Question

In: Finance

Project S requires an initial outlay at t = 0 of $14,000, and its expected cash...

Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $25,500, and its expected cash flows would be $12,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend?

Select the correct answer.

a. Project S, since the NPVS > NPVL.

b. Both Projects S and L, since both projects have IRR's > 0.

c. Neither Project S nor L, since each project's NPV < 0.

d. Project L, since the NPVL > NPVS.

e. Both Projects S and L, since both projects have NPV's > 0.

Solutions

Expert Solution

Computation of NPV of both the project
year Project S Project L PVIF @ 13% Present vlaue S Present vlaue L
0 -14000 -25500 1 (14,000.00) (25,500.00)
1 4000 12,850 0.884956      3,539.82    11,371.68
2 4000 12,850 0.783147      3,132.59    10,063.43
3 4000 12,850 0.69305      2,772.20      8,905.69
4 4000 12,850 0.613319      2,453.27      7,881.15
5 4000 12,850 0.54276      2,171.04      6,974.47
NPV =           68.93    19,696.42
We can see that NPV of L is higher compraed to S . Therefore L should be accepted.
answer is option :
d. Project L, since the NPVL > NPVS.

Related Solutions

Project S requires an initial outlay at t = 0 of $16,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $29,000, and its expected cash flows would be $14,900 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,500, and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $34,500, and its expected cash flows would be $14,200 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $47,500, and its expected cash flows would be $13,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,000, and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,000, and its expected cash flows would be $13,450 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,500, and its expected cash flows would be $11,950 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer: a. Neither Project S nor L, since each project's NPV <...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. b.Project L requires an initial outlay at t = 0 of $75,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT