Question

In: Operations Management

Assume that you are the project manager for the construction of a 15-mile road. Further assume...

Assume that you are the project manager for the construction of a 15-mile road. Further assume that the work is uniformly distributed over 12 weeks. The total approved budget for this project is $600,000. At the end of the first three weeks of work $160,000 has been spent and five miles of road have been completed. At the end of the first three weeks, what do you think of the current status of the project in terms of cost and schedule? Describe the earned value analysis terms that you use and their formulas, and then calculate each metric. Then interpret your results. Important: there are more than 3 earned value metrics to calculate.

Solutions

Expert Solution

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****

EV = BAC x (work completed/total work required)
EV = 600,000 x (5 mi/15 mi) =
200,000

PV = BAC x (time passed/total schedule time)
PV = 600,000 x (3weeks/12 weeks) =
150,000

CV = EV - AC
CV = 200,000 - 160,000 =
40,000

SV = EV - PV
SV = 200,000 - 150,000 =
50,000

The cost performance index (CPI) is a measure of the conformance of the actual work completed (measured by its earned value) to the actual cost incurred: CPI = EV / AC. The schedule performance index (SPI) is a measure of the conformance of actual progress (earned value) to the planned progress: SPI = EV / PV.

CPI = EV / AC = 200,000 / 160,000 = 1.25
SPI = EV / PV = 200,000 / 150,000 = 1.33

A CPI value of 1.25 and an SPI value of 1.33 for a project mean

The project is making faster progress and is costing less than planned.
CPI > 1 means cost performance is better than planned
SPI > 1 means schedule performance is better than planned

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****


Related Solutions

You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Assume that your project has started to slip dramatically. Let’s further assume that the project deadline...
Assume that your project has started to slip dramatically. Let’s further assume that the project deadline is fixed and can't change. Your project currently has one developer working on module of code with 21 day duration on the critical path. You are desperate to shorten this timeframe and you are considering adding a second resource to this activity but, the resource does not have all the right skills and he might work five days just to reduce the overall time...
You are a project manager at a construction company that specializes in building office buildings. You...
You are a project manager at a construction company that specializes in building office buildings. You were approached by a representative of a company that was interested in your company’s services. He told you that their company was growing and they decided to build a new office building to address their needs. Then he told you that they already started the process with another construction company. They signed a contract with the other construction company and they started the building...
Why should we hire you as a construction project Engineer on a complex, multi-phase large road...
Why should we hire you as a construction project Engineer on a complex, multi-phase large road or bridge construction project.
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections...
Paccione Paving is considering purchasing a unique piece of equipment for a road construction project that...
Paccione Paving is considering purchasing a unique piece of equipment for a road construction project that will last five years. At the end of the five-year project, Paccione will no longer need the equipment. The equipment will cost $1,225,000, will be depreciated straight-line over seven years, and will be sold for $415,000 at the end of the project. The project will generate additional revenues of $750,000 with annual expenses of $165,000. The project will require an initial investment in net...
Assume you are a project manager at JCDecaux and have been assigned to work with the...
Assume you are a project manager at JCDecaux and have been assigned to work with the city of Lyon to implement this physical, organizational, and social change. What are the practical and philosophical implications of this work?
•Assume you borrow from the bank $5,000,000. Assume you make quarterly payments. Further assume that the...
•Assume you borrow from the bank $5,000,000. Assume you make quarterly payments. Further assume that the stated coupon rate is 9% per annum and the loan matures in 12 years. Determine the interest and principal payment for year 5. • Assume you borrow from the bank $5,000,000. Assume you make quarterly payments. Further assume that the stated coupon rate is 9% per annum and the loan matures in 12 years. You also make a balloon payment of $1,000,000 in the...
There is a new amusement park under construction in town and the manager of the project...
There is a new amusement park under construction in town and the manager of the project has hired you to design a "Zero-Gravity" room. (a) Based on your knowledge of nature of electric charge and electric forces, how will you design such a facility? Comment on components of the room, and explain how it will work for walk in customers? What would be the safety concerns and measures? (b) Assume that your design has been approved and facility has been...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT