Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products.
Activity Cost Pools Activity Rate Setting up batches $ 69.22 per batch
Processing customer orders $ 26.28 per customer order
Assembling products $ 12.11 per assembly hour
Data concerning two products appear below:
Product K52W Product X94T
Number of batches 65 52
Number of customer orders 45 30
Number of assembly hours 418 161
How much overhead cost would be assigned to each of the two products using the company's activity-based costing system?
Statement showing computations | |||||
Particulars | Activity Rate | Activity of K52W | Cost Allocated to K52W | Activity of X94T | Cost Allocated to X94T |
Setting up batches | 69.22 | 65.00 | 4,499.30 | 52.00 | 3,599.44 |
Processing customer orders | 26.28 | 45.00 | 1,182.60 | 30.00 | 788.40 |
Assembling products | 12.11 | 418.00 | 5,061.98 | 161.00 | 1,949.71 |
Overhead cost allocated | 10,743.88 | 6,337.55 |