Question

In: Economics

Arwin and Dewi are neighbors that work for the same company in the same office building....

Arwin and Dewi are neighbors that work for the same company in the same office

building. Each morning they both have the choice to commute to work by car or by bicycle. The

road to their office is narrow and in poor condition. Arwin and Dewi are the only people who

travel on this road at this particular time in the morning. If both choose to commute by car it

takes each of them 17 minutes to get to work. However, if there is just one car on the road

traveling the time is reduced to 8 minutes. Commuting by bicycle is generally quite fast: it only

takes 12 minutes if there are no cars. However the local law gives priority to the cars on the

road. As a result, it takes 22 minutes to reach the destination by bicycle if another person

decides to drive at the same time. Both Arwin and Dewi seek to minimize their commute times

each morning to reach the office in the shortest amount of time possible.

a. Using the information above, create the payoff matrix for this game.

Solutions

Expert Solution

A) There are two commuters: Arwin and Dewi. There are two modes of commute: car and bicycle.

If both of them travel by car, it takes each of them 17 minutes to get to work.

If one of them travels by car, then his commute time is reduced to 8 minutes. On the other hand the person who chooses to commute by bicycle, due to the local law giving priority to the cars on the road, it takes 22 minutes to reach the destination.

If both of them travel by bicycle, it takes each of them 12 minutes to get to work.

The payoff matrix has been depicted in table given below. The first number in parenthesis denotes the payoff of Arwin to commute and the second number denotes the payoff of Dew to commute. These are negative because each of them wants to reach the office in the shortest amount of time possible, so the less time it takes the better or the higher payoff they receive.

Please drop a thumbs up if you found this answer helpful. Thanks!


Related Solutions

The customer has asked to have a customer representative office set up in the same building...
The customer has asked to have a customer representative office set up in the same building as the project office. As a project manager, you put the customer’s office at the opposite end of the building from where you are, and on a different floor. The customer states that he wants his office next to yours. Should this be permitted, and, if so, under what conditions?
If a company experiences a complete loss of an office building as a result of a...
If a company experiences a complete loss of an office building as a result of a fire and receives a $2 million recovery payment from the insurance company: Explain the tax consequences if the company decides not to rebuild. Identify the tax consequences if the company distributes the $2 million to its two (2) shareholders, assuming that no stock was exchanged in return. Under what conditions will the distribution meet the requirements to be treated as a partial liquidation and...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During 2020, Stellar, Inc. incurred costs of $1,941,020, billed its customers for $1,138,000, and collected $904,000. At December 31, 2020, the estimated additional costs to complete the project total $3,304,980. Prepare Stellar’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,639,900, billed its customers for $1,300,000, and collected $1,055,000. At December 31, 2020, the estimated additional costs to complete the project total $3,650,100. Prepare Sarasota’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Concord, Inc. began work on a $6,466,000 contract in 2017 to construct an office building. During...
Concord, Inc. began work on a $6,466,000 contract in 2017 to construct an office building. During 2017, Concord, Inc. incurred costs of $1,547,340, billed its customers for $1,085,000, and collected $1,013,000. At December 31, 2017, the estimated additional costs to complete the project total $3,003,660. Prepare Concord’s 2017 journal entries using the percentage-of-completion method.
Culver, Inc. began work on a $6,391,000 contract in 2017 to construct an office building. During...
Culver, Inc. began work on a $6,391,000 contract in 2017 to construct an office building. During 2017, Culver, Inc. incurred costs of $1,867,020, billed its customers for $1,209,000, and collected $908,000. At December 31, 2017, the estimated additional costs to complete the project total $3,178,980. Prepare Culver’s 2017 journal entries using the percentage-of-completion method.
The ZMH Company has two divisions, Corporate Office Systems and Home Office Systems. You are building...
The ZMH Company has two divisions, Corporate Office Systems and Home Office Systems. You are building the budget for Home Office Systems. The forecast included 2019 year's sales of $35,000,000. There was a common sales team for both devisions. 35% of the sales team would be dedicated to Home Office Systems. Sales reps for Home Office would earn a 20% commission on sales of Home Office Systems. Home Office Systems would be charged for 35% of the fixed direct costs...
Q2. XYZ company is considering building a new office building.  XYZ already owns a plot of land...
Q2. XYZ company is considering building a new office building.  XYZ already owns a plot of land worth $2M and has paid an architectural firm $300k for building designs.  Construction cost for the building is $1M.  Projected rent income from the building is $400k/year and interest expense will be $300k/year.  After three years XYZ expects to sell the building and land for $2.5M.  If XYZ has a required rate of return of 10%, what is the NPV and IRR of building the office building? Please...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT