 300
E 1 1 0 --
F 1 1 0 --
G 3 1 2 200
H 3 2 1 350
I 2 2 0 --

In this project, there are two critical paths. So to shorten the project by three weeks we need to crash the activities on both paths simultaneously.

Step 1:

On Path A-C-F-H, min crashing cost is for A, while on path B-E-G-I min crashing cost is for G.

So we can crash the both activity A and G by 1 week.

Crashing Cost = 200 +200 = 400

Step 2:

Now, D is also become a critical activity.

Further, we can crash Activity G by 1 week, and simultaneously we can crash activity H by 1 wee.

Crashing Cost = 200 +350 = 550

Step 3:

Further, we can crash Activity B by 1 week, and simultaneously we need to crash Activity C and D (because both are on the critical path) by 1 week.

Crashing Cost = 250+ 250 +300 =800

Total Crashing Cost = 400 + 550 +800 = 1750


Related Solutions

The table below contains information about the production, costs and profits of a firm. The price...
The table below contains information about the production, costs and profits of a firm. The price faced by the firm is $40 per unit. There are 50 empty cells in the table. (a) Fill in all the empty cells. Output Total Fixed Costs Total Variable Costs Marginal Costs Average Variable Costs Average Fixed Costs Average Total Costs Price per unit Profits 0 12 1 12 50 50.0 50.0 -22.0 2 12 75 25.0 37.5 43.5 3 10.0 28.3 4 20.0...
Question 5 (25 marks) – ALL CALCULATIONS MUST BE SHOWN The table below contains information about...
Question 5 – ALL CALCULATIONS MUST BE SHOWN The table below contains information about weekly production and costs of a firm. Number of Workers Output (units) Marginal Product of Labour Fixed Cost (capital) Variable Cost (labour) Total Cost Marginal Costs Average Fixed Costs Average Variable Costs Average Total Costs 0 -- -- -- -- -- 1 330 $600 $300 2 375 $600 $1,200 3 1020 $600 $1,500 4 1260 $600 $1,200 5 150 $600 $2,100 6 1470 $600 $1,800 a....
The following table contains information related to the major activities of a research project. Use the...
The following table contains information related to the major activities of a research project. Use the information to do the following: a. Compute the expected duration, variance, and standard deviation for each activity b. What is the probability that the project finishes in less than 60 days? Activity Predecessor To Tm Tp A - 3 7 12 B A 8 11 17 C B 7 13 16 D B 7 10 13 E C 14 17 23 F D 12...
The table below contains economic cost information for aperfect competitor. Use it to answer the...
The table below contains economic cost information for a perfect competitor. Use it to answer the questions that follow. Q, ATC, AVC, and MC = quantity, average total cost, average variable cost, and marginal cost.QATCAVCMC10100.0080.00101195.4577.27501293.3376.67701392.3176.92801491.7977.50851591.6778.33901691.8879.38951792.3580.591001893.0681.941051993.9583.421102095.2585.25120What quantity maximizes profit when price = $101?Q = __What is the maximum profit when price = $101?Maximum profit = ___Would the maximum profit increase, decrease, or remain constant in the long run?The maximum profit would ____________________.Why?Would the firm produce output or shut down in the...
The table below contains the completed investment analysis for a certain property. Using the information in...
The table below contains the completed investment analysis for a certain property. Using the information in the table, What is the internal rate of return of the before-tax levered cash flows if the property is sold at the end of the 5th year?. Purchase Price $25 million Loan Amount 70% of purchase price Interest Rate 6% per year with monthly payments and compounding Amortization 25 years Year 1 2 3 4 5 Net Operating Income $2,000,000 $2,100,000 $2,205,000 $2,315,250 $2,431,013...
The table below contains information pertaining to the gasoline mileage for random samples of trains of...
The table below contains information pertaining to the gasoline mileage for random samples of trains of two different types X and Y. Assume their population standard deviations are known (as given) and the two distributions are normal. Brand X Brand Y Number of Trains    14 11 Mean mileage 20.04 24.03 Pop. St Dev. σ 2.18 1.76 A) Name and Find the 95% Confidence Interval for the difference of two pop. means (μx - μY). B) What can you conclude (if...
Regression Project: Data The table below contains the price, demand, and total cost data for the...
Regression Project: Data The table below contains the price, demand, and total cost data for the production of x widgets. Here p is the price (in dollars) of a widget for an annual demand of x widgets, and C is the annual total cost (in dollars) of producing x widgets per year. Demand x (widgets) Price p ($/widget) Total Cost C ($) 10 141 609 20 133 1103 30 126 1618 40 128 2109 50 113 2603 60 97 3111...
Using the information provided in the table below, find the probability of completing the project in...
Using the information provided in the table below, find the probability of completing the project in 46 weeks? Activity Immediate Predecessor(s) Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) A none 3 6 9 B A 3 5 7 C A 4 7 12 D B, C 4 8 10 E B, C 9 12 18 F D 5 10 13 G E 3 6 8 H F 1 5 12 I G 7 8...
Use the information in the table below for the following 5 questions. A capital investment project...
Use the information in the table below for the following 5 questions. A capital investment project is estimated to have the following after-tax cash flows, by year: 0 1 2 3 4 -$50,000 $15,000 $17,500 $17,500 $25,000 The company utilizes a discount rate of 20% to evaluate capital projects. You may have rounding errors in your calculations so choose the closest answer. Assume cash flows are received equally over the year. The NET PRESENT VALUE for the project shown above...
The table below contains information from a survey among 499 participants classified according to their age...
The table below contains information from a survey among 499 participants classified according to their age groups. The second column shows the percentage of obese people per age class among the study participants. The last column comes from a different study at the national level that shows the corresponding percentages of obese people in the same age classes in the USA. Perform a hypothesis test at the 5% significance level to determine whether the survey participants are a representative sample...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT