Question

In: Finance

Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...

Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) What is the IRR? Should it be accepted or rejected?

    

  Project E
  Time: 0 1 2 3 4 5
  Cash flow –$1,000 $350 $480 $520 $300

$100

Solutions

Expert Solution

Solution :

The IRR Static for the project E, is 25.49 %

As per the IRR Rule,

a. In case the IRR of the project is greater than its cost of capital, the project should be accepted.

b. In case the IRR of the project is lesser than its cost of capital, the project should not be accepted.

Since, the IRR of the project E, at 25.49 %, is greater than its cost of capital at 8 % , the project should be accepted.

Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.


Related Solutions

Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$2,700 $830 $840 $760 $540 $340
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,400 $510 $600 $600 $380 $180 Should the project be accpeted or rejected?
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)        Project E   Time: 0 1 2 3 4 5   Cash flow –$2,000 $750 $780 $720 $500 $300        IRR %    Should the project be accepted or rejected? Accepted Rejected
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,400 $510 $600 $600 $380 $180 Should the project be accepted or rejected? accepted rejected
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not...
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: –$11,500 $3,600 $4,430 $1,770 $2,400 IRR__________% Should the project be accepted or rejected? accepted rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Should the project be accepted or rejected?
commute the irr static for a project e the appropriatecost of capital is 9%commute...
commute the irr static for a project e the appropriate cost of capital is 9%commute the irr static for project e the appropriate cost of capital is 9%, project e time cash flow minus 1200 $430 $540 $560 $340 $140 the irr is
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent....
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project I Time: 0 1 2 3 4 Cash flow –$11,500 $5,580 $4,430 $1,770 $2,250 MIRR % Should the project be accepted or rejected?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT