In: Finance
Galbraith Co. is considering a four-year project that will require an initial investment of $12,000. The base-case cash flows for this project are projected to be $14,000 per year. The best-case cash flows are projected to be $20,000 per year, and the worst-case cash flows are projected to be a -$2,500 per year. The company's analysts have estimated that there is a 50% probability that the project will generate the base-case cash flows. The analysts also think that there is a 25% probability of the project generating the best-case cash flows and a 25% probability of the project generating the worst-case cash flows.
What would be the expected net present value (NPV) of this project if the project's cost of capital is 10%?
(a) $22,365 (b) $26,093 (c) $24,850 (d) $19,880
Galbraith now wants to take into account its ability to abandon the project at the end of year 2 if the project ends up generating the worst-case scenario cash flows. If it decides to abandon the project at the end of year 2, the company will receive a one-time net cash inflow of $4,000 (at the end of year 2). The $4,000 the company receives at the end of year 2 is the difference between the cash the company receives from selling off the project's assets and the company's -$2,500 cash outflow from operations. Additionally, if it abandons the project, the company will have no cash flows in years 3 and 4 of the project.
Using the information in the preceding problem, find the expected NPV of this project when taking the abandonment option into account.
(a) $227.089 (b) $24,380 (c) $29,798 (d) $31,152
What is the value of the option to abandon the project?
(a) $1,567 (b) $2,239 (c) $2,351 (d) $2,463 (e) $1,791
Scenario 1:
Expected cash flow per year= 50%*14000+25%*20000+25%*(-2500)=$11375
Now, below is the calculation for the NPV:
Year | Cash Flow | Present Value (CashFlow/1.1^year) |
0 | (12,000.00) | (12,000.00) |
1 | 11,375.00 | 10,340.91 |
2 | 11,375.00 | 9,400.83 |
3 | 11,375.00 | 8,546.21 |
4 | 11,375.00 | 7,769.28 |
NPV (Total of Present Value) | 24,057.22 |
So, Expected NPV is $24057.22
Scenario 2:
When the project is abandoned at the end 2nd year, below is the calculation for NPV:
Year | Cash Flow | Present Value (CashFlow/1.1^year) |
0 | (12,000.00) | (12,000.00) |
1 | (2,500.00) | (2,272.73) |
2 | 4,000.00 | 3,305.79 |
NPV (Total of Present Value) | (10,966.94) |