Question

In: Accounting

Designer Frames makes bicycle frames in two processes, tubing and welding. The tubing process has a...

Designer Frames makes bicycle frames in two processes, tubing and welding. The tubing process has a capacity of 125,000 units per year; welding has a capacity of 150,000 units per year. Cost information follows:

Design of product and process costs

$100,000

Inspection and testing costs

42,500

Scrap cost per unit (all in the tubing dept.)

34.00

The company enjoys high demand for its products. Designer Frames can sell whatever output it can produce for the market price of $55 per frame. Designer Frames can start only 125,000 units into production in the tubing department because of capacity constraints on the tubing machines. The company scraps all defective units produced in the tubing department. Of the 125,000 units started in the tubing operation, 12,500 units (10 percent) are scrapped at the end of the production process. Scrap costs, based on total (fixed and variable) manufacturing costs incurred in the tubing operation, equal $34.00 per unit as follows:

Direct materials (variable)

$17.50

Direct manufacturing, setup, and materials handling labor (variable)

6.50

Depreciation, rent, and other overhead (fixed)

10.00

$34.00

The “$10 fixed cost” is the portion of the total fixed costs of $1,250,000 allocated to each unit, whether good or defective. The good units from the tubing department are sent to the welding department. Variable manufacturing costs in the welding department are $2.00 per unit. There is no scrap in the welding department. Therefore, Designer Frames’ total sales quantity equals the tubing department’s output. Designer Frames incurs no other variable costs. Designer Frames’ designers have discovered that using a different type of material in the tubing operation would reduce scrap to zero, but it would increase the variable costs per unit in the tubing department by $2.25. Recall that only 125,000 units can be started each year.

Required:

  1. What is the additional direct materials cost of implementing the new method?

The additional direct material cost for implementing the new method would be $2.25 per unit and a total of $281,250.

b. What is the additional benefit to Designer Frames from using the new material and improving quality?

c. Should Designer Frames use the new materials?

d. Draft brief note to management describing other nonfinancial and qualitative factors should Designer Frames consider in making the decision?

Solutions

Expert Solution

a) The additional direct materials cost of implementing the new method is calculated as follows:-

No of units produced during the year * Additional cost per unit

125,000 Units * $ 2.25 per unit

= $ 281,250

b) Additional benefit from using the new material and improving quality can be calculated as follows:-

  • Increase in profit equivalent to contribution on defective products which can be calculated as follows:-

No of units scrapped * (Sale price/Unit - Variable cost/unit)

= 12,500 Units * ($ 55 - $ 24)

= $ 387,500

c) Yes, the designer frames should use new materials, as it will increase profit of the Company by $ 106,250 ( 387,500 - 281,250)

d) Following are the certain illustrative factors that can be considered in making the decision:-

  • Improving quality will improve the goodwill of the Company amongst customers, and they may also charge certain premium for such quality in due course of time
  • The Company will be able to utilize Welding department more, as the quantity transferred from Tubing department to Welding department will increase
  • Inspection and Quality costs will also be gradually reduced, hence increasing the profitability in long term.
  • By earning more profits, The Company can expand the capacity of tubing department, so as to increase the production and profits in turn.

Related Solutions

Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer uses the weighted average method. Manufacturing costs are added uniformly throughout the process. The following are cost and production data for the cutting department for October: Production: Units in process, October 1, 40% complete 6,000 Units completed and transferred out 40,800 Units in process, October 31, 60% complete 12,000 Costs: WIP, October 1 $ 48,000 Costs added during October 912,000 Required: Prepare a production...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer uses the weighted average method. Manufacturing costs are added uniformly throughout the process. The following are cost and production data for the cutting department for October: Production: Units in process, October 1, 40% complete 5,600 Units completed and transferred out 38,080 Units in process, October 31, 60% complete 11,200 Costs: WIP, October 1 $ 44,800 Costs added during October 851,200 Required: Prepare a production...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer uses the weighted average method. Manufacturing costs are added uniformly throughout the process. The following are cost and production data for the cutting department for October: Production: Units in process, October 1, 40% complete 5,600 Units completed and transferred out 38,080 Units in process, October 31, 60% complete 11,200 Costs: WIP, October 1 $ 44,800 Costs added during October 851,200 Required: Prepare a production...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer uses the weighted average method. Manufacturing costs are added uniformly throughout the process. The following are cost and production data for the cutting department for October: Production: Units in process, October 1, 40% complete 4,800 Units completed and transferred out 32,640 Units in process, October 31, 60% complete 9,600 Costs: WIP, October 1 $ 38,400 Costs added during October 729,600 Required: Prepare a production...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer...
Production Report, Weighted Average Manzer Inc. manufactures bicycle frames in two departments: cutting and welding. Manzer uses the weighted average method. Manufacturing costs are added uniformly throughout the process. The following are cost and production data for the cutting department for October: Production: Units in process, October 1, 40% complete 4,000 Units completed and transferred out 27,200 Units in process, October 31, 60% complete 8,000 Costs: WIP, October 1 $32,000 Costs added during October 608,000 Required: Prepare a production report...
Thomas Ltd., a manufacturing firm, manufactures frames for the Kona Bicycle company. The company has supplied...
Thomas Ltd., a manufacturing firm, manufactures frames for the Kona Bicycle company. The company has supplied information from its accounting records for the last 12 months. No. of Factory Month Frames Overhead Jan          5,000 $      9,000 Feb          6,000        10,800 Mar          4,400          8,600 Apr          5,800          9,600 May          4,800          9,100 Jun          5,300          9,400 Jul          4,500          7,900 Aug          7,000        13,000 Sep          5,500        10,800 Oct          5,600...
You are tasked with a process selection project. There are two processes (A and B) that...
You are tasked with a process selection project. There are two processes (A and B) that could potentially work for your application (cutting tubing to a specified length). Sample data is provided by the two companies. Out of the 16 samples from process A, you find an average of 17.92 inches and a standard deviation of 1.98 inches. Thirteen samples were taken from process B improvement and had an average length of 16.58 inches and a standard deviation of 1.30...
Ringsmith Company is considering two different processes to make its product—process 1 and process 2. Process...
Ringsmith Company is considering two different processes to make its product—process 1 and process 2. Process 1 requires Ringsmith to manufacture subcomponents of the product in-house. As a result, materials are less expensive, but fixed overhead is higher. Process 2 involves purchasing all subcomponents from outside suppliers. The direct materials costs are higher, but fixed factory overhead is considerably lower. Relevant data for a sales level of 25,000 units follow:     Process 1     Process 2 Sales     $6,600,000    ...
Two processes share the variable "I". Process A increments it 10 times and process B decrements...
Two processes share the variable "I". Process A increments it 10 times and process B decrements it 25 times without using critical sections. The initial value of I is 0. The final value of I MUST be Please explain.
Sheffield Rides makes bicycles. It has always purchased its bicycle tires from the Balyo Tires at...
Sheffield Rides makes bicycles. It has always purchased its bicycle tires from the Balyo Tires at $11 each but is currently considering making the tires in its own factory. The estimated costs per unit of making the tires are as follows: Direct materials $4 Direct labor $4 Variable manufacturing overhead $2 The company’s fixed expenses would increase by $29,820 per year if managers decided to make the tire. (a1) Calculate total relevant cost to make or buy if the company...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT