In: Operations Management
In a project, what is generally the duration of each of the five process groups?
For example, Initiation takes about 14-21 days to complete. So, what about other process groups?
In the project generally, 2% time spent on the initiation, 21% on planning, 69% of executing, 5% on monitoring, 3% on closing the projects. The initiating group provides motivation for the planning process. Hereafter document and other required formal documents completion next process planning process initiated. Here as per the question, 14-21 days take on the initiation that is approx 2% time of the project.
The planning phase provides the motivation for the executing phase. Here proper planning considered to start executing process groups of the project here 140-210 days in the planning phase.
The executing phase which is a major process of the project and here project work delivered as per planning. It takes a longer time period compared to others as 69% which is 450- 1200 days as per the question.
In the monitoring and controlling phase is only the management process that interacts with all process group, where the project team checks about factors affecting the project work and it take 5% and 20-39 days as per the question.
Then the final phase is the closing phase which helps to close the project and takes almost 3% time and 16-24 days as per the question.
PLEASE RATE WITH A THUMBS UP.