Questions
A wastewater treatment plant with activated-sludge process treats wastewater for 120,000 m3/d. The effluent standard for...

A wastewater treatment plant with activated-sludge process treats wastewater for 120,000 m3/d. The effluent standard for both BOD and TSS is 20 mg/L. Influent TSS concentration is 450 mg/L and influent BOD concentration is 220 mg/L. MLSS concentration is 3500 mg/L (Assume no nitrification and temperature is 20°C). Determine: (20 pts) (a) Influent BOD and TSS concentration to the aeration tank if the treatment efficiencies in primary clarifier are 30% and 70% for BOD and TSS, respectively. (b) Determine sludge production as kg TSS/d (c) What is the design volume and retention time of the aeration basin (m3)? (d) Determine the F/M ratio in units of kg BOD5/kg MLVSS-day.
(According to your design you can assume some parameters i.e SRT but do not forget to check both your assumptions and your results are in the desirable design conditions)

In: Civil Engineering

An anaerobic stabilization pond is designed for a residential area have a population of 8000 (wastewater...

An anaerobic stabilization pond is designed for a residential area have a population of 8000 (wastewater production is 225 L/day-capita). Pond is designed as a facultative pond and maturation pond in series. The BOD of raw sewage is 180 mg/L, the influent FC is 106 FC/100 mL and the operating temperature is 12°C. The effluent BOD concentration should be lower than 20 mg/L. Design completely both ponds using the relevant information and assumptions to provide an efficient design.

In: Civil Engineering

Design a reinforced concrete steel rectangular tie column with ACI standards, total LL = 14.0625 kips,...

Design a reinforced concrete steel rectangular tie column with ACI standards, total LL = 14.0625 kips, total DL = 18.95625kips, cross-section 12in by 12 in, Hight of column 12ft. Show all the steps and which table used. Assume the information which is not given with justifications. Show drawing as well. If the high is not suitable you can change it.

In: Civil Engineering

Determine the nominal concrete cover for a simply supported beam with exposure condition XC4. The concrete...

Determine the nominal concrete cover for a simply supported beam with exposure condition XC4. The concrete strength is 25MPa, the diameter of tension reinforcement is 32mm, diameter of shear link is 10mm, design working life is 50 years and the quality control is normal.

In: Civil Engineering

civil engineering cv and cover letter sample for undergraduate students (no experience)

civil engineering cv and cover letter sample for undergraduate students (no experience)

In: Civil Engineering

With regard to the queueing system, please answer the following questions: a.   Identify 4 (four) measures...

With regard to the queueing system, please answer the following questions:

a.   Identify 4 (four) measures of performance of the queueing system.
b.   Which measure is considered the most important for the service company? Why?
c.   Referring to the Dupit case as discussed in class, please state at least 2 (two) recommendations that can effectively shorten the waiting time in the queue, Wq. How do you choose the best recommendation? Which factors do you consider? Explain.

In: Civil Engineering

Panama Canal, which took 10 years to build and opened in 1914, handles 5% of world...

Panama Canal, which took 10 years to build and opened in 1914, handles 5% of world trade.
The government of Panama recently initiated a project to expand the canal in order to
increase its share of global shipment, boost job creation, stimulate economic growth and
boost foreign exchange and tax revenue. Among other things, the expansion project involves
the building of a third set of locks that can accommodate mega cargo ships carrying up to
12,000 containers; at the moment the biggest ships that can navigate the canal carry 5,000
containers. The work was awarded to GUPC (Grupo Unidos por el Canal), a consortium of
international construction firms led by Sacyr of Spain. Others are Impregilo of Italy, Belgian
firm Jan De Nul and Constructora Urbana, a Panamanian firm. Work began in 2009 and was
expected to be completed in September 2014 at a total cost of $3.2 billion, according to the
contract.
As of January 2014, the work was already nine months behind schedule (with project
completion now expected in June 2015) and a cost overrun of $1.6 billion had been incurred
as of January 2013. According to GUPC, the cost overrun and schedule slippage were due to
“many and varied unforeseen costs which came up during these gigantic works... They are
technical matters, questions over cement ingredients, geotechnical matters, geological
questions, taxes matters, financial matters, labour issues and weather conditions". However,
Panama Canal Authority (APC), the Panamanian state-owned company responsible for
managing the canal and overseeing the project, attributed the problem partly to a delay of
four months shortly after the project began as a result of GUPC’s attempt to use low-quality
cement, which was rejected by the canal authority.
Since January 2013, there had been an escalating dispute over who should bear the additional
cost of $1.6 billion. The position of APC was that GUPC should respect the existing contract
by absorbing the additional cost, arguing that the cost overrun was due to events that were
"normal" in such a construction project. But GUPC said the cost overrun was due to
"unforeseeable" circumstances and delays caused by APC. On December 30, 2013, the
dispute had become so bad that GUPC threatened to halt work unless the Panamanian
government paid the money within 21 days. In response, the president of Panama, President
Ricardo Martinelli, threatened to go to Europe to demand that the governments of the
member firms of GUPC “take moral responsibility for what happened, because it is not
possible that a company puts such a huge extra charge on expansion work."
News of the suspension threat sent Sacyr’s shares plunging by more than 18% on the Madrid
stock exchange. On January 4th, 2014, Spain's minister for public works, Ana Pastor, flew to
Panama for an emergency meeting with President Martinelli and also met all the parties
involved to try to resolve the impasse. According to a spokesperson for Spain's foreign
ministry, "Panama is a country that is close and friendly towards Spain, and we share the
desire and interest to find a solution as soon as possible". Spain's ambassador to Panama,
Jesus Silva, added that all stood to lose out if the contract fell through.
Question
What was the justification (business case) for the project from the perspective of the
government of Panama? And according to GUPC, what was the estimate at completion? Justify your answer.

In: Civil Engineering

Two pipes are connected in parallel, the characteristics of pipe A are D = 0.2m, L...

Two pipes are connected in parallel, the characteristics of pipe A are D = 0.2m, L = 1000m, λ(lamda) = 0.014 and of pipe B are D = 0.25m, L = 2000m, λ (lamda) = 0.017; what will be the total discharge if the head loss in the pipe A is 14.3 m? Neglect the local losses.

Lütfen birini seçin:

A. 0.133 m3/s

B. 0.093 m3/s

C. 0.106 m3/s

D. 0.079 m3/s

In: Civil Engineering

Panama Canal, which took 10 years to build and opened in 1914, handles 5% of world...

Panama Canal, which took 10 years to build and opened in 1914, handles 5% of world trade.
The government of Panama recently initiated a project to expand the canal in order to
increase its share of global shipment, boost job creation, stimulate economic growth and
boost foreign exchange and tax revenue. Among other things, the expansion project involves
the building of a third set of locks that can accommodate mega cargo ships carrying up to
12,000 containers; at the moment the biggest ships that can navigate the canal carry 5,000
containers. The work was awarded to GUPC (Grupo Unidos por el Canal), a consortium of
international construction firms led by Sacyr of Spain. Others are Impregilo of Italy, Belgian
firm Jan De Nul and Constructora Urbana, a Panamanian firm. Work began in 2009 and was
expected to be completed in September 2014 at a total cost of $3.2 billion, according to the
contract.
As of January 2014, the work was already nine months behind schedule (with project
completion now expected in June 2015) and a cost overrun of $1.6 billion had been incurred
as of January 2013. According to GUPC, the cost overrun and schedule slippage were due to
“many and varied unforeseen costs which came up during these gigantic works... They are
technical matters, questions over cement ingredients, geotechnical matters, geological
questions, taxes matters, financial matters, labour issues and weather conditions". However,
Panama Canal Authority (APC), the Panamanian state-owned company responsible for
managing the canal and overseeing the project, attributed the problem partly to a delay of
four months shortly after the project began as a result of GUPC’s attempt to use low-quality
cement, which was rejected by the canal authority.
Since January 2013, there had been an escalating dispute over who should bear the additional
cost of $1.6 billion. The position of APC was that GUPC should respect the existing contract
by absorbing the additional cost, arguing that the cost overrun was due to events that were
"normal" in such a construction project. But GUPC said the cost overrun was due to
"unforeseeable" circumstances and delays caused by APC. On December 30, 2013, the
dispute had become so bad that GUPC threatened to halt work unless the Panamanian
government paid the money within 21 days. In response, the president of Panama, President
Ricardo Martinelli, threatened to go to Europe to demand that the governments of the
member firms of GUPC “take moral responsibility for what happened, because it is not
possible that a company puts such a huge extra charge on expansion work."
News of the suspension threat sent Sacyr’s shares plunging by more than 18% on the Madrid
stock exchange. On January 4th, 2014, Spain's minister for public works, Ana Pastor, flew to
Panama for an emergency meeting with President Martinelli and also met all the parties
involved to try to resolve the impasse. According to a spokesperson for Spain's foreign
ministry, "Panama is a country that is close and friendly towards Spain, and we share the
desire and interest to find a solution as soon as possible". Spain's ambassador to Panama,
Jesus Silva, added that all stood to lose out if the contract fell through.

