In: Finance
Violet Sky Consulting has a weighted-average cost of capital of 9.46 percent and is evaluating two projects: A and B. Project A involves an initial investment of 6,723 dollars and an expected cash flow of 9,748 dollars in 8 years. Project A is considered more risky than an average-risk project at Violet Sky Consulting, such that the appropriate discount rate for it is 1.21 percentage points different than the discount rate used for an average-risk project at Violet Sky Consulting. The internal rate of return for project A is 4.75 percent. Project B involves an initial investment of 4,242 dollars and an expected cash flow of 7,211 dollars in 9 years. Project B is considered less risky than an average-risk project at Violet Sky Consulting, such that the appropriate discount rate for it is 1.28 percentage points different than the discount rate used for an average-risk project at Violet Sky Consulting. The internal rate of return for project B is 6.07 percent. What is X if X equals the NPV of project A plus the NPV of project B?
Formula sheet
A | B | C | D | E | F | G | H | I | J | K | L | M | N |
2 | |||||||||||||
3 | WACC for the firm | 0.0946 | |||||||||||
4 | Cost of capital of project A | =D3+1.21% | |||||||||||
5 | Cost of capital of project B | =D3-1.28% | |||||||||||
6 | |||||||||||||
7 | Cash Flow of project A will be as follows: | ||||||||||||
8 | Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |||
9 | Cash Flow | -6723 | 9748 | =$E$9 | =$E$9 | =$E$9 | =$E$9 | =$E$9 | =$E$9 | =$E$9 | |||
10 | |||||||||||||
11 | Cash Flow of project B will be as follows: | ||||||||||||
12 | Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
13 | Cash Flow | -4242 | 7211 | =E13 | =F13 | =G13 | =H13 | =I13 | =J13 | =K13 | =L13 | ||
14 | |||||||||||||
15 | Calculation of NPV of project A: | ||||||||||||
16 | |||||||||||||
17 | NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment. | ||||||||||||
18 | |||||||||||||
19 | Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |||
20 | Cash Flow (FCF) | =D9 | =E9 | =F9 | =G9 | =H9 | =I9 | =J9 | =K9 | =L9 | |||
21 | Cost of capital (i) | =D4 | |||||||||||
22 | (P/F,i,n) for each year | =1/((1+$D21)^E19) | =1/((1+$D21)^F19) | =1/((1+$D21)^G19) | =1/((1+$D21)^H19) | =1/((1+$D21)^I19) | =1/((1+$D21)^J19) | =1/((1+$D21)^K19) | =1/((1+$D21)^L19) | ||||
23 | Present Value of cash flows = FCF*(P/F,i,n) | =E20*E22 | =F20*F22 | =G20*G22 | =H20*H22 | =I20*I22 | =J20*J22 | =K20*K22 | =L20*L22 | ||||
24 | Present value if future cash flows | =SUM(E23:L23) | =SUM(E23:L23) | ||||||||||
25 | |||||||||||||
26 | NPV for Project | =Present value fo future cash flows - Initial investment | |||||||||||
27 | =D24+D20 | =D24+D20 | |||||||||||
28 | |||||||||||||
29 | Hence NPV for Project A | =D27 | |||||||||||
30 | |||||||||||||
31 | Calculation of NPV of project B: | ||||||||||||
32 | |||||||||||||
33 | NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment. | ||||||||||||
34 | Given the following cash flow and WACC, NPV for the project can be calculated as follows: | ||||||||||||
35 | Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
36 | Cash Flow (FCF) | =D13 | =E13 | =F13 | =G13 | =H13 | =I13 | =J13 | =K13 | =L13 | =M13 | ||
37 | Cost of capital (i) | =D5 | |||||||||||
38 | (P/F,i,n) for each year | =1/((1+$D37)^E35) | =1/((1+$D37)^F35) | =1/((1+$D37)^G35) | =1/((1+$D37)^H35) | =1/((1+$D37)^I35) | =1/((1+$D37)^J35) | =1/((1+$D37)^K35) | =1/((1+$D37)^L35) | =1/((1+$D37)^M35) | |||
39 | Present Value of cash flows = FCF*(P/F,i,n) | =E36*E38 | =F36*F38 | =G36*G38 | =H36*H38 | =I36*I38 | =J36*J38 | =K36*K38 | =L36*L38 | =M36*M38 | |||
40 | Present value if future cash flows | =SUM(E39:M39) | =SUM(E39:M39) | ||||||||||
41 | |||||||||||||
42 | NPV for Project | =Present value fo future cash flows - Initial investment | |||||||||||
43 | =D40+D36 | =D40+D36 | |||||||||||
44 | |||||||||||||
45 | Hence NPV for Project B | =D43 | |||||||||||
46 | |||||||||||||
47 | Value of X | =NPV of Project A + NPV of Project B | |||||||||||
48 | =D29+D45 | =D29+D45 | |||||||||||
49 | |||||||||||||
50 | Thus Value of X is | =D48 | |||||||||||
51 |