Question

In: Finance

11-2: Net Present Value (NPV) 11-7: NPV Profiles NPV Your division is considering two projects with...

11-2: Net Present Value (NPV)
11-7: NPV Profiles

NPV

Your division is considering two projects with the following cash flows (in millions):

0 1 2 3
Project A -$27 $13 $17 $8
Project B -$25 $14 $11 $2

What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
Project A    $   million
Project B    $   million

What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
Project A    $   million
Project B    $   million

What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
Project A    $   million
Project B    $   million

What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places.
Project A   %
Project B   %

What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places.
Project A   %
Project B   %

What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places.
Project A   %
Project B   %

If the WACC were 5% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 90.37%.)  
-Select- (Project A) (Project B) (Neither A, nor B)

If the WACC were 10% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 90.37%.)  
-Select-(Project A) (Project B) (Neither A, nor B)

If the WACC were 15% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 90.37%.)  
-Select- (Project A) (Project B) (Neither A, nor B)

Solutions

Expert Solution

For project A

Cash flow for year 1, C1 = $13

Cash flow for year 2, C2 = $17

Cash flow for year 3, C3 = $8

Initial investment , IA = $27

For project B

Cash flow for year 1, B1 = $14

Cash flow for year 2, B2 = $11

Cash flow for year 3, B3 = $2

Initial investment , IB = $25

a)

(i) WACC = 5% = 0.05

NPV of project A = [ (C1/(1.05)1) + (C2/(1.05)2) + (C3/(1.05)3) ] - IA

[ (13/(1.05)1) + (17/(1.05)2) + (8/(1.05)3) ] - 27 = [12.380952 + 15.419501 + 6.9107007] -27 = $7.711154 million or $7.71 million

NPV of project B = [ (C1/(1.05)1) + (C2/(1.05)2) + (C3/(1.05)3) ] - IB

[ (14/(1.05)1) + (11/(1.05)2) + (2/(1.05)3) ] - 25 = [13.3333 + 9.977324 + 1.727675] -25 = $0.038332 million or $0.04 million

(ii)

WACC = 10% = 0.10

NPV of project A = [ (C1/(1.10)1) + (C2/(1.10)2) + (C3/(1.10)3) ] - IA

[ (13/(1.10)1) + (17/(1.10)2) + (8/(1.10)3) ] - 27 = [11.8181 + 14.0495 + 6.0105] -27 = $4.87828 million = -$4.88 million

NPV of project B = [ (C1/(1.10)1) + (C2/(1.10)2) + (C3/(1.10)3) ] - IB

[ (14/(1.10)1) + (11/(1.10)2) + (2/(1.10)3) ] - 25 = [12.7272 + 9.0909 + 1.5026] -25 = -$1.6791 million or -$1.68 million

(iii)

WACC = 15% = 0.15

NPV of project A = [ (C1/(1.15)1) + (C2/(1.15)2) + (C3/(1.15)3) ] - IA

[ (13/(1.15)1) + (17/(1.15)2) + (8/(1.15)3) ] - 27 = [11.3043 + 12.8544 + 5.2601] -27 = $2.4189 million or $2.42 million

NPV of project B = [ (C1/(1.15)1) + (C2/(1.15)2) + (C3/(1.15)3) ] - IB

[ (14/(1.15)1) + (11/(1.15)2) + (2/(1.15)3) ] - IB = [12.1739 + 8.3175 + 1.3150] -25 = -$3.1934 million or -$3.19 million

b)

(i) For project A

IRR is the rate of return for which NPV = 0

NPV = Present value of cash inflows of the project - initial investment

Putting NPV = 0

Present value of cash inflows of the project = initial investment

[ (C1/(1+IRR)1) + (C2/(1+IRR)2) + (C3/(1+IRR)3) ] = I

[ (13/(1+IRR)1) + (17/(1+IRR)2) + (8/(1+IRR)3) ] = 27

We have to find IRR by trial and error method

by assuming any value and substituting the assumed value in the above equation

we want IRR such that

Leht Hand side of equation(LHS) = Right hand side of equation (RHS) = 27

by following this method we find that for IRR = 20.6723% or 20.67% ( rounding off to 2 decimal places)

LHS = RHS

hence IRR = 20.6723% or 20.67% ( rounding off to two decimal places)

this is the IRR for WACC = 5% , 10%, 15%

(ii) For project B

IRR is the rate of return for which NPV = 0

NPV = Present value of cash inflows of the project - initial investment

Putting NPV = 0

Present value of cash inflows of the project = initial investment

[ (C1/(1+IRR)1) + (C2/(1+IRR)2) + (C3/(1+IRR)3) ] = I

[ (14/(1+IRR)1) + (11/(1+IRR)2) + (2/(1+IRR)3) ] = 25

We have to find IRR by trial and error method

by assuming any value and substituting the assumed value in the above equation

we want IRR such that

Leht Hand side of equation(LHS) = Right hand side of equation (RHS) = 25

by following this method we find that for IRR = 5.10476% or 5.10% ( rounding off to 2 decimal places)

LHS = RHS

hence IRR = 5.104% or 5.10% ( rounding off to two decimal places)

this is the IRR for WACC = 5% , 10%, 15%

c)

(i) if WACC = 5%

crossover rate = 90.37%

for WACC < crossover rates, Project A would be selected, since NPV of A > NPV of B

(ii) if WACC = 10%

crossover rate = 90.37%

for WACC < crossover rates ,

hence project A would be selected, since project B's NPV is negative

(iii) WACC =15%

crossover rate = 90.37%

Project A would be selected, since project B's NPV is negative


Related Solutions

All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:    Project_A     Project_B     Project_C     Project_D     Project_E     Project_F     Project_G NPV=    $137,083    $31,290    $6,016    $7,647    ($584)    $12,521    $9,214 IRR=    31.80%    48.34%    12.03%    11.30%    9.94%    26.79%    37.87% MIRR=    18.52%    23.52%...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria Project_A Project_B Project_C Project_D Project_E Project_F Project_G NPV= $14,154 $77,992 $29,515 $11,564 ($8,849) $26,514 $30,022 IRR= 28.66% 20.33% 19.72% 45.52% 9.03% 16.40% 16.05% MIRR= 17.28% 14.35% 12.86% 22.76% 9.53% 11.97% 12.45% PI= 1.57 1.31 1.20 2.16 0.97 1.13 1.17 The cost of capital (r) is 10%. Which of the...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria: Project_A Project_B Project_C Project_D Project_E Project_F Project_G NPV= $137,083 $36,290 $6,016 $7,647 ($584) $14,521 $8,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.28 1.92 The discounting rate (r) is 10%. Which of the following...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 Which of the following...
Problem 11-6 NPV Your division is considering two projects with the following cash flows (in millions):...
Problem 11-6 NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$17 $8 $8 $3 Project B -$26 $13 $10 $9 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign....
Problem 11-6 NPV Your division is considering two projects with the following cash flows (in millions):...
Problem 11-6 NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$17 $8 $8 $3 Project B -$26 $13 $10 $9 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. (fill in the blank space) Project A    $____ million Project B    $____ million What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Project A    $____ million...
Problem 10-7 NPV Your division is considering two investment projects, each of which requires an up-front...
Problem 10-7 NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects'...
Problem 12-7 NPV Your division is considering two investment projects, each of which requires an up-front...
Problem 12-7 NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects'...
The NPV (net present value) of Plan Alpha is $ (130,539) The NPV (net present value)...
The NPV (net present value) of Plan Alpha is $ (130,539) The NPV (net present value) of Plan Beta is $ 233,001 The IRR (internal rate of return) of Plan Alpha is $ 19.36 %. The IRR (internal rate of return) of Plan Beta is $ 21.25 %. Which​ plan, if​ any, should the company​ pursue? Based on the results​ above, the company should pursue Plan Beta because the NPV is positive and the IRR is greater than the​ company's...
NPV Your division is considering two projects with the following cash flows (in millions): Project A...
NPV Your division is considering two projects with the following cash flows (in millions): Project A -$31 $7 $12 $22 Project B -$19 $13 $6 $5 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A $ million Project B...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT