In: Finance
Your division is considering two investment projects, each of which requires an up-front expenditure of $24 million. You estimate that the cost of capital is 11% and that the investments will produce the following after-tax cash flows (in millions of dollars):
Year Project A Project B
1 5 20
2 10 10
3 15 8
4 20 6
What is the regular payback period for each of the projects? Round your answers to two decimal places.
Project A
Project B
What is the discounted payback period for each of the projects? Round your answers to two decimal places.
Project A
Project B
If the two projects are independent and the cost of capital is 11%, which project or projects should the firm undertake?
If the two projects are mutually exclusive and the cost of capital is 5%, which project should the firm undertake?
If the two projects are mutually exclusive and the cost of capital is 15%, which project should the firm undertake?
What is the crossover rate? Round your answer to two decimal places.
If the cost of capital is 11%, what is the modified IRR (MIRR) of each project? Round your answers to two decimal places.
Project A
Project B
Regular Payback period for project A
Year | Project A | Cumualtive cash flow |
0 | -24 | -24 |
1 | 5 | -19 |
2 | 10 | -9 |
3 | 15 | 6 |
4 | 20 | 26 |
Regular paynack period = Last year of negative cumulative cash flow + absolute value of cumulative cash flow that year / Cash flow next year
Regular Payback period for project A = 2 +9/15 = 2.60 Years
Regular Payback period for Project B
Year | Project B | Cumualtive cash flow |
0 | -24 | -24 |
1 | 20 | -4 |
2 | 10 | 6 |
3 | 8 | 14 |
4 | 6 | 20 |
Regular payback period for project B = 1 + 4/10 = 1.4 Years
Discounted payback for project A
Year | Project A | Duiscounted Cash flow | Cumualtive cash flow |
0 | -24 | -24.00 | -24.00 |
1 | 5 | 4.50 | -19.50 |
2 | 10 | 8.12 | -11.38 |
3 | 15 | 10.97 | -0.41 |
4 | 20 | 13.17 | 12.76 |
Discounted payback for Project A = 3 + 0.41/13.17 = 3.03 Years
Discounted payabck for Project B
Year | Project B | Duiscounted Cash flow | Cumualtive cash flow |
0 | -24 | -24.00 | -24.00 |
1 | 20 | 18.02 | -5.98 |
2 | 10 | 8.12 | 2.13 |
3 | 8 | 5.85 | 7.98 |
4 | 6 | 3.95 | 11.94 |
Discounted payback for Project B = 1 + 5.98/8.12 = 1.74 Years
If the two projects are independent at 11% cost of capital, we calculate the NPV of both projects
Year | Project A |
0 | -24 |
1 | 5 |
2 | 10 |
3 | 15 |
4 | 20 |
NPV | $ 12.76 |
Year | Project B |
0 | -24 |
1 | 20 |
2 | 10 |
3 | 8 |
4 | 6 |
NPV | $ 11.94 |
Since both Projects A and B have positive NPV, both of them can be selected since they are independent
If the two projects are mutually exclusive at 5% cost of capital, we calculate the NPV of both projects
Year | Project A |
0 | -24 |
1 | 5 |
2 | 10 |
3 | 15 |
4 | 20 |
NPV | $ 19.24 |
Year | Project B |
0 | -24 |
1 | 20 |
2 | 10 |
3 | 8 |
4 | 6 |
NPV | $ 15.96 |
Since at 5%, project A has a higher NPV, Project A should be selected
If the two projects are mutually exclusive at 15% cost of capital, we calculate the NPV of both projects
Year | Project A |
0 | -24 |
1 | 5 |
2 | 10 |
3 | 15 |
4 | 20 |
NPV | $ 9.21 |
Year | Project B |
0 | -24 |
1 | 20 |
2 | 10 |
3 | 8 |
4 | 6 |
NPV | $ 9.64 |
Since at 15%, project B has a higher NPV, Project B should be selected
Cross over rate is the internal rate of return (IRR) of the differential cash flow between the two projects
Year | Project A | Project B | Difference |
0 | -24 | -24 | 0 |
1 | 5 | 20 | -15 |
2 | 10 | 10 | 0 |
3 | 15 | 8 | 7 |
4 | 20 | 6 | 14 |
CROSS OVER RATE | 13.53% |
MIRR of the two projects at 11%
Year | Project A |
0 | -24 |
1 | 5 |
2 | 10 |
3 | 15 |
4 | 20 |
MIRR of Project A | 23.49% |
Year | Project B |
0 | -24 |
1 | 20 |
2 | 10 |
3 | 8 |
4 | 6 |
MIRR of Project B | 22.79% |