In: Finance
Question 1-- NPV Profiles: Graph the NPV profiles for both projects on a common chart., making sure you identify the "crucial" points.
0 -$725 -$850
1 100 200
2 250 200
3 250 200
4 200 200
5 100 200
6 100 200
7 100 200
Note: First column is time, second column is Project A cash flow , third column is Project B flow. This is a two-part question. Answer for first ? is needed to solve ? 2.
Question 2-- IRR Applicability:For what range of possible interest rates would you want to use IRR to choose between the those to projects? For what range would you NOT want to use IRR?
(1): For NPV computations I have computed the PVs using the present value interest factor (PVIF). PVIF = 1/(1+r)^n where r is the discount rate and n is the year of cash flow.
PV = Cash flow in a year*PVIF
For instance when r = 10% then the PVs will be:
Year | Cash flow of A | Cash flow of B | 1+r | PVIF | PV of A | PV of B |
- | - 725.00 | - 850.00 | 1.1000 | 1.00000 | - 725.00 | - 850.00 |
1.00 | 100.00 | 200.00 | 0.90909 | 90.91 | 181.82 | |
2.00 | 250.00 | 200.00 | 0.82645 | 206.61 | 165.29 | |
3.00 | 250.00 | 200.00 | 0.75131 | 187.83 | 150.26 | |
4.00 | 200.00 | 200.00 | 0.68301 | 136.60 | 136.60 | |
5.00 | 100.00 | 200.00 | 0.62092 | 62.09 | 124.18 | |
6.00 | 100.00 | 200.00 | 0.56447 | 56.45 | 112.89 | |
7.00 | 100.00 | 200.00 | 0.51316 | 51.32 | 102.63 | |
NPV | 66.81 | 123.68 |
I have computed NPVs for different rates and the NPV profile graph is shown below:
Since the two NPV profiles shown above do not cross in the first quadrant, the only crucial points are the two projects’ IRRs:
For A = 13.00%
For B = 14.29%
(2): Since the two projects’ NPV profiles do not cross in the first quadrant, IRR would work for ALL possible ranges of rates.