In: Finance
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project F | |||||
Time: | 0 | 1 | 2 | 3 | 4 |
Cash flow: | –$11,500 | $3,600 | $4,430 | $1,770 | $2,400 |
IRR__________%
Should the project be accepted or rejected?
accepted
rejected