Question

In: Accounting

Q 22 Suppose that a manufacturing company makes four components: A, B, C and D, for...

Q 22

Suppose that a manufacturing company makes four components: A, B, C and D, for which costs in the forthcoming year are expected to be:

A B C D
Production in units 1,000 2,000 4,000 3,000
Unit variable costs
Direct materials 4 5 2 4
Direct labour 8 9 4 6
Variable production costs 2 3 1 2
14 17 7 12

Total fixed costs per annum:

Incurred as a direct consequence of making A 1,000
Incurred as a direct consequence of making B 5,000
Incurred as a direct consequence of making C 6,000
Incurred as a direct consequence of making D 8,000
Other fixed costs 30,000
Total 50,000


A sub-contractor has offered to supply units of A, B, C and D for €12, €21, €10 and €14 respectively.

Which components should the company make and which ones buy from the subcontractor? Choose the appropriate altenative for each component.

Component A : BUY or MAKE ?

Component B : BUY or MAKE ?      

Component C : BUY or MAKE ?

Component D : BUY or MAKE ?

Solutions

Expert Solution

A

B

C

D

Direct material

$            4.00

$               5.00

$            2.00

$               4.00

Direct labor

$            8.00

$               9.00

$            4.00

$               6.00

Variable Production cost

$            2.00

$               3.00

$            1.00

$               2.00

Relevant variable cost per unit

$          14.00

$            17.00

$            7.00

$            12.00

Number of Units

             1,000

                2,000

             4,000

                3,000

Total Variable cost

$ 14,000.00

$    34,000.00

$ 28,000.00

$    36,000.00

add: Avoidable fixed cost

$    1,000.00

$      5,000.00

$    6,000.00

$      8,000.00

Total Relevant cost of Production

     15,000.00

       39,000.00

     34,000.00

       44,000.00

A

B

C

D

Purchase price per unit

$ 12

$ 21

$ 10

$ 14

Number of Units

             1,000

                2,000

             4,000

                3,000

Total Purchase cost

$ 12,000.00

$    42,000.00

$ 40,000.00

$    42,000.00

Decision

BUY

MAKE

MAKE

BUY

In case of A and D Purchase cost is lower than relevant production cost so it’s better to purchase.

Although B and C has lower production cost than outsourcing price so it’s better to manufacture.

Only avoidable fixed cost will be considered for this decision and since other fixed cost would remain same whatever the decision is that is why other cost is not taken into consideration.


Related Solutions

Prove that the set R ={ a+ b√2+c√3+d√6 , a,b,c,d belongs to Q } is a...
Prove that the set R ={ a+ b√2+c√3+d√6 , a,b,c,d belongs to Q } is a field
Suppose there are four identical conducting spheres: A, B, C, and D. In each scenario, sphere...
Suppose there are four identical conducting spheres: A, B, C, and D. In each scenario, sphere A starts with a charge of −?,sphere C starts out with a charge of +Q, and spheres B and D start out neutral. Then, the spheres are touched to each other and separated in the order described. Any spheres not in contact are held very far away. For each scenario, give the final charge of sphere C as a whole‑number fraction of ?. For...
At a chip manufacturing plant, four technicians, (A, B, C, D) produce three products (Products 1,...
At a chip manufacturing plant, four technicians, (A, B, C, D) produce three products (Products 1, 2, and 3). This month, the chip manufacturer can sell 80 units of Product 1, 50 units of Product 2 and, at most, 50 units of Product 3. Technician A can make only Product 1 and 3. Techncian B can make only Products 1 and 2. Technician C can make only Product 3. Techncian D can make only Product 2. For each unit produced,...
Suppose we have multinomial population with four categories: A,B,C, and D. The null hypothesis is that...
Suppose we have multinomial population with four categories: A,B,C, and D. The null hypothesis is that the proportion of items is the same in every category. The null hypothesis is H0: Pa =Pb=Pc=Pd =0.25 A sample of size 300 yielded the following results. A:80 B:85 C:60 D:70 Use alpha=0.05, determine whether H0 should be rejected?
A large company has the opportunity to select one of four projects: A, B, C, D,...
A large company has the opportunity to select one of four projects: A, B, C, D, or the null (Do nothing) alternative. Each project requires a single initial investment as shown in the table below. Information on each alternative was fed into a computer program that calculated the IRR for each project as well as the pertinent incremental IRR(s) as shown in the table below. Project Initial Investment Project IRR Incremental Rate of Return of “Row” – “Column” Null A...
A manufacturing company makes three products, A, B, and C. The fixed FO is $60,000, consisting...
A manufacturing company makes three products, A, B, and C. The fixed FO is $60,000, consisting of $10,000 for material handling, material waste, and procurement; $30,000 for rent and utilities; and $20,000 for safety and canteen costs. Other costs are shown in Table 6.16 Product A Product B Product C Number of Units Produced Per Month (-)       250 400 900 Total Material Costs Per Month ($)     5000 8000 4000 Labor Hours Per Unit (hr) 4 3.5 1.5 Labor Rate Per...
Consider the cross: A/a; b/b; C/c; D/d; E/e x A/a; B/b; c/c; D/d; e/e a) what...
Consider the cross: A/a; b/b; C/c; D/d; E/e x A/a; B/b; c/c; D/d; e/e a) what proportion of the progeny will phenotypically resemble the first parent? b) what proportion of the progeny will genotypically resemble neither parent?
An experiment consists of four outcomes (A, B, C, D) with P(A) = 0.2, P(B) =...
An experiment consists of four outcomes (A, B, C, D) with P(A) = 0.2, P(B) = 0.3, and P(C) = 0.4.  The P(D) is 0.500 0.024 0.100 0.900 Given that event E has a probability of 0.3, the probability of the complement of event E cannot be determined with the above information can have any value between zero and one must be 0.7 is 0.3 If P(A) = 0.38, P(B) = 0.83, and P(A Ç B) = 0.57; then P(A È...
There is a chess team with four players {A, B, C, D} training for a competition....
There is a chess team with four players {A, B, C, D} training for a competition. The coach wants all players to play each other. Ignore which player is chosen to take the first move. 1. Do we use a counting rule for combinations or for permutations to calculate the total number of possible games if all players must play each other once? (Only one is correct.) 2. Calculate by hand (you can use a calculator but show some work),...
There are four urns, which we label A, B, C, and D, and each of these...
There are four urns, which we label A, B, C, and D, and each of these urns contains some white balls and some black balls, as specified below.•UrnAhas3white balls and2black balls•UrnBhas2white balls and6black balls•UrnChas3white balls and6black balls•UrnDhas5white balls and7black balls one of the urns is chosen at random, and then one of the balls is selected from the chosen urn. (a) What is the probability that urnAis chosen, and then a white ball is chosen from thaturn? (b) What is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT