Question

In: Operations Management

A fashion & textile manufacturer currently has four manufacturing plants (Plant A, B, C, D) and...

A fashion & textile manufacturer currently has four manufacturing plants (Plant A, B, C, D) and two retail outlets (Outlet 1 and 2). Due to expected reduction in demand, the company is considering whether closing some of the plants would be possible. The details of the weekly forecasted demand at outlets, weekly supply at plants, and the unit cost to transport between plants and outlets are shown as follows.

Outlet 1

Outlet 2

Supply

Fixed Annual Operating Cost

Plant A

$5

$7

3,560

$750,000

Plant B

4.5

6

3,200

830,000

Plant C

6

8

2,800

680,000

Plant D

9

7

4,200

825,000

Forecasted Demand

4,500

6,000

The plant can produce only if it is operated, and the quantity should not exceed the weekly supply. Plant B can be used only if either plant A or plant C or both plants are used. Both Plant C and D should be operated at the same time. The manufacturer does not need to pay the fixed annual operating cost if the plant is not operated.

Questions:

  1. Formulate an integer programming model for this problem to determine which plants should be operated and the number of products that should be shipped from each plant to each outlet to minimize the total cost, which includes the operating cost and transportation cost.                                                                                    
  1. Solve the problem using solver (you need to attach the Excel worksheet as evidence).      

Solutions

Expert Solution

a

Formulating integer programming model.

Decision variables:

Yi = 1 if plant i should produce; else 0 if plant i should not produce and shut down

Y1=1 if plant 1 should produce; else 0 if plant A should not produce and shut down

Y2=1 if plant 2 should produce; else 0 if plant B should not produce and shut down

Y1=3 if plant 3 should produce; else 0 if plant C should not produce and shut down

Y4=1 if plant 4 should produce; else 0 if plant D should not produce and shut down

Xij = Number of units to be produced and shipped from plant i to Outlet j

X11 = Number of units to be produced and shipped from plant A to Outlet 1

X12 = Number of units to be produced and shipped from plant A to Outlet 2

X21 = Number of units to be produced and shipped from plant B to Outlet 1

X22 = Number of units to be produced and shipped from plant B to Outlet 2

X31 = Number of units to be produced and shipped from plant C to Outlet 1

X32 = Number of units to be produced and shipped from plant C to Outlet 2

X41 = Number of units to be produced and shipped from plant D to Outlet 1

X42 = Number of units to be produced and shipped from plant D to Outlet 2

Objective function

The objective is to minimize total cost. Total cost is the sum of fixed operating cost and variable transport cost from each plant to each outlet.

MIN Z= (750000Y1+830000Y2+680000Y3+825000Y4)+ (5Y1X11+7Y1X12+4.5Y2X21+6Y2X22+6Y3X31+8Y3X32+9Y4X41+7Y4X42)

Constraints:

Supply constraints:

X11+X12<= 3560

X21+X22<=3200

X31+X32<= 2800

X41+X42<= 4200

Demand constraints are:

Y1X11+Y2X21+Y3X31+Y4X41>=4500

Y1X12+Y2X22+Y3X32+Y4X42 >=6000

Y1 + Y3 >= Y2    (Plant B can be used only if either plant A or plant C or both plants are used)

Y3 = Y4    (Both Plant C and D should be operated at the same time)

Y1+Y2+Y3+Y4 <= 3

Y1, Y2, Y3, Y4 = {0,1}; binary variable

X11, X12, X21, X22, X31, X32, X41, X42 = {0, 1, 2....}; integer variable

b.

We will solve this integer programming problem using Excel Solver. Below Excel screen print show the approach.


Go to File-> Options-> Excel Add ins -> Solver Add in
Now go to Data -> Solver and setup Solver with decision variables, objective function and constraints.

Click on Solve to get the optimal solution as below:

Hence, only plant A, C and D should be operated and following units should be transported as optimal schedule.


Please give thumbs up/ likes if you find this answer helpful. Thank you


Related Solutions

At a chip manufacturing plant, four technicians, (A, B, C, D) produce three products (Products 1,...
At a chip manufacturing plant, four technicians, (A, B, C, D) produce three products (Products 1, 2, and 3). This month, the chip manufacturer can sell 80 units of Product 1, 50 units of Product 2 and, at most, 50 units of Product 3. Technician A can make only Product 1 and 3. Techncian B can make only Products 1 and 2. Technician C can make only Product 3. Techncian D can make only Product 2. For each unit produced,...
A manufacturer of automotive gaskets has two plants, A and B. Plant A manufactures 65 %...
A manufacturer of automotive gaskets has two plants, A and B. Plant A manufactures 65 % of the gaskets and plant B manufactures 35 %. Because of a batch of faulty material from a company supplying both plants, 3% of the gaskets are of sub-standard quality from plant A and 5% are sub-standard from plant B. Despite your internal quality control procedures, you still had a sub-standard gasket returned from one of your customers. What is the probability it came...
1) A book manufacturing company has two different production plants, plant A and plant B. 40%...
1) A book manufacturing company has two different production plants, plant A and plant B. 40% of books come from plant A. Of the books that come from plant A 30% are defective and 70% work as intended. Of the books from plant B 10% are defective and 90% work as intended. On top of this 10% of the defective books from plant A explode. A) Draw a tree diagram of this data. B) What is the probability of randomly...
Q 22 Suppose that a manufacturing company makes four components: A, B, C and D, for...
Q 22 Suppose that a manufacturing company makes four components: A, B, C and D, for which costs in the forthcoming year are expected to be: A B C D Production in units 1,000 2,000 4,000 3,000 Unit variable costs € € € € Direct materials 4 5 2 4 Direct labour 8 9 4 6 Variable production costs 2 3 1 2 14 17 7 12 Total fixed costs per annum: € Incurred as a direct consequence of making...
A project has four activities (A, B, C, and D) that must be performed sequentially. The...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.32 6 0.39 7 0.27 8 0.02 B 4 0.18 6 0.51 8 0.31 C 7 0.10 9 0.29 11 0.43 13 0.15 15 0.03 D 10 0.61 12 0.39 Provide the base-case, worst-case, and best-case calculations for the time to complete...
The following graph contains four lines (A, B, C and D), each of which has a...
The following graph contains four lines (A, B, C and D), each of which has a slope that is either positive, negative, zero, or infinite.For each of the following scenarios, indicate whether the relationship between the two variables is positive or negative, as well as which line on the previous graph has a slope that reflects this type of relationship. Hint: The X-axis and Y-axis on the graph are not labeled intentionally. You need to substitute the variables from each scenario...
The following graph contains four lines (A, B, C and D), each of which has a...
The following graph contains four lines (A, B, C and D), each of which has a slope that is either positive, negative, zero, or infinite.For each of the following scenarios, indicate whether the relationship between the two variables is positive or negative, as well as which line on the previous graph has a slope that reflects this type of relationship. Hint: The X-axis and Y-axis on the graph are not labeled intentionally. You need to substitute the variables from each scenario...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3 levels and is a between-subjects variable; Factor B has 2 levels and is a within-subjects variable; Factor C has 2 levels and is a between-subjects variable; Factor D has 3 levels and is a within-subjects variable. 1. How many “cells” or “conditions” or “groups” are there in this experiment? 2. If you want to test 10 participants per cell, how many TOTAL participants will...
A process has four stages (A, B, C, and D). The stages have output rates of...
A process has four stages (A, B, C, and D). The stages have output rates of 5 units/hr, 12 units/hr, 10 units/hr, and 7 units/hr, respectively. What is the output rate of this process? a. 12 units/hr b. 10 units/hr c. 7 units/hr d. 5 units/hr
A large company has the opportunity to select one of four projects: A, B, C, D,...
A large company has the opportunity to select one of four projects: A, B, C, D, or the null (Do nothing) alternative. Each project requires a single initial investment as shown in the table below. Information on each alternative was fed into a computer program that calculated the IRR for each project as well as the pertinent incremental IRR(s) as shown in the table below. Project Initial Investment Project IRR Incremental Rate of Return of “Row” – “Column” Null A...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT