Question

In: Finance

Your division is considering two investment projects, each of which requires an up-front expenditure of $28...

Your division is considering two investment projects, each of which requires an up-front expenditure of $28 million. You estimate that the cost of capital is 11% and that the investments will produce the following after-tax cash flows (in millions of dollars):

Year

Project A

Project B

1

6

18

2

10

12

3

15

8

4

22

5

  1. What is the regular payback period for each of the projects? Round your answers to two decimal places.
  2. What is the NPV and IRR for each of the projects? Round your answers to two decimal places.
  3. If the two projects are independent and the cost of capital is 11%, which project or projects should the firm undertake?
  4. What is the crossover rate? Round your answer to two decimal places.
  5. If the two projects are mutually exclusive and the cost of capital is 5%, which project should the firm undertake?
  6. If the cost of capital is 11%, what is the MIRR of each project? Round your answers to two decimal places.

Solutions

Expert Solution

(a): Payback for the two projects are:

Year A cumulative cash flows of A B cumulative cash flows of B
0 -          28.00 -                       28.00 -      28.00 -                       28.00
                1               6.00 -                       22.00         18.00 -                       10.00
                2             10.00 -                       12.00         12.00                            2.00
                3             15.00                            3.00           8.00
                4             22.00           5.00

Thus payback of A = 2 + (12/15) = 2.80 years

Payback of B = 1 + (10/12) = 1.83 years

(b): NPV:

Year A 1+r PVIF PV of A's cash flow B PV of B's cash flow
0 -          28.00                            1.11             1.00000 -              28.00 -      28.00 -      28.00
                1               6.00             0.90090                   5.41         18.00         16.22
                2             10.00             0.81162                   8.12         12.00           9.74
                3             15.00             0.73119                 10.97           8.00           5.85
                4             22.00             0.65873                 14.49           5.00           3.29
Total                10.98          7.10

NPV of A = $10.98 million and NPV of B = $7.10 million

IRR: This is the rate at which NPV is nil.

Year A 1+r PVIF PV of A's cash flow B 1+r PVIF PV of B's cash flow
0 -          28.00                       1.2482                    1.00 -              28.00 -      28.00         1.2556           1.00 -      28.00
                1               6.00                    0.80                   4.81         18.00           0.80         14.34
                2             10.00                    0.64                   6.42         12.00           0.63           7.61
                3             15.00                    0.51                   7.71           8.00           0.51           4.04
                4             22.00                    0.41                   9.06           5.00           0.40           2.01
Total                   0.00           0.00

IRR of A = 24.82% and IRR of B = 25.56%

(c):  In this case the firm will undertake both the projects as their NPV>0 and IRR>cost of capital.

(d): Crossover rate is the rate at which NPV of both the projects are same. The rate is:

Year A 1+r PVIF PV of A's cash flow B PV of B's cash flow
0 -          28.00                       1.2348             1.00000 -              28.00 -      28.00 -          28.00
                1               6.00             0.80984                   4.86         18.00            14.58
                2             10.00             0.65584                   6.56         12.00               7.87
                3             15.00             0.53112                   7.97           8.00               4.25
                4             22.00             0.43012                   9.46           5.00               2.15
Total                  0.85              0.85

Hence the crossover rate is 23.48%

(e): Here compute the NPV at 5% rate:

Year A 1+r PVIF PV of A's cash flow B PV of B's cash flow
0 -          28.00                       1.0500             1.00000 -              28.00 -      28.00 -          28.00
                1               6.00             0.95238                   5.71         18.00            17.14
                2             10.00             0.90703                   9.07         12.00            10.88
                3             15.00             0.86384                 12.96           8.00               6.91
                4             22.00             0.82270                 18.10           5.00               4.11
Total                17.84            11.05

Project A will be selected as at 5% its NPV is higher.

(f): For A terminal value of cash inflows = 6*(1.11)^3 + 10*(1.11)^2 + 15*(1.11)^1 + 22

= 59.18. Thus 28 = 59.18/(1+mirr)^4

Or MIRR of A = 20.58%

For B terminal value of cash inflows = 18*(1.11)^3 + 12*(1.11)^2 + 8*(1.11)^1 + 5 = 53.28

Thus 28 = 53.28/(1+mirr)^4

Or Mirr of B = 17.45%

Thus MIRR of A = 20.58% and of B = 17.45%


Related Solutions

Your division is considering two investment projects, each of which requires an up-front expenditure of $17...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%, 10% and 15%? What are the two projects' IRRs at these same costs of capital?
Your division is considering two investment projects, each of which requires an up-front expenditure of $17...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the two...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
Your division is considering two investment projects, each of which requires an up-front expenditure of $24...
Your division is considering two investment projects, each of which requires an up-front expenditure of $24 million. You estimate that the cost of capital is 11% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places. Project A Project B...
Your division is considering two investment projects, each of which requires an up-front expenditure of $20...
Your division is considering two investment projects, each of which requires an up-front expenditure of $20 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $4,500,000 $20,000,000 2 10,000,000 10,000,000 3 20.000.000 6,500,000 What are the two project’s NPVs assuming the cost of capital is 3%, 12%, 17%? What are the two projects’ IRRs at those same costs of capital?
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
Your division is considering two facility investment projects, each of which requires an up-front expenditure of...
Your division is considering two facility investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $5,000,000 $20,000,000 2 $10,000,000 $10,000,000 3 $20,000,000 $6,000,000 What are the project's net present values, assuming the cost of the capital is a)10% b)5% )15%? What does this analysis tell you about the projects?
Your division is considering two investment projects, each of which requires an up-front expenditure of $23...
Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present...
Your division is considering two investment projects, each of which requires an up-front expenditure of $14...
Your division is considering two investment projects, each of which requires an up-front expenditure of $14 million. You estimate that the investments will produce the following net cash flows: Year Year $5,000,000 $20,000,000 1 10,000,000 10,000,000 2 20.000.000 6,000,000 3 a. What are the two project’s NPVs assuming the cost of capital is 4%, 11%, 16%? b. What are the two projects’ IRRs at those same costs of capital?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT