In: Finance
Investment Decision Rules
Problem 1
Coral, Inc. is evaluating investment opportunities and should decide between two mutually exclusive projects: B or C. Both projects require the same initial investments 18 million and generate different cash flows as follow:
IRR is the rate at which present value of perpetual cashflows equal the investment made at the start.
Part a
IRR of Project B
|
Initial investments (in Mn) |
18 |
|
Perpetual cashflows (in Mn) |
2.2 |
|
Constant growth rate |
3% |
Present value of perpetual cashflows = Cashflows / (discount rate % - growth %)
Lets take IRR of Project B to be a%; Therefore at IRR of a% present value of perpetual cashflows equal the initial investment
|
Initial investment = Present value of cashflows |
|
Initial investment = Cashflows / (discount rate% - growth %) |
|
Initial investment = Cashflows / (IRR% - growth %) |
|
Initial investment = Cashflows / (IRR% - growth %) |
|
18 = 2.2 / (a% - 3%) |
|
(a% - 3%) = 2.2 /18 |
|
(a% - 3%) = 2.2 /18 |
|
(a% - 3%) = 0.1222 |
|
a% = 0.1222 + 0.03 |
|
a% = 0.1222 + 0.03 |
|
Therefore IRR is 15.22% |
IRR of Project B
|
Initial investments (in Mn) |
18 |
|
Perpetual cashflows (in Mn) |
1.6 |
|
Constant growth rate |
4% |
Present value of perpetual cashflows = Cashflows / (discount rate % - growth %)
Lets take IRR of Project B to be b%; Therefore at IRR of a% present value of perpetual cashflows equal the initial investment
|
Initial investment = Present value of cashflows |
|
Initial investment = Cashflows / (discount rate% - growth %) |
|
Initial investment = Cashflows / (IRR% - growth %) |
|
Initial investment = Cashflows / (IRR% - growth %) |
|
18 = 1.6 / (b% - 4%) |
|
(b% - 4%) = 1.6 /18 |
|
(b% - 4%) = 1.6 /18 |
|
(b% - 4%) = 0.0889 |
|
b% = 0.0889 + 0.04 |
|
b% = 0.0889 + 0.04 |
|
Therefore IRR is 12.89% |
Part b : NPV computation
Project B
Present value of cashflows @ 10% discount rate
|
Cashflows |
2.2 |
|
Discount rate |
10% |
|
Growth rate |
3% |
|
Present value of cashflows |
Cashflows / (Discount rate - growth rate) |
|
Present value of cashflows |
2.2 / (10%-3%) |
|
Present value of cashflows |
2.2 / (10%-3%) |
|
Present value of cashflows |
31.43 |
|
Initial investment |
18 |
|
NPV (Present value of cashflows - initial investment) |
13.43 |
Project C
Present value of cashflows @ 10% discount rate
|
Cashflows |
1.6 |
|
Discount rate |
10% |
|
Growth rate |
4% |
|
Present value of cashflows |
Cashflows / (Discount rate - growth rate) |
|
Present value of cashflows |
1.6 / (10%-4%) |
|
Present value of cashflows |
1.6 / (10%-4%) |
|
Present value of cashflows |
26.67 |
|
Initial investment |
18 |
|
NPV (Present value of cashflows - initial investment) |
8.67 |
Crossover rate
Crossover rate is the discount rate at which NPV of both projects are equal. Lets assume crossover rate to be x%
|
NPV of B = NPV of C |
|
2.2 / (x%-3%) - 18 = 1.6 / (x%-4%) -18 |
|
2.2 / (x%-3%) = 1.6 / (x%-4%) |
|
2.2 / (x%-3%) = 1.6 / (x%-4%) |
|
1.6 * (x%-3%) = 2.2*(x%-4%) |
|
1.6x%-4.8% = 2.2x%-68.8% |
|
8.8%-4.8% = 2.2x%-1.6x% |
|
4% = 0.6x% |
|
x = 6.67%; therefore crossove rate is 6.67% |
NPV Table
|
Project B |
13.43 |
|
Project C |
8.67 |

Hope this helps you answer the question. Please leave your rating or feedback on the answer.
Thanks