Question

In: Finance

commute the irr static for a project e the appropriatecost of capital is 9%commute...

commute the irr static for a project e the appropriate cost of capital is 9%

commute the irr static for project e the appropriate cost of capital is 9%, project e time cash flow minus 1200 $430 $540 $560 $340 $140 the irr is

Solutions

Expert Solution

IRR :
IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash Outflows or Rate of growth is expected from project/ Investment. At IRR, NPV of Project/ Investment will be Zero.
It assumes that intermediary Cfs are reinvested at IRR only.

IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in disc rate ] * 1%

If IRR > Cost of Capital - Project can be accepted
IRR = Cost of Capital - Indifferebce Point - Project will be accepted / Rejected
IRR < Cost of Capital - Project will be erejected

Year CF PVF @23 % Disc CF PVF @24 % Disc CF
0 $         -1,200.00          1.0000 $         -1,200.00         1.0000 $         -1,200.00
1 $             430.00          0.8130 $             349.59         0.8065 $             346.77
2 $             540.00          0.6610 $             356.93         0.6504 $             351.20
3 $             560.00          0.5374 $             300.93         0.5245 $             293.71
4 $             340.00          0.4369 $             148.55         0.4230 $             143.81
5 $             140.00          0.3552 $                49.73         0.3411 $                47.76
NPV $                  5.73 $              -16.75

IRR = Rate at which least +ve NPV + [ NPV at that rate / Change in NPV due to Inc of 1% in Int Rate ] * 1%
= 23 % + [ 5.73 / ( 5.73 - ( -16.75) ) ] * 1 %
= 23 % + [ 5.73 / ( 22.48) ] * 1 %
= 23 % + [ 0.25 ] * 1 %
= 23 % + 0.25 %
= 23.25 %


Related Solutions

Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,400 $510 $600 $600 $380 $180 Should the project be accpeted or rejected?
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)        Project E   Time: 0 1 2 3 4 5   Cash flow –$2,000 $750 $780 $720 $500 $300        IRR %    Should the project be accepted or rejected? Accepted Rejected
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) What is the IRR? Should it be accepted or rejected?        Project E   Time: 0 1 2 3 4 5   Cash flow –$1,000 $350 $480 $520 $300 $100
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,400 $510 $600 $600 $380 $180 Should the project be accepted or rejected? accepted rejected
1. Compute the NPV of a project with the following information. The IRR is 9%. The...
1. Compute the NPV of a project with the following information. The IRR is 9%. The project life is 3 years. The initial cost is $19,000. In years 1 and 2 the cash inflows are $4,500 and $5,500, respectively. Cash flow in year 3 is missing. WACC is 12%.
If your company’s weighted average cost of capital is 17% and the IRR on a project...
If your company’s weighted average cost of capital is 17% and the IRR on a project is 12%, would it be profitable to invest?
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not...
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: –$11,500 $3,600 $4,430 $1,770 $2,400 IRR__________% Should the project be accepted or rejected? accepted rejected
The Basics of Capital Budgeting: IRR IRR A project's internal rate of return (IRR) is the...
The Basics of Capital Budgeting: IRR IRR A project's internal rate of return (IRR) is the (Select: compound rate, discount rate, or risk-ree rate) that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the (Select: YTM, Coupon, gain) on a bond. CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be...
Internal rate of return (IRR) Ziff Corp. is evaluating a proposed capital budgeting project that will...
Internal rate of return (IRR) Ziff Corp. is evaluating a proposed capital budgeting project that will require an initial investment of $1,550,000. The project is expected to generate the following net cash flows: Year Net Cash Flow 1 $350,000 2 $475,000 3 $400,000 4 $475,000 Ziff Corp. hasbeen basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to start using the internal rate of return (IRR) method for capital budgeting decisions. The CFO says that the...
Question #9 Calculating NPA and IRR LO1,5 A project that provides annual cash flows of $11,700...
Question #9 Calculating NPA and IRR LO1,5 A project that provides annual cash flows of $11,700 for nine years’ costs $63,000 today is the a good project if the required return is 8 percent? What if it’s 20 percent? At what discount rate would you be indifferent between accepting the project the project and rejecting it?    
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT