Dunning, Inc. is trying to decide between two investment projects using NPV. Project A requires an...

Dunning, Inc. is trying to decide between two investment projects using NPV. Project A requires an initial investment of $600,000 and has annual cash inflows of $196,000 for the next 5 years. Project B has an initial investment of $400,000 and offers annual cash inflows of $88,000 over the next 7 years. Dunning, Inc. uses a 6% discount rate to evaluate investment projects.

a) Calculate the NPV for both projects and determine which investment Dunning should choose.

Solutions

Expert Solution

Solution:-

PROJECT - A NPV CALCULATION

Year

Discounting factor

(please refer to the below note)

(A)

Cash Inflow

(B)

Present value of cash inflow

   

A X B

1

.943

$196,000

$184,828

2

.890

$196,000

$174,440

3

.840

$196,000

$164,640

4

.792

$196,000

$155,232

5

.747

$196,000

$146,412

PRESENT VALUE OF TOTAL CASH INFLOW

$825,552

INITIAL INVESMENT

$600,000

Net present value

(PRESENT VALUE OF TOTAL CASH INFLOW - INITIAL INVESMENT)

$225,552



PROJECT - B NPV CALCULATION

Year

Discounting factor

(please refer to the below note)

(A)

Cash Inflow

(B)

Present value of cash inflow

    

A X B

1

.943

$88,000

$82,984

2

.890

$88,000

$78,320

3

.840

$88,000

$73,920

4

.792

$88,000

$69,696

5

.747

$88,000

$65,736

6

.705

$88,000

$62,040

7

.665

$88,000

$58,520

PRESENT VALUE OF TOTAL CASH INFLOW

$491,216

INITIAL INVESMENT

$400,000

Net present value

(PRESENT VALUE OF TOTAL CASH INFLOW - INITIAL INVESMENT)

$91,216



CONCLUSION

NPV OF PROJECT A = $225,552

NPV OF PROJECT B = $91,216

NPV of PROJECT A is greater than PROJECT B

From the above conclusion we can say that Dunning should choose PROJECT A as its NPV is greater than PROJECT B






Note - Calculation of discounting factor

Year

Discounting factor

1 / [ (1 + r)^n ]

1

1 / [(1 +0.06) ^1]

.943

2

1 / [(1 +0.06) ^2]

.890

3

1 / [(1 +0.06) ^3]

.840

4

1 / [(1 +0.06) ^4]

.792

5

1 / [(1 +0.06) ^5]

.747

6

1 / [(1 +0.06) ^6]

.705

7

1 / [(1 +0.06) ^7]

.665

If you have any doubt or query please comment.

Please upvote . Thanks


Related Solutions

4) The company you work for is trying to decide between two projects. Project 1 costs...
4) The company you work for is trying to decide between two projects. Project 1 costs $160,000 up front, and has an expected life of 4 years, over which it will return $52,000 each of the four years. Project 2 would last for 20 years, costs $1.5 million up front, and returns $170,000 at the end of each of the 20 years. Assuming a real discount rate of 6%, which project has the higher equivalent annual net benefit?
Tempura, Inc., is considering two projects. Project A requires an investment of $52,000. Estimated annual receipts...
Tempura, Inc., is considering two projects. Project A requires an investment of $52,000. Estimated annual receipts for 20 years are $22,000; estimated annual costs are $12,500. An alternative project, B, requires an investment of $71,000, has annual receipts for 20 years of $31,000, and has annual costs of $18,000. Assume both projects have a zero salvage value and that MARR is 10.0 %/year. A) What is the present worth of each project?
OpenSea, Inc. is evaluating investment opportunities and should decide between two mutually exclusive projects: A, or...
OpenSea, Inc. is evaluating investment opportunities and should decide between two mutually exclusive projects: A, or B. Both projects require the same initial investments 14 million and generate different cash flows as follow: -Project (A) generates 3.0 million per year in a perpetuity - Project (B) generates 1.9 million in perpetuity growing at 2.2% (forever) If OpenSea is using the IRR to make her final decision, calculate the IRR of each of the following project. Calculate the NPV of both...
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an...
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $24 million. You estimate that the cost of capital is 9% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places....
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an...
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $22 million. You estimate that the cost of capital is 10% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places....
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an...
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the cost of capital is 9% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places....
A company is trying to decide between TWO projects that would provide the same necessary service...
A company is trying to decide between TWO projects that would provide the same necessary service and each project can be repeated indefinitely at the same cost and same cash flows. The first project costs $7,000 and is expected to generate cash flows of $4,250 for NINE years. The second project cost $10,000 and is expected to generate cash flows of $4,400 for ELEVEN years While the replacement chain approach is a valid option, you currently cannot use a spreadsheet...
1. There are two mutually exclusive projects. Project A requires a $600,000 initial investment and is...
1. There are two mutually exclusive projects. Project A requires a $600,000 initial investment and is expected to provide $120,000 annual net cash inflows for 6 years. Project B requires a $740,000 initial investment and is expected to provide $200,000 annual net cash inflows for 4 years. Which project should you accept according to IRR method when your cost of capital is 10%? A. Project A B. Project B C. Both D. Neither of these 2. Leveraged IRR: A. estimates...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT