In: Operations Management
1)Which one of the following integration management processes is responsible for implementing process improvement activities?
A.Direct and Manage Project Work
B. Monitor and Control Project Work
C.Develop Project Charter
D Perform Integrated Change Control
2.Which of the following statements is false about the Executing
Process Group?
A.The process group usually takes the most time
and resources.
B.The processes in this process group measure and analyze the process and performance of the project, ensure that the plan is working, identify any areas in which changes to
the plan are required, and initiate the corresponding changes.
C.Corrective actions, preventative actions, and defect repairs are implemented in the process group.
DThis process group consists of processes to complete the work defined in the project management plan and ultimately satisfies the project specifications and objectives.
3) You identified all people who would be impacted by the project and documented relevant information regarding their interests, expectation, involvement, and influence on the
project success in a stakeholder register. The stakeholder register will not be used as an input to which of the following processes?
A.Collect Requirement and Identify Risks
B.Plan Risk Management and Plan Resource Management
C.Plan Quality Management and Plan Communications Management
D.Develop Project Charter and Perform Integrated Change Control
4,You are in the process of evaluating and monitoring overall stakeholder relationships and ensuring stakeholders' appropriate engagement in the project by adjusting plans and
strategies as required. The Work Performance Data that is an input to this Monitor Stakeholder Engagement process usually comes from:
A.Validate Scope
BPerform Integrated Change
C.Monitor and Control Project Work
D.Direct and Manage Project Work
Answer of question 1- (B) Monitor and Control Project Work
Explanation - because the Monitor and Control Project Work is process used to monitor that project is correctly going on or not.It is the part of the integration management process.Monitor and Control Project Work help the Project management plan, during the monitoring and controlling process if any risk is found or might affect the project in the future.it will change the process or improve the process.So, that defect must be fixed.
Answer of question 2- (B) The processes in the monitoring & controlling process group track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project to ensure that the plan is working by identify many areas in which changes to the plan are required and initiate the corresponding changes.
Explanation - The Executing Process Group is a place where all the project work is done effectively and efficiently.So, that project is stayed in the target and achieve the goal of the project.It is time taking process.where we analyze the defect and take a preventive action to repair the defect in the project.In the project management plan the work of Executing Process Group is to complete the work by satisfies the project specifications and objectives.
Answer of question 3 - (B) Plan Risk Management and Plan Resource Management.
Explanation - The stakeholder register always used to identify the risk in th project and also stakeholder help in the project to plan to how quality of the project will manage by communicating.
Answer of question 4 - (A) Validate Scope
Explanation - Validate Scope is the process of formalizing acceptance of the completed project deliveries.The Work Performance Data that is an input to this Monitor Stakeholder Engagement process usually comes from Validate Scope