A wastewater treatment plant with activated-sludge process
treats wastewater for 120,000 m3/d. The effluent standard for both
BOD and TSS is 20 mg/L. Influent TSS concentration is 450 mg/L and
influent BOD concentration is 220 mg/L. MLSS concentration is 3500
mg/L (Assume no nitrification and temperature is 20°C). Determine:
(20 pts) (a) Influent BOD and TSS concentration to the aeration
tank if the treatment efficiencies in primary clarifier are 30% and
70% for BOD and TSS, respectively. (b) Determine sludge production
as kg TSS/d (c) What is the design volume and retention time of the
aeration basin (m3)? (d) Determine the F/M ratio in units of kg
BOD5/kg MLVSS-day.
(According to your design you can assume some parameters i.e SRT
but do not forget to check both your assumptions and your results
are in the desirable design conditions)
In: Civil Engineering
An anaerobic stabilization pond is designed for a residential area have a population of 8000 (wastewater production is 225 L/day-capita). Pond is designed as a facultative pond and maturation pond in series. The BOD of raw sewage is 180 mg/L, the influent FC is 106 FC/100 mL and the operating temperature is 12°C. The effluent BOD concentration should be lower than 20 mg/L. Design completely both ponds using the relevant information and assumptions to provide an efficient design.
In: Civil Engineering
Design a reinforced concrete steel rectangular tie column with ACI standards, total LL = 14.0625 kips, total DL = 18.95625kips, cross-section 12in by 12 in, Hight of column 12ft. Show all the steps and which table used. Assume the information which is not given with justifications. Show drawing as well. If the high is not suitable you can change it.
In: Civil Engineering
In: Civil Engineering
civil engineering cv and cover letter sample for undergraduate students (no experience)
In: Civil Engineering
With regard to the queueing system, please answer the following questions:
a. Identify 4 (four) measures of performance of the
queueing system.
b. Which measure is considered the most important for
the service company? Why?
c. Referring to the Dupit case as discussed in class,
please state at least 2 (two) recommendations that can effectively
shorten the waiting time in the queue, Wq. How do you choose the
best recommendation? Which factors do you consider? Explain.
In: Civil Engineering
Panama Canal, which took 10 years to build and opened
in 1914, handles 5% of world trade.
The government of Panama recently initiated a project to expand the
canal in order to
increase its share of global shipment, boost job creation,
stimulate economic growth and
boost foreign exchange and tax revenue. Among other things, the
expansion project involves
the building of a third set of locks that can accommodate mega
cargo ships carrying up to
12,000 containers; at the moment the biggest ships that can
navigate the canal carry 5,000
containers. The work was awarded to GUPC (Grupo Unidos por el
Canal), a consortium of
international construction firms led by Sacyr of Spain. Others are
Impregilo of Italy, Belgian
firm Jan De Nul and Constructora Urbana, a Panamanian firm. Work
began in 2009 and was
expected to be completed in September 2014 at a total cost of $3.2
billion, according to the
contract.
As of January 2014, the work was already nine months behind
schedule (with project
completion now expected in June 2015) and a cost overrun of $1.6
billion had been incurred
as of January 2013. According to GUPC, the cost overrun and
schedule slippage were due to
“many and varied unforeseen costs which came up during these
gigantic works... They are
technical matters, questions over cement ingredients, geotechnical
matters, geological
questions, taxes matters, financial matters, labour issues and
weather conditions". However,
Panama Canal Authority (APC), the Panamanian state-owned company
responsible for
managing the canal and overseeing the project, attributed the
problem partly to a delay of
four months shortly after the project began as a result of GUPC’s
attempt to use low-quality
cement, which was rejected by the canal authority.
Since January 2013, there had been an escalating dispute over who
should bear the additional
cost of $1.6 billion. The position of APC was that GUPC should
respect the existing contract
by absorbing the additional cost, arguing that the cost overrun was
due to events that were
"normal" in such a construction project. But GUPC said the cost
overrun was due to
"unforeseeable" circumstances and delays caused by APC. On December
30, 2013, the
dispute had become so bad that GUPC threatened to halt work unless
the Panamanian
government paid the money within 21 days. In response, the
president of Panama, President
Ricardo Martinelli, threatened to go to Europe to demand that the
governments of the
member firms of GUPC “take moral responsibility for what happened,
because it is not
possible that a company puts such a huge extra charge on expansion
work."
News of the suspension threat sent Sacyr’s shares plunging by more
than 18% on the Madrid
stock exchange. On January 4th, 2014, Spain's minister for public
works, Ana Pastor, flew to
Panama for an emergency meeting with President Martinelli and also
met all the parties
involved to try to resolve the impasse. According to a spokesperson
for Spain's foreign
ministry, "Panama is a country that is close and friendly towards
Spain, and we share the
desire and interest to find a solution as soon as possible".
Spain's ambassador to Panama,
Jesus Silva, added that all stood to lose out if the contract fell
through.
Question
What was the justification (business case) for the project from the
perspective of the
government of Panama? And according to GUPC, what was the estimate
at completion? Justify your answer.
In: Civil Engineering
Two pipes are connected in parallel, the characteristics of pipe A are D = 0.2m, L = 1000m, λ(lamda) = 0.014 and of pipe B are D = 0.25m, L = 2000m, λ (lamda) = 0.017; what will be the total discharge if the head loss in the pipe A is 14.3 m? Neglect the local losses.
Lütfen birini seçin:
A. 0.133 m3/s
B. 0.093 m3/s
C. 0.106 m3/s
D. 0.079 m3/s
In: Civil Engineering
Panama Canal, which took 10 years to build and opened
in 1914, handles 5% of world trade.
The government of Panama recently initiated a project to expand the
canal in order to
increase its share of global shipment, boost job creation,
stimulate economic growth and
boost foreign exchange and tax revenue. Among other things, the
expansion project involves
the building of a third set of locks that can accommodate mega
cargo ships carrying up to
12,000 containers; at the moment the biggest ships that can
navigate the canal carry 5,000
containers. The work was awarded to GUPC (Grupo Unidos por el
Canal), a consortium of
international construction firms led by Sacyr of Spain. Others are
Impregilo of Italy, Belgian
firm Jan De Nul and Constructora Urbana, a Panamanian firm. Work
began in 2009 and was
expected to be completed in September 2014 at a total cost of $3.2
billion, according to the
contract.
As of January 2014, the work was already nine months behind
schedule (with project
completion now expected in June 2015) and a cost overrun of $1.6
billion had been incurred
as of January 2013. According to GUPC, the cost overrun and
schedule slippage were due to
“many and varied unforeseen costs which came up during these
gigantic works... They are
technical matters, questions over cement ingredients, geotechnical
matters, geological
questions, taxes matters, financial matters, labour issues and
weather conditions". However,
Panama Canal Authority (APC), the Panamanian state-owned company
responsible for
managing the canal and overseeing the project, attributed the
problem partly to a delay of
four months shortly after the project began as a result of GUPC’s
attempt to use low-quality
cement, which was rejected by the canal authority.
Since January 2013, there had been an escalating dispute over who
should bear the additional
cost of $1.6 billion. The position of APC was that GUPC should
respect the existing contract
by absorbing the additional cost, arguing that the cost overrun was
due to events that were
"normal" in such a construction project. But GUPC said the cost
overrun was due to
"unforeseeable" circumstances and delays caused by APC. On December
30, 2013, the
dispute had become so bad that GUPC threatened to halt work unless
the Panamanian
government paid the money within 21 days. In response, the
president of Panama, President
Ricardo Martinelli, threatened to go to Europe to demand that the
governments of the
member firms of GUPC “take moral responsibility for what happened,
because it is not
possible that a company puts such a huge extra charge on expansion
work."
News of the suspension threat sent Sacyr’s shares plunging by more
than 18% on the Madrid
stock exchange. On January 4th, 2014, Spain's minister for public
works, Ana Pastor, flew to
Panama for an emergency meeting with President Martinelli and also
met all the parties
involved to try to resolve the impasse. According to a spokesperson
for Spain's foreign
ministry, "Panama is a country that is close and friendly towards
Spain, and we share the
desire and interest to find a solution as soon as possible".
Spain's ambassador to Panama,
Jesus Silva, added that all stood to lose out if the contract fell
through.
Question
Explain the main issue in dispute, the disputants involved, and why
this dispute was or
may be related to the following aspects of the project:
i. Project Scope
ii. Project Quality
iii. Project Schedule
iv. Project Risks
v. Project Procurement
In: Civil Engineering
A vertical sag curve connects two tangents with grades -3% and
+2% with the design speed of
100 km/h.
(a) Calculate the available sight distance and the length of the
vertical curve using the minimum
flatness of curve that will satisfy the headlight criterion during
dark conditions. Assume the
height of the headlight above the pavement is 0.6 m and the angle
of the light beam upward
from the axis of beam is 1.
(a) Assuming that the length of the vertical curve is 75 m,
calculate the available sight distance
and the maximum design speed (check for the requirements of i)
minimum flatness of curve
for headlight and comfort criteria and ii) minimum stopping sight
distance for one-way road.
Assume 2.5 s for driver’s perception and reaction time.
In: Civil Engineering
In a laboratory work a rigid bucket with a diameter of 1 ft and
height of 1.25 ft was filled with loose aggregate. The weight of
aggregate was recorded to be 110 lb and its specific gravity was
found to be 2.68. Given the above data, calculate (a) the bulk
density of the aggregate and (b) the void content of the aggregate
sample.
In: Civil Engineering
Discuss why air-entrained concrete mixtures require
lower water-to-cement ratio in comparison with non-air-entrained
mixtures.
Discuss the importance of the slump test for fresh
concrete.
In: Civil Engineering
What were the major developments in literature and are in the 14th century? Provide specific examples. How did they contrast to earlier literature and art of the Middle ages?
In: Civil Engineering
Discuss why air-entrained concrete mixtures require
lower water-to-cement ratio in comparison with non-air-entrained
mixtures.
Discuss the importance of the slump test for fresh
concrete.
In: Civil Engineering
Choose the correct answer:
1- The stopping sight distance depends upon:
a) design speed, driver perception & reaction time, vehicle
acceleration rate and road slope
b) design speed, vehicle length, vehicle acceleration rate and road
width
c) vehicle length, vehicle width, vehicle speed and road
slope
d) wind speed, road slope, road curvature and side friction
factor
none of the above
2- The superelevation rate of a highway has a design speed of
100kph, radius of 393.7m and side friction
factor of 0.12 is:
a) 4%
b) 6%
c) 8%
d) 10%
e) none of the above
3- Camber in the road cross-section is generally provided
for:
a) counteracting the centrifugal force
b) effective drainage
c) having proper sight distance
d) dividing the carriageway
e) none of the above
4- The highway geometric design can be well presented by:
a) longitudinal profile only
b) plan only
c) cross-section elements only
d) all of the above
e) none of the above
5- The length of a vertical curve formed by two gradients +4% and
-3% with a rate of vertical curvature of
17 is:
a) 119m
b) 139m
c) 159m
d) 179m
e) none of the above
6- For the movement of vehicles at an intersection of two roads,
without any interference, the type of grade
separator generally preferred to, is:
a) trumpet
b) cloverleaf
c) partial cloverleaf
d) diamond
e) none of the above
7- The minimum desirable longitudinal slope required for drainage
purposes is:
a) 0.03%
b) 0.30%
c) 1.30%
d) 2.30%
e) none of the above
8- Raising of outer edge of a road with respect to inner edge, is
known:
a) widening
b) excavating
c) filling
d) grading
e) none of the above
9- In ice or snow conditions, the maximum limit of the
superelevation rate should be:
a) not changed
b) decreased
c) increased
d) 20%
e) 2%
10- The highest point on a vertical symmetrical curve lies in the
middle of the curve when:
a) the left grade is greater than the right grade
b) the left grade is smaller than the right grade
c) the left grade equals the right grade
d) none of the above
e) all of the above
In: Civil Engineering