Expert Solution

Drawing of any project is very important as it will give many assumptions and estimations regarding the structure and the project. Often the project managers, developers and the contractors have meetings regarding the drawings of the project. The major points which are being discussed regarding the drawing of the project is it's dimension, scale and aesthetic views of the drawing. The cost estimation is also assumed by the drawing itself as the amount of material used and the construction area would also be calculated. The contractors would always request from the developers that the design of the project should be least complex or we can say it should be as simple as possible while the project manager would demand for a quality drawing so it's on the developer to make such a drawing by which both may be satisfied and it would be regarded as a quality work.

There are many issues also while dealing with the project drawings in the construction field. One of the major issue is that in many cases the drawing is not being completed due to the casualties and mistakes done by the developers. Below are listed some more problems other than the one discussed regarding common problems in project drawing :

  • Many of the plans are not being well coordinated. Change of orders may usually occur which may cause problems to the contractor while obtaining or implementing any dimension.
  • The drawing may lack detailing. Details need to be provided for each and every small thing regarding the dimension, quantity and the materials used in the project.
  • PCR provider may review the wrong set. It will reduce the accuracy and reliability of the PCR.

Related Solutions

You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Discuss how can a project manager prepare a project final report ?
Discuss how can a project manager prepare a project final report ?
Discuss how can a project manager prepare a project final report ?
Discuss how can a project manager prepare a project final report ?
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
Consider the following relation schema about project meetings: PMG(projID, title, type, manager, jobID, start-date, end-date, contractor,...
Consider the following relation schema about project meetings: PMG(projID, title, type, manager, jobID, start-date, end-date, contractor, contractNo) Some notes on the semantics of attributes are as follows: • Each project has a unique project ID (projID) and also has a title, type and manager. Each manager has a specialty project type. • A project often contracts jobs to contractors with start-date and end-date. Contracts are identified by contract numbers (contractNo), but contract details are out of the scope of the...
Samsung. is considering a project that has the following cash flow data. What is the project's...
Samsung. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC or negative, in both cases it will be rejected. Year 0 1 2 3 Cash flows -$1,025 $425 $425 $425
Discuss clearly, what is meant by resource smoothing and what steps would a project manager in...
Discuss clearly, what is meant by resource smoothing and what steps would a project manager in a project of your choice, undertake to smooth a resource?
How (by what way) is each detail drawing connected with the assembly drawing of the design?...
How (by what way) is each detail drawing connected with the assembly drawing of the design? (keep your answer brief and concise, all lower cases) HTML EditorKeyboard Shortcuts
discuss briefly some of the roles of a project manager
discuss briefly some of the roles of a project manager
Discuss in detail what should a project manager do to prepare cost baseline.
Discuss in detail what should a project manager do to prepare cost baseline.