In: Operations Management
Assume that you are the project manager for the construction of a 15-mile road. Further assume that the work is uniformly distributed over 12 weeks. The total approved budget for this project is $600,000. At the end of the first three weeks of work $160,000 has been spent and five miles of road have been completed. At the end of the first three weeks, what do you think of the current status of the project in terms of cost and schedule? Describe the earned value analysis terms that you use and their formulas, and then calculate each metric. Then interpret your results. Important: there are more than 3 earned value metrics to calculate.
*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****
EV = BAC x (work
completed/total work required)
EV = 600,000 x (5 mi/15 mi) =
200,000
PV = BAC x (time
passed/total schedule time)
PV = 600,000 x (3weeks/12 weeks) =
150,000
CV = EV - AC
CV = 200,000 - 160,000 =
40,000
SV = EV - PV
SV = 200,000 - 150,000 =
50,000
The cost performance index (CPI) is a measure of the conformance of the actual work completed (measured by its earned value) to the actual cost incurred: CPI = EV / AC. The schedule performance index (SPI) is a measure of the conformance of actual progress (earned value) to the planned progress: SPI = EV / PV.
CPI = EV / AC = 200,000 / 160,000 = 1.25
SPI = EV / PV = 200,000 / 150,000 = 1.33
A CPI value of 1.25 and an SPI value of 1.33 for a project mean
The project is making faster progress and
is costing less than planned.
CPI > 1 means cost
performance is better than planned
SPI > 1 means schedule performance is better than
planned
*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****