In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018
2019
2020
Cost incurred during the year
2,400,000
3,600,000
2,200,000
Estimated costs to complete as of year-end
5,600,000
2,000,000
0
Billings during the year
2,000,000
4,000,000
4,000,000
Cash collections during the year
1,800,000
3,600,000
4,600,000
Westgate Construction uses the completed contract method of
accounting for long-term construction contracts.
Required:
1. Calculate the amount of revenue and gross profit (loss) to
be recognized in each of the three years.
2-a.In the journal below, complete the necessary journal
entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b.In the journal below, complete the necessary journal
entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary journal
entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to prepare a
partial balance sheet for 2018 and 2019 showing any items related
to the contract.
4. Calculate the amount of revenue and gross profit (loss) to
be recognized in each of the three years assuming the following
costs incurred and costs to complete information.
2018
2019
2020
Cost incurred during the year
2,400,000
3,800,000
3,200,000
Estimated costs to complete as of year-end
5,600,000
3,100,000
0
5. Calculate the amount of revenue and gross profit (loss) to
be recognized in each of the three years assuming the following
costs incurred and costs to complete information. (same table as
above)