Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual.
Project: Vacation
Team: "Workgroup 1", "Individual"
Start/End: February 19 - May 26
START
A. February 19: Vacation participation must be
confirmed
Time allotted: 7 days
i. Confirm participation
Time needed: 1 day
ii. Research vacation deals
Time needed: 1 days
iii. Decide on destination
Time needed: 2 days
iv. Create travel list
Time needed: 1 day
Slack available: 2 days
B. February 26: Lodging and excursion reservations must be
made
Time allotted: 18 days
i. Research lodging options
Time needed: 3 days
ii. Make lodging reservation
Time needed: 1 Day
iii. Research and reserve excursions
Time needed: 5 days
iv. Make payment
Time needed: 1 days
Slack available: 8 days
C. March 16: All travel must be booked and confirmed
Time allotted: 57 days
i. Payment Status
Time needed: 3 days
ii. Reservation Status
Time needed: 1 day
iii. Pack
Time needed: 3 days
Slack available: 50 days
D. May 11: Check in to flights early
Time allotted: 1 day
i. Check into airport online
Time needed: 2 hours
ii. Receive itinerary/tickets
Time needed: 2 hours
iii. Call and reserve cab to airport
Time needed: 1 hour
Slack available: 20 hours, 30 minutes
E. May 12: Travel, Arrive at hotel (no later than 6:00
PM)
Time allotted: 18 hours
i. Board plane and fly to destination
Time needed: 6 hours
ii. Arrive at destination and grab luggage
Time needed: 2 hours
iii. Take shuttle to hotel and check in
Time needed: 3 hours
Slack available: 7 hours
F. May 12- May 25: Arrive at destination (Relax!)
Time allotted: 12 days
i. Unpack and get acquainted with hotel and surroundings
Time needed: 3 hours
ii. Relax, eat, dance, shop, explore
Time needed: 4-12 days
iii. Excursions
Time needed: 4-12 days
Slack available: 0-4 days
G. May 26th: Travel, Shuttle departs to airport at 11:00
AM (G)
Time allotted: 11 hours
i. Pack up all belongings and check out of hotel
Time needed: 3 hours
ii. Board shuttle at 11am at designated area
Time needed: less than 5 minutes
Slack time: 7 hours and 55 minutes
H. Arrive at airport and fly home
END
Image of the gantt chart:
The data is provided in a
tabular form below:
Activity | Start Date | Duration | End Date |
Confirm Participation | 2/19/2018 | 1 | 2/20/2018 |
Research vacation deals | 2/20/2018 | 1 | 2/21/2018 |
Decide on destination | 2/21/2018 | 2 | 2/23/2018 |
Create travel list | 2/23/2018 | 1 | 2/24/2018 |
Slack | 2/24/2018 | 2 | 2/26/2018 |
Research lodging options | 2/26/2018 | 3 | 3/1/2018 |
Make lodging reservation | 3/1/2018 | 1 | 3/2/2018 |
Research and reserve excursions | 3/2/2018 | 5 | 3/7/2018 |
Make payment | 3/7/2018 | 1 | 3/8/2018 |
Slack | 3/8/2018 | 8 | 3/16/2018 |
Payment Status | 3/16/2018 | 3 | 3/19/2018 |
Reservation Status | 3/19/2018 | 1 | 3/20/2018 |
Pack | 3/20/2018 | 3 | 3/23/2018 |
Slack | 3/23/2018 | 49 | 5/11/2018 |
Check into airport online | 5/11/2018 | 0.083 | 5/11/2018 |
Receive itinerary/tickets | 5/11/2018 | 0.083 | 5/11/2018 |
Call and reserve cab to airport | 5/11/2018 | 0.041 | 5/11/2018 |
Slack | 5/11/2018 | 0.854 | 5/12/2018 |
Board plane and fly to destination | 5/12/2018 | 0.25 | 5/12/2018 |
Arrive at destination and grab luggage | 5/12/2018 | 0.083 | 5/12/2018 |
Take shuttle to hotel and check in | 5/12/2018 | 0.125 | 5/12/2018 |
Slack | 5/12/2018 | 0.291 | 5/12/2018 |
Unpack and get acquainted with hotel and surroundings | 5/12/2018 | 0.125 | 5/12/2018 |
Relax, eat, dance, shop, explore | 5/12/2018 | 4 | 5/16/2018 |
Excursions | 5/16/2018 | 6 | 5/22/2018 |
Slack | 5/22/2018 | 3.875 | 5/26/2018 |
Pack up all belongings and check out of hotel | 5/26/2018 | 0.125 | 5/26/2018 |
Board shuttle at 11am at designated area | 5/26/2018 | 0.003 | 5/26/2018 |
Slack | 5/26/2018 | 0.329 | 5/27/2018 |