Question

In: Finance

Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...

Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,400 $510 $600 $600 $380 $180

Should the project be accpeted or rejected?

Solutions

Expert Solution

1) IRR 22.39%
2) Project has IRR more than cost of capital.So, it should be accepted.
Working:
IRR is the rate at which Net Present Value of project is zero.
a. Calculation of Net Present Value(NPV) at 7%
Year Cash flow Discount factor Present Value
0 $       -1,400      1.0000 $ -1,400.00
1 $            510      0.9346 $      476.64
2 $            600      0.8734 $      524.06
3 $            600      0.8163 $      489.78
4 $            380      0.7629 $      289.90
5 $            180      0.7130 $      128.34
Total $      508.72
NPV and discount rate has inverse relation.If Discount rate increases, NPV decreses and vice versa.
So, IRR must be more than 7% to get NPV Zero.
b. Calculation of Net Present Value(NPV) at 25%
Year Cash flow Discount factor Present Value
0 $       -1,400      1.0000 $ -1,400.00
1 $            510      0.8000 $      408.00
2 $            600      0.6400 $      384.00
3 $            600      0.5120 $      307.20
4 $            380      0.4096 $      155.65
5 $            180      0.3277 $         58.98
Total $       -86.17
IRR = 7%+(25%-7%)*(508.72/(508.72+86.17))
= 22.39%
This is an approximation method.So, It mat not be exact IRR but approximate to exact IRR.

Related Solutions

Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)        Project E   Time: 0 1 2 3 4 5   Cash flow –$2,000 $750 $780 $720 $500 $300        IRR %    Should the project be accepted or rejected? Accepted Rejected
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) What is the IRR? Should it be accepted or rejected?        Project E   Time: 0 1 2 3 4 5   Cash flow –$1,000 $350 $480 $520 $300 $100
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not...
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: –$11,500 $3,600 $4,430 $1,770 $2,400 IRR__________% Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project M   Time: 0 1 2 3 4 5   Cash flow –$2,000 $550 $680 $720 $800 $300         NPV $       Should the project be accepted or rejected? Accepted Rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Should the project be accepted or rejected?
commute the irr static for a project e the appropriatecost of capital is 9%commute...
commute the irr static for a project e the appropriate cost of capital is 9%commute the irr static for project e the appropriate cost of capital is 9%, project e time cash flow minus 1200 $430 $540 $560 $340 $140 the irr is
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent....
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project I Time: 0 1 2 3 4 Cash flow –$11,500 $5,580 $4,430 $1,770 $2,250 MIRR % Should the project be accepted or rejected?
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT