In: Finance
Your division is considering two investment projects, each of which requires an up-front expenditure of $14 million. You estimate that the investments will produce the following net cash flows:
Year
Year | $5,000,000 | $20,000,000 | |
1 | 10,000,000 | 10,000,000 | |
2 | 20.000.000 | 6,000,000 | |
3 |
a. What are the two project’s NPVs assuming the cost of capital is 4%, 11%, 16%?
b. What are the two projects’ IRRs at those same costs of capital?
answer a) | ||||||||||||
Present value computation | Present value computation | |||||||||||
Year | Project A | PVIF @ 4% | PVIF @ 11% | PVIF @ 16% | PV @ 4% | PV @ 11% | PV @ 16% | |||||
0 | -14000000 | 1 | 1 | 1 | (14,000,000) | (14,000,000) | (14,000,000) | |||||
1 | 5000000 | 0.96154 | 0.9009 | 0.86207 | 4,807,692 | 4,504,505 | 4,310,345 | |||||
2 | 10000000 | 0.92456 | 0.81162 | 0.74316 | 9,245,562 | 8,116,224 | 7,431,629 | |||||
3 | 20000000 | 0.889 | 0.73119 | 0.64066 | 17,779,927 | 14,623,828 | 12,813,153 | |||||
NPV = | 17,833,182 | 13,244,556 | 10,555,127 | |||||||||
Year | Project B | PVIF @ 4% | PVIF @ 11% | PVIF @ 16% | PV @ 4% | PV @ 11% | PV @ 16% | |||||
0 | -14000000 | 1 | 1 | 1 | (14,000,000) | (14,000,000) | (14,000,000) | |||||
1 | 20000000 | 0.96154 | 0.9009 | 0.86207 | 19,230,769 | 18,018,018 | 17,241,379 | |||||
2 | 10000000 | 0.92456 | 0.81162 | 0.74316 | 9,245,562 | 8,116,224 | 7,431,629 | |||||
3 | 6000000 | 0.889 | 0.73119 | 0.64066 | 5,333,978 | 4,387,148 | 3,843,946 | |||||
NPV= | 19,810,310 | 16,521,391 | 14,516,954 | |||||||||
answer b) | IRR : we have to use trial and error method to compute IRR. IRR is the rate at which NPV = ZERO | |||||||||||
Lets use 48% and 49% for project A | ||||||||||||
Year | Project A | PVIF @ 48% | PVIF @ 49% | PV @ 48% | PV @ 49% | |||||||
0 | -14000000 | 1 | 1 | (14,000,000) | (14,000,000) | |||||||
1 | 5000000 | 0.67568 | 0.67114 | 3,378,378 | 3,355,705 | |||||||
2 | 10000000 | 0.45654 | 0.45043 | 4,565,376 | 4,504,302 | |||||||
3 | 20000000 | 0.30847 | 0.3023 | 6,169,427 | 6,046,042 | |||||||
113,182 | (93,951) | |||||||||||
IRR = | ||||||||||||
Lower rate +(Lower rate NPV/(Lower rate NPV-Higher rate NPV))*Difference in rate | ||||||||||||
=48%+(113182/(113182--93951))*1% | ||||||||||||
48.55% | ||||||||||||
Lets use 91% and 92% for project B | ||||||||||||
Year | Project A | PVIF @ 91% | PVIF @ 92% | PV @ 91% | PV @ 92% | |||||||
0 | -14000000 | 1 | 1 | (14,000,000) | (14,000,000) | |||||||
1 | 20000000 | 0.52356 | 0.52083 | 10,471,204 | 10,416,667 | |||||||
2 | 10000000 | 0.27412 | 0.27127 | 2,741,153 | 2,712,674 | |||||||
3 | 6000000 | 0.14352 | 0.14129 | 861,095 | 847,711 | |||||||
73,452 | (22,949) | |||||||||||
IRR = | ||||||||||||
Lower rate +(Lower rate NPV/(Lower rate NPV-Higher rate NPV))*Difference in rate | ||||||||||||
=91%+(73452/(73452--22949))*1% | ||||||||||||
91.76% |