In: Operations Management
BORNEO TEC. is a smart card technology company. Currently it has
three project leaders that are very experienced in developing
micropayment cards using the technology of MiFARE 3.0. There are 4
micropayment companies in Malaysia wanted to adopt the technology,
these clients namely Client 1, Client 2, Client 3 and Client
4.
All projects are very critical to be completed in timely basis,
therefore, the Program leader would assign the Project Leader
strategically using the assignment method. The estimated project
completion time’s requirement, in days, is as follows.
Project Leader | Client 1 | Client 2 | Client 3 | Client 4 |
ABU | 19 | 14 | 18 | 16 |
BALA | 18 | 17 | 17 | 16 |
CHAN | 13 | 18 | 16 | 18 |
Find the assignment of each project leaders to clients that will
minimize the total days to complete all the projects.
Create Excel model as follows:
Enter Solver Parameters as follows:
Click Solve to generate the solution:
Click OK
----------------------
Result:
Project leader ABU should be assigned to clients 2 and 4
Project leader CHAN should be assigned to projects 1 and 3
Total days to complete all the projects = 59