In: Finance
Blue Eagle Recycling has a weighted-average cost of capital of 7.27 percent and is evaluating two projects: A and B. Project A involves an initial investment of 5,062 dollars and an expected cash flow of 7,745 dollars in 8 years. Project A is considered more risky than an average-risk project at Blue Eagle Recycling, such that the appropriate discount rate for it is 1.1 percentage points different than the discount rate used for an average-risk project at Blue Eagle Recycling. The internal rate of return for project A is 5.46 percent. Project B involves an initial investment of 5,615 dollars and an expected cash flow of 7,861 dollars in 9 years. Project B is considered less risky than an average-risk project at Blue Eagle Recycling, such that the appropriate discount rate for it is 0.95 percentage points different than the discount rate used for an average-risk project at Blue Eagle Recycling. The internal rate of return for project B is 3.81 percent. What is X if X equals the NPV of project A plus the NPV of project B?
Solution) For Project A:
Initial Investment = $5,062
Expected cash flow in 8 years = $7,745
Weighted-average cost of capital of company = 7.27%
Since, Project A is more risky than an average-risk project of the company, thus, the appropriate discount rate for it is 1.1 percentage points higher than the discount rate used for an average-risk project of the company.
Thus, discouint rate for project A = 7.27% + 1.1% = 8.37%
Net Present Value of project A = Present value of future cash flow - Initial Investment
Present Value = Future Cash Flow/(1 + discount rate)^n
= 7,745/(1 + 8.37%)^8 - 5,062
= 4,071.447 - 5,062
= -$990.5525
For Project B:
Initial Investment = $5,615
Expected cash flow in 9 years = $7,861
Weighted-average cost of capital of company = 7.27%
Since, Project B is less risky than an average-risk project of the company, thus, the appropriate discount rate for it is 0.95 percentage points lower than the discount rate used for an average-risk project of the company.
Thus, discouint rate for project B = 7.27% - 0.95% = 6.32%
Net Present Value of project B = Present value of future cash flow - Initial Investment
Present Value = Future Cash Flow/(1 + discount rate)^n
= 7,861/(1 + 6.32%)^9 - 5,615
= 4,528.382 - 5,615
= -$1,086.618
X = Net Present Value of project A + Net Present Value of project B
X = - 990.5525 - 1,086.618
X = -$2,077.17
Please comment in case of any doubts or clarifications. Please Thumbs Up!!