Question
Explain the main issue in dispute, the disputants involved, and why this dispute was or
may be related to the following aspects of the project:
i. Project Scope
ii. Project Quality
iii. Project Schedule
iv. Project Risks
v. Project Procurement

In: Civil Engineering

A vertical sag curve connects two tangents with grades -3% and +2% with the design speed...

A vertical sag curve connects two tangents with grades -3% and +2% with the design speed of
100 km/h.
(a) Calculate the available sight distance and the length of the vertical curve using the minimum
flatness of curve that will satisfy the headlight criterion during dark conditions. Assume the
height of the headlight above the pavement is 0.6 m and the angle of the light beam upward
from the axis of beam is 1.
(a) Assuming that the length of the vertical curve is 75 m, calculate the available sight distance
and the maximum design speed (check for the requirements of i) minimum flatness of curve
for headlight and comfort criteria and ii) minimum stopping sight distance for one-way road.
Assume 2.5 s for driver’s perception and reaction time.

In: Civil Engineering

In a laboratory work a rigid bucket with a diameter of 1 ft and height of...

In a laboratory work a rigid bucket with a diameter of 1 ft and height of 1.25 ft was filled with loose aggregate. The weight of aggregate was recorded to be 110 lb and its specific gravity was found to be 2.68. Given the above data, calculate (a) the bulk density of the aggregate and (b) the void content of the aggregate sample.

In: Civil Engineering

Discuss why air-entrained concrete mixtures require lower water-to-cement ratio in comparison with non-air-entrained mixtures. Discuss the...

Discuss why air-entrained concrete mixtures require lower water-to-cement ratio in comparison with non-air-entrained mixtures.




Discuss the importance of the slump test for fresh concrete.

In: Civil Engineering

What were the major developments in literature and are in the 14th century?  Provide specific examples.  How did...

What were the major developments in literature and are in the 14th century?  Provide specific examples.  How did they contrast to earlier literature and art of the Middle ages?

In: Civil Engineering

Discuss why air-entrained concrete mixtures require lower water-to-cement ratio in comparison with non-air-entrained mixtures. Discuss the...

Discuss why air-entrained concrete mixtures require lower water-to-cement ratio in comparison with non-air-entrained mixtures.




Discuss the importance of the slump test for fresh concrete.

In: Civil Engineering

Choose the correct answer: 1- The stopping sight distance depends upon: a) design speed, driver perception...

Choose the correct answer:
1- The stopping sight distance depends upon:
a) design speed, driver perception & reaction time, vehicle acceleration rate and road slope
b) design speed, vehicle length, vehicle acceleration rate and road width
c) vehicle length, vehicle width, vehicle speed and road slope
d) wind speed, road slope, road curvature and side friction factor
none of the above
2- The superelevation rate of a highway has a design speed of 100kph, radius of 393.7m and side friction
factor of 0.12 is:
a) 4%
b) 6%
c) 8%
d) 10%
e) none of the above
3- Camber in the road cross-section is generally provided for:
a) counteracting the centrifugal force
b) effective drainage
c) having proper sight distance
d) dividing the carriageway
e) none of the above
4- The highway geometric design can be well presented by:
a) longitudinal profile only

b) plan only
c) cross-section elements only
d) all of the above
e) none of the above
5- The length of a vertical curve formed by two gradients +4% and -3% with a rate of vertical curvature of
17 is:
a) 119m
b) 139m
c) 159m
d) 179m
e) none of the above
6- For the movement of vehicles at an intersection of two roads, without any interference, the type of grade
separator generally preferred to, is:
a) trumpet
b) cloverleaf
c) partial cloverleaf
d) diamond
e) none of the above
7- The minimum desirable longitudinal slope required for drainage purposes is:
a) 0.03%
b) 0.30%
c) 1.30%
d) 2.30%
e) none of the above
8- Raising of outer edge of a road with respect to inner edge, is known:
a) widening
b) excavating
c) filling
d) grading
e) none of the above

9- In ice or snow conditions, the maximum limit of the superelevation rate should be:
a) not changed
b) decreased
c) increased
d) 20%
e) 2%
10- The highest point on a vertical symmetrical curve lies in the middle of the curve when:
a) the left grade is greater than the right grade
b) the left grade is smaller than the right grade
c) the left grade equals the right grade
d) none of the above
e) all of the above

In: Civil Engineering