Question

In: Finance

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,500, and its expected cash flows would be $11,950 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend?

Select the correct answer:

a. Neither Project S nor L, since each project's NPV < 0.
b. Project S, since the NPVS > NPVL.
c. Both Projects S and L, since both projects have NPV's > 0.
d. Project L, since the NPVL > NPVS.
e. Both Projects S and L, since both projects have IRR's > 0.

Solutions

Expert Solution

Answer :

Project S

Year Project cash flows (i) DF @ 12% DF @ 12% PV of Project [ (i) * (ii) ]
0 - 11,000 1 1 - 11,000
1 5,000 1 / [ 1 + 12% )^1 ] 0.89286 4,464.30
2 5,000 1 / [ 1 + 12% )^2 ] 0.79719 3,985.95
3 5,000 1 / [ 1 + 12% )^3 ] 0.71178 3,558.90
4 5,000 1 / [ 1 + 12% )^4 ] 0.63552 3,177.60
5 5,000 1 / [ 1 + 12% )^5 ] 0.56743 2,837.15
NPV => 7,023.90

Project L

Year Project cash flows (i) DF @ 12% DF @ 12% PV of Project [ (i) * (ii) ]
0 - 26,500 1 1 - 26,500
1 11,950 1 / [ 1 + 12% )^1 ] 0.89286 10,669.68
2 11,950 1 / [ 1 + 12% )^2 ] 0.79719 9,526.42
3 11,950 1 / [ 1 + 12% )^3 ] 0.71178 8,505.77
4 11,950 1 / [ 1 + 12% )^4 ] 0.63552 7,594.46
5 11,950 1 / [ 1 + 12% )^5 ] 0.56743 6,780.79
NPV => 16,577.12

If projects are mutually exclusive then only one project can be selected. In this case, NPV of project L is more than NPV of project S. So, we must select project L.

Therefore, the answer is option (d) i.e., Project L, since the NPVL > NPVS.


Related Solutions

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,500, and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,000, and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $29,000, and its expected cash flows would be $14,900 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $34,500, and its expected cash flows would be $14,200 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $47,500, and its expected cash flows would be $13,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,000, and its expected cash flows would be $13,450 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $25,500, and its expected cash flows would be $12,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. b.Project L requires an initial outlay at t = 0 of $75,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT