Question

In: Economics

Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project....

  1. Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project.
  2. Outline the six main steps of the PERT method for project management.
  3. Explain why it is important to consider project budgets and other resources in project design.

Solutions

Expert Solution

A Gantt chart is basically a type of bar chart which shows a visual representation of tasks v/s time. It gives information like duration of the task(work done) that is time taken to complete the required task,it shows start-to-end date and the order of task. It basically shows how much work is completed in the project.It measure the progress of project-you can get to know how much project is completed and if your project is lagging behind or not. Gantt chat help us to practice time management-one can easily assign time to each and every task.

the six main steps of the PERT method for project management are as follows:

1.identify the specific activities and milestones

-The activities means the tasks or work required to make a project complete. The milestones means the events that mark the start & the end of one or more than one activities.

2.determine the correct order  of activities

-We can combine this step with the first step because the sequence of activity is evident for some tasks. Other tasks might require some more analysis to know the proper sequence in which they must be performed.

3.construct network diagram

-by using the sequence of the activities a network diagram has to be drawn that shows the sequence of the serial and parallel activities. In order to make this step easy the software packages automatically transform tabular activity information into a network diagram.

4.estimate time requires for each activity

For completion of activity, weeks are mostly used as a unit of time, but it is not compulsory to use only weeks as a unnit of time. One can use any consistent unit of time.

5.determine the critical path

To determine the critical path we allocate the time for the activities in each sequence and determine the path which is longest in the project. The critical path is used for determining the total calendar time that it requires for the project completion.

6.Update the Pert chart as the project progresses

-as and when new tasks are done update the perk chart.

The importance of considering project budgets is that it helps us to avoid unnecessary expenditure and helps us to spend the amount wisely.. Project budgeting is done to get rough estimate of the project costs and to know if it fits in their budget.If there is no project budgets then the company or firm can easily lose money and costs can rise above the project profit.Other project resources are people capital and material goods.These are required for successful completion of the project. If there is a lack of project resources the progress of the project will most likely stop or it may cause the project to run behind schedule.


Related Solutions

discuss how using a Gantt chart in a project charter can be an effective method in...
discuss how using a Gantt chart in a project charter can be an effective method in project management. Please provide a case study to demonstrate your point. OR, this can be based on experience. If you are basing this on experience, you will need to be able to cite the project and share its details.
Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend...
Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress. Discuss the significance of the two paths or what they mean to the project. Activity immediate predecessors normal time budget organizational unit percent complete A - 4 $90 U1 100 B A 2 $35 U2 100 C A 6 $75 U2 40 D B 3 $60 U1 80 E C 10 $80 U1 0...
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup...
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual. Project: Vacation Team: "Workgroup 1", "Individual" Start/End: February 19 - May 26 START A. February 19: Vacation participation must be confirmed Time allotted: 7 days i. Confirm participation Time needed: 1 day ii. Research vacation deals Time needed: 1 days iii. Decide on destination Time needed: 2 days iv. Create travel list Time needed: 1 day Slack available: 2 days B. February...
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a...
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a computerised Human Resource Information system. The company is switching to paper less. A WBS has to be created/invented for the new project
Compare the main strengths and weaknesses of the Gantt chart and PERT for project management, and...
Compare the main strengths and weaknesses of the Gantt chart and PERT for project management, and give your opinion on which you believe is the most effective for project management.
Need assistance with developing a Gantt Chart for a project plan for system development. Looking to...
Need assistance with developing a Gantt Chart for a project plan for system development. Looking to create an application for a health food company. They have published books and part of the plan is to convert to digital as well as making the application readily available via mobile. I want to know as far as resources go, the team will be made up of project manager, systems analyst, web/software developer, and research. How do I know what the cost and...
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of...
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of them and discuss how they relate to each other. Given the system goals, requirements, and scope as they are currently understood, is the project schedule reasonable? Why or why not?
Hi Guys! How do I prepare gantt chart including activities and time for a project developing...
Hi Guys! How do I prepare gantt chart including activities and time for a project developing a website?
Discuss the benefits of cloud computing in a brief  paragraph
Discuss the benefits of cloud computing in a brief  paragraph
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT