As described in earlier chapters, your Global Treps team would pay for a new website and account through an online provider. Bobby would do most of the customization and programming for the site, but you would consider outsourcing or purchasing services to provide some of the capabilities like accepting donations and developing the short videos on the site. You would also buy a new laptop and Internet access for your three team members abroad, which they could share with their contacts in those countries. You have budgeted $20,000 for outsourced hardware and software. The actives listed in your WBS for outsourced software development include:
1 |
Initiate Project |
1.1 |
Develop Project Charter |
1.1.1 |
Define Scope |
1.1.2 |
Define Requirements |
1.1.3 |
Identify High-Level Roles |
1.1.4 |
Develop High-Level Budget |
1.1.5 |
Identify High-Level Control Strategies |
1.1.6 |
Finalize Charter and Gain Approvals |
1.1.6.1 |
Consolidate and Publish Project Charter |
1.1.6.2 |
Hold Review Meeting |
1.1.6.3 |
Revise Project charter |
1.1.6.4 |
Gain approvals |
2 |
Plan Project |
2.1 |
Develop Work Plan |
2.1.1 |
Develop Work Breakdown Structure |
2.1.2 |
Develop Project Staffing Plan |
2.1.3 |
Develop Project Schedule |
2.1.4 |
Develop Project Budget |
2.2 |
Develop Project Control Plan |
2.2.1 |
Develop Communication Plan |
2.2.2 |
Develop Quality Management Plan |
2.3 |
Finalize Project Plan and Gain Approvals |
3 |
Execute and Control Project |
3.1 |
SRS (Software requirements specification ) Development |
3.1.1 |
Define stages and activities |
3.1.2 |
Design content formats |
3.1.3 |
Requirement review and approval |
3.2 |
SRS Signed and Approved |
3.3 |
Software and hardware design |
3.4 |
Design Doc Created |
3.5 |
Detailed design signed and approved |
4.0 |
Software Testing/Verification |
4.1 |
Test usability of web tool |
4.2 |
Test usability of content |
4.3 |
Adjust framework based on user feedback |
4.4 |
Implement Framework |
4.4.1 |
Move framework to production environment |
4.4.2 |
Announce availability of framework |
5 |
Close the Project |
4.1 |
Conduct Post-Project Review |