Question

In: Finance

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,000, and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project L, since the NPVL > NPVS. c. Project S, since the NPVS > NPVL. d. Both Projects S and L, since both projects have NPV's > 0. e. Both Projects S and L, since both projects have IRR's > 0.

Solutions

Expert Solution

We can calculate the Present Value of both the projects given using the Excel sheet as below

The formulas used in excel sheet are

As initial cash outlay is required for both projects, so value in year 0 is in negative.

So, with the given WACC of 14% the NPV of both projects come out to be

NPV of Project S is $ 13,032

NPV of Project L is $ 11,077

Therefore as the NPV of both the projects is positive, so both look feasible. However Project S has higher NPV than Project L, so Project S should be selected over Project L.

Hence, the correct answer is option (c) Project S, since the NPVS > NPVL

Hope I was able to solve your concern. If you are satisfied hit a thumbs up !!


Related Solutions

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,500, and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,500, and its expected cash flows would be $11,950 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer: a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $29,000, and its expected cash flows would be $14,900 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $34,500, and its expected cash flows would be $14,200 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $47,500, and its expected cash flows would be $13,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,000, and its expected cash flows would be $13,450 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $25,500, and its expected cash flows would be $12,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. b.Project L requires an initial outlay at t = 0 of $75,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT