Question

In: Operations Management

Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend...

  1. Develop a Gantt Chart based on Table below.
  2. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.
  3. Discuss the significance of the two paths or what they mean to the project.
Activity immediate predecessors normal time budget organizational unit percent complete
A - 4 $90 U1 100
B A 2 $35 U2 100
C A 6 $75 U2 40
D B 3 $60 U1 80
E C 10 $80 U1 0
F - 2 $40 U2 100
G F 5 $55 U1 50
H F 7 $80 U2 100
I D,E,G 1 $40 U2 0
J H 10 $100 U1 0

Solutions

Expert Solution

Gantt chart is following:

Resource loading chart:

Actual progress is shown on the Gantt chart as below:

Completion status is indicated by green color bar.

Four alternative paths in the project and their respective duration are following:

A-B-D-I 10
A-C-E-I 21
F-G-I 8
F-H-J 19

The longest path is the critical path, which is A-C-E-I

Significance of the critical path is that, its duration is the duration of the entire project.

Another significance of the critical path is that all the activities on critical path have 0 slack. Therefore, any delay in any of the critical path activities results in a delay in overall project.

The other three paths are non-critical. Slack of any path is equal to the difference between the duration of the critical path and the duration of that path. Slack of any activity is equal to the difference between the duration of the critical path and the duration of the longest path on which that activity lies.

Significance of the non-critical path is that, resources from non-critical activities can be diverted to expedite critical activities, up to the limit of slack of non-critical activity. This may expedite the completion of critical activities and eventually the entire project may be completed on or before time.


Related Solutions

Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup...
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual. Project: Vacation Team: "Workgroup 1", "Individual" Start/End: February 19 - May 26 START A. February 19: Vacation participation must be confirmed Time allotted: 7 days i. Confirm participation Time needed: 1 day ii. Research vacation deals Time needed: 1 days iii. Decide on destination Time needed: 2 days iv. Create travel list Time needed: 1 day Slack available: 2 days B. February...
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project....
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project. Outline the six main steps of the PERT method for project management. Explain why it is important to consider project budgets and other resources in project design.
Detail the steps in an implementation plan (Gantt Chart) for fire and safety management based on...
Detail the steps in an implementation plan (Gantt Chart) for fire and safety management based on the five project management process groups .
Gantt chart for home renovation project
Gantt chart for home renovation project
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between...
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours                                  Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 Which department is the bottleneck? Calculate the machine utilization?
Contractor Use of WBS and Gantt Chart As stated above, the buyer organization generally prepares a...
Contractor Use of WBS and Gantt Chart As stated above, the buyer organization generally prepares a WBS and Gantt chart internally as part of its project planning. When there is to be an acquisition of IT services from an external source, the WBS and Gantt chart, as well as other aspects of the implementation plan, are likely to be modified by the selected contractor's proposal and the final negotiated contract. The contractor will likely take the negotiated WBS and Gantt...
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a...
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a computerised Human Resource Information system. The company is switching to paper less. A WBS has to be created/invented for the new project
can i have sample of gantt chart with resource loading
can i have sample of gantt chart with resource loading
Use the table below to answer questions 4.5 – 4.7: This table contains the same client...
Use the table below to answer questions 4.5 – 4.7: This table contains the same client data as the first table. This time, though, the instructor is interested in knowing how his clients’ other activities might impact their average cycling speed in spin class. He notes that half of his clients also ride bikes outside during the week, while the other half of his clients do not bike anywhere except spin class. Rides Outside Only Spin Rides Outside Only SPin...
Homework 16:   Complete the MRP chart below. A(1) B(2) C(4) D(1) LEGEND: A to F are...
Homework 16:   Complete the MRP chart below. A(1) B(2) C(4) D(1) LEGEND: A to F are part numbers E(2) E(2) F(2) F(1) (n) is number of children needed for                                                                                                                       each parent Part A: Lead-time = 1 week OQ = LFL Safety Stock = 0 1 2 3 4 5 6 7 8 1. Gross Requirements 30 15 50 60 50 10 2. Scheduled Receipts 3. Projected On Hand         60 4. Net Requirements 5. Planned Order Receipt 6. Planned Order...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT