Question

In: Accounting

A firm uses activity-based costing and has the following activity rates: $100 per machine hours, $500...

A firm uses activity-based costing and has the following activity rates: $100 per machine hours, $500 per batch start, $5 per order.

The firm has two several products, including the following two.

Product 1: $100,000 revenue, $50,000 direct costs, 250 machine hours, 25 batch starts, 500 orders

Product 2: $95,000 revenue, $40,000 direct costs, 40 machine hours, 16 batch starts, 400 orders

Which of the following process improvements is the MOST profitable?

a.

Reduce both product’s batch starts by 25%.

b.

Reduce Product 1’s direct costs by 12.5%.

c.

Reduce Product 2’s orders by 50%.

d.

Reduce machine hour activity rate cost by 25%.

Solutions

Expert Solution

Current Profiablity
Product 1 Product 2
Revenue 100000 95000
Direct Costs 50000 40000
Machine Hour Costs 25000 4000
Batch Starts Costs 12500 8000
Order Costs 2500 2000
Profit 10000 41000 51000
Reduce Batch products start by 25%
Revenue 100000 95000
Direct Costs 50000 40000
Machine Hour Costs 25000 4000
Batch Starts Costs 9375 6000
Order Costs 2500 2000
Profit 13125 43000 56125
Reduce Product 1st Direct Costs by 25%
Revenue 100000 95000
Direct Costs 37500 40000
Machine Hour Costs 25000 4000
Batch Starts Costs 12500 8000
Order Costs 2500 2000
Profit 22500 41000 63500
Reduce Product 2s Order By 50%
Revenue 100000 95000
Direct Costs 50000 40000
Machine Hour Costs 25000 4000
Batch Starts Costs 12500 8000
Order Costs 1250 1000
Profit 11250 42000 53250
Reduce Machine Hour Activity Rate by 25%
Product 1 Product 2
Revenue 100000 95000
Direct Costs 50000 40000
Machine Hour Costs 18750 3000
Batch Starts Costs 12500 8000
Order Costs 2500 2000
Profit 16250 42000 58250

Most Profitable Option is Reduce 1st Products Direct cost by 25%


Related Solutions

Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $108,000 Number of moves 4,500 Engineering 165,000 Number of change orders 10,000 Other overhead 263,200 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products:Information is given as Activity Cost Pool; Amount; Activity RateSetting up batches; $59.06; per batchProcessing customer orders; $72.66; per customer orderAssembling products; $3.75; per assembly hourData concerning the two products is below:Product K91B:Number of batches = 84; number of customer orders = 32; number of assembly hours = 483Product F650:Number of batches = 50; number of customer orders = 43; number of assembly hours...
Hane Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Hane Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pools Activity Rate Assembling products $8.90 per assembly hour Processing customer orders $31.23 per customer order Setting up batches $43.72 per batch Data for one of the company's products follow: Product U94W Number of assembly hours 389 Number of customer orders 53 Number of batches 61 How much overhead cost would be assigned to Product U94W using the activity-based costing system?
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches $ 59.31 per batch Processing customer orders $ 72.81 per customer order Assembling products $ 4.00 per assembly hour Data concerning two products appear below: Product K91B Product F65O Number of batches 84 55 Number of customer orders 34 48 Number of assembly hours 488 895 How much overhead cost would be assigned to Product...
Bera Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Bera Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pools Activity Rate Assembling products $ 4.26 per assembly hour Processing customer orders $ 49.63 per customer order Setting up batches $ 77.63 per batch Data for one of the company's products follow: Product Q79P Number of assembly hours’ 266 Number of customer orders 56 Number of batches 82 How much overhead cost would be assigned to Product Q79P using the...
Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products. Activity Cost Pools Activity Rate Setting up batches $ 69.22 per batch Processing customer orders $ 26.28 per customer order Assembling products $ 12.11 per assembly hour Data concerning two products appear below: Product K52W Product X94T Number of batches 65 52 Number of customer orders 45 30 Number of assembly hours 418 161 How much overhead cost would be assigned to each...
40. Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs...
40. Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products. Activity Cost Pools Activity Rate Setting up batches $ 68.12 per batch Processing customer orders $ 25.18 per customer order Assembling products $ 11.51 per assembly hour Data concerning two products appear below: Product K52W Product X94T Number of batches 66 53 Number of customer orders 46 31 Number of assembly hours 419 162 Required: How much overhead cost would be assigned...
Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity...
Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign overhead costs to products:   Activity Cost Pools Activity Rate   Processing customer orders $95.88 per customer order   Assembling products $2.76 per assembly hour   Setting up batches $53.30 per batch Last year, Product F76D involved 3 customer orders, 496 assembly hours, and 27 batches. How much overhead cost would be assigned to Product F76D using the activity-based costing system? Multiple Choice $1,439.10 $3,095.70...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT