Question

In: Finance

Job-Order Costing - Using the weighted procedure method setting rates, calculate the relative value and cost...

Job-Order Costing - Using the weighted procedure method setting rates, calculate the relative value and cost per procedure for the following lab procedures. Assume total lab cost of $2,500,000 and average hourly wage of $20. Round your answer to the nearest whole dollar.

Procedure

Projected Volume

Labor Minutes

Supply Expense

A

5100

15

0.95

B

5700

13

0.75

C

4600

11

0.70

D

6100

10

0.65

E

4600

12

0.90

Solutions

Expert Solution

Procedure Projected Volume Labor Minutes Supply Expense Actual Production Time required to Production in Units Labour Cost Lab Cost Total Cost Cost per procedure
a b c d=a X c e= d/b f= e X 20 per Hour g= d * 2500000/20445 h=g+f '=h/d
A 5100 15 0.95 4845 323                            6,460.00                         592,443.14        598,903.14             123.61
B 5700 13 0.75 4275 329                            6,576.92                         522,743.95        529,320.87             123.82
C 4600 11 0.7 3220 293                            5,854.55                         393,739.30        399,593.85             124.10
D 6100 10 0.65 3965 397                            7,930.00                         484,837.37        492,767.37             124.28
E 4600 12 0.9 4140 345                            6,900.00                         506,236.24        513,136.24             123.95
20445                          33,721.47                      2,500,000.00    2,533,721.47

Related Solutions

Using the Weighted Average Method of process costing, what is the dollar value of inventory transferred...
Using the Weighted Average Method of process costing, what is the dollar value of inventory transferred out of the department? Please round rates to $0.01 and inventory amounts to $1. units percent complete cost WIP, beginning 3,053 44 % 37,486 Started 274,793 2,603,144 WIP, ending 1,270 50
Job Order Costing: Define job order costing. Compare and contrast job order costing with process costing....
Job Order Costing: Define job order costing. Compare and contrast job order costing with process costing. Trace the flow of costs through a job order costing system. Discuss manufacturing overhead and how it is applied. Why is the manufacturing overhead account adjusted at the end of the period?
When is by-product/scrap cost considered in setting the predetermined overhead rate in a job order costing system? When is cost not considered?
When is by-product/scrap cost considered in setting the predetermined overhead rate in a job order costing system? When is cost not considered?
Lafarge Machine Works collects its cost data by the job order cost accumulation procedure. For Job...
Lafarge Machine Works collects its cost data by the job order cost accumulation procedure. For Job 100, the following data are available: Direct Materials Direct Labor 3/14 Issued $ 1,100 Week of Mar 20 200 hrs @ $6.10/hr 3/20 Issued      625 Week of Mar. 26 140 hrs @ $7.00/hr 3/22 Issued   450 Factory overhead applied at the rate of $3.50 per direct labor hour. Lafarge Machine WorksJob Order Cost Sheet–Job 100 Direct materials Direct labor Applied factory overhead Date...
Compare and contrast the job-order costing method with the activity-based costing method. If you had your...
Compare and contrast the job-order costing method with the activity-based costing method. If you had your own business which would you prefer and why?
Job-order costing:
Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor-hour, and 70,000 direct labor-hours. The company has provided the following data concerning Job T498 which was recently completed: Number of units in the job 40 Total direct labor-hours 80 Direct materials $ 950 Direct labor...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $108,000 Number of moves 4,500 Engineering 165,000 Number of change orders 10,000 Other overhead 263,200 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,370 $6,280 $0 Direct materials $10,510 $12,350 $16,190 Direct labor $16,040 $12,240 $24,030 Machine hours 500 290 980 Overhead is applied to jobs at the rate of $17 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT