Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup...

Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual.

Project: Vacation
Team: "Workgroup 1", "Individual"
Start/End: February 19 - May 26

START

A. February 19: Vacation participation must be confirmed
Time allotted: 7 days

i. Confirm participation
Time needed: 1 day

ii. Research vacation deals
Time needed: 1 days

iii. Decide on destination
Time needed: 2 days

iv. Create travel list
Time needed: 1 day

Slack available: 2 days


B. February 26: Lodging and excursion reservations must be made
Time allotted: 18 days

i. Research lodging options
Time needed: 3 days

ii. Make lodging reservation
Time needed: 1 Day

iii. Research and reserve excursions
Time needed: 5 days

iv. Make payment
Time needed: 1 days

Slack available: 8 days


C. March 16: All travel must be booked and confirmed
Time allotted: 57 days


i. Payment Status
Time needed: 3 days

ii. Reservation Status
Time needed: 1 day

iii. Pack
Time needed: 3 days

Slack available: 50 days

D. May 11: Check in to flights early
Time allotted: 1 day

i. Check into airport online
Time needed: 2 hours

ii. Receive itinerary/tickets
Time needed: 2 hours

iii. Call and reserve cab to airport
Time needed: 1 hour

Slack available: 20 hours, 30 minutes

E. May 12: Travel, Arrive at hotel (no later than 6:00 PM)
Time allotted: 18 hours

i. Board plane and fly to destination
Time needed: 6 hours

ii. Arrive at destination and grab luggage
Time needed: 2 hours

iii. Take shuttle to hotel and check in
Time needed: 3 hours

Slack available: 7 hours

F. May 12- May 25: Arrive at destination (Relax!)
Time allotted: 12 days

i. Unpack and get acquainted with hotel and surroundings
Time needed: 3 hours

ii. Relax, eat, dance, shop, explore
Time needed: 4-12 days

iii. Excursions
Time needed: 4-12 days

Slack available: 0-4 days

G. May 26th: Travel, Shuttle departs to airport at 11:00 AM (G)
Time allotted: 11 hours

i. Pack up all belongings and check out of hotel
Time needed: 3 hours

ii. Board shuttle at 11am at designated area
Time needed: less than 5 minutes

Slack time: 7 hours and 55 minutes

H. Arrive at airport and fly home

END

Solutions

Expert Solution

Image of the gantt chart:
The data is provided in a tabular form below:

Activity Start Date Duration End Date
Confirm Participation 2/19/2018 1 2/20/2018
Research vacation deals 2/20/2018 1 2/21/2018
Decide on destination 2/21/2018 2 2/23/2018
Create travel list 2/23/2018 1 2/24/2018
Slack 2/24/2018 2 2/26/2018
Research lodging options 2/26/2018 3 3/1/2018
Make lodging reservation 3/1/2018 1 3/2/2018
Research and reserve excursions 3/2/2018 5 3/7/2018
Make payment 3/7/2018 1 3/8/2018
Slack 3/8/2018 8 3/16/2018
Payment Status 3/16/2018 3 3/19/2018
Reservation Status 3/19/2018 1 3/20/2018
Pack 3/20/2018 3 3/23/2018
Slack 3/23/2018 49 5/11/2018
Check into airport online 5/11/2018 0.083 5/11/2018
Receive itinerary/tickets 5/11/2018 0.083 5/11/2018
Call and reserve cab to airport 5/11/2018 0.041 5/11/2018
Slack 5/11/2018 0.854 5/12/2018
Board plane and fly to destination 5/12/2018 0.25 5/12/2018
Arrive at destination and grab luggage 5/12/2018 0.083 5/12/2018
Take shuttle to hotel and check in 5/12/2018 0.125 5/12/2018
Slack 5/12/2018 0.291 5/12/2018
Unpack and get acquainted with hotel and surroundings 5/12/2018 0.125 5/12/2018
Relax, eat, dance, shop, explore 5/12/2018 4 5/16/2018
Excursions 5/16/2018 6 5/22/2018
Slack 5/22/2018 3.875 5/26/2018
Pack up all belongings and check out of hotel 5/26/2018 0.125 5/26/2018
Board shuttle at 11am at designated area 5/26/2018 0.003 5/26/2018
Slack 5/26/2018 0.329 5/27/2018

Related Solutions

Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend...
Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress. Discuss the significance of the two paths or what they mean to the project. Activity immediate predecessors normal time budget organizational unit percent complete A - 4 $90 U1 100 B A 2 $35 U2 100 C A 6 $75 U2 40 D B 3 $60 U1 80 E C 10 $80 U1 0...
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of...
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of them and discuss how they relate to each other. Given the system goals, requirements, and scope as they are currently understood, is the project schedule reasonable? Why or why not?
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Gantt chart for home renovation project
Gantt chart for home renovation project
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project....
Discuss (in a paragraph below) the benefits of using a GANTT chart for managing a project. Outline the six main steps of the PERT method for project management. Explain why it is important to consider project budgets and other resources in project design.
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a...
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a computerised Human Resource Information system. The company is switching to paper less. A WBS has to be created/invented for the new project
Compare the main strengths and weaknesses of the Gantt chart and PERT for project management, and...
Compare the main strengths and weaknesses of the Gantt chart and PERT for project management, and give your opinion on which you believe is the most effective for project management.
Create a project schedule based on task dependencies and resource constraints
Create a project schedule based on task dependencies and resource constraints
Detail the steps in an implementation plan (Gantt Chart) for fire and safety management based on...
Detail the steps in an implementation plan (Gantt Chart) for fire and safety management based on the five project management process groups .
Need assistance with developing a Gantt Chart for a project plan for system development. Looking to...
Need assistance with developing a Gantt Chart for a project plan for system development. Looking to create an application for a health food company. They have published books and part of the plan is to convert to digital as well as making the application readily available via mobile. I want to know as far as resources go, the team will be made up of project manager, systems analyst, web/software developer, and research. How do I know what the cost and...