Question

In: Civil Engineering

1) Timber formwork and shoring support a cast-in-place concrete slab during curing. The 9 inch concrete...

1) Timber formwork and shoring support a cast-in-place concrete slab during curing. The 9 inch concrete slab is placed on the ¾ inch plywood supports that are supported by 2 x 4 joists spaced 16 inches apart. 4 x 6 stringers spaced 36 inches apart support these joists. The shores directly underneath the stringers are 4 x 4 and are spaced at 5 ft intervals along the stringers. The lumber is No. 2 Douglas Fir Larch. The concrete has a specific weight of 150 pcf and a construction live load of 50 psf. Limit all deflection to l/360. [Weight of forms, estimated = 7.5psf]

You are asked to:

1. Check the joist spacing of 16 in.                                                 

2. Check the stringer spacing of 36 in.                                            

3. Check shoring space of 5 ft along the stringer.                         

Solutions

Expert Solution


Related Solutions

1-A building requires a 100-foot long by 83-foot wide by 5-inch thick concrete slab. Using a...
1-A building requires a 100-foot long by 83-foot wide by 5-inch thick concrete slab. Using a waste factor of 10 %, Include calculations. a)determine the number of cubic yards of concrete needed to pour the slab. (2 points) 2-Determine the number of rolls of wire mesh needed if there are 750 SF of wire per roll and 12% of waste. Include calculations. (2 points) 9 BCT 2770 Estimating Fundamentals 3-Determine the amount of rebar needed for the slab if it...
1- what is the formula to find the approximate depth of a concrete slab that measure...
1- what is the formula to find the approximate depth of a concrete slab that measure 180' long X 110' wide (Feets)? [[let said that I have two of them (same length and wide, and one have have 4" thickness and the other 6" (inches)? ]] 2. What types of concrete slabs are better to use in residential, commercial, and one story store buildings? please explain clearly, thank you.
Please name the RMS Specification of construction of cast-in-place reinforced concrete piles without permanent casing. (200-250...
Please name the RMS Specification of construction of cast-in-place reinforced concrete piles without permanent casing. (200-250 words)
International business 1. What is the current status of Pakistan in the world market place? support...
International business 1. What is the current status of Pakistan in the world market place? support your answer with research. please give citiation. 2. What is the ease of doing business in Pakistan? support your answer with research. please give citiation. 3. Are other countries wanting to invest in Pakistan? support your answer with research. please give citiation. 4. What do you see as the future of your country in the world market place? support your answer with research. please...
Support we have a dataset with 10 instances as follows: 9 5 1 9 76 42...
Support we have a dataset with 10 instances as follows: 9 5 1 9 76 42 9 26 23 18 (1) What are the arithmetic mean, median and mode values? (2) Is the data negative skewed or positive skewed? (3) If using a polynomial function to transform this dataset, what the value of the power could be used?
1. Explain the formation of ettringite during a sulfate attack to concrete. 2. What is the...
1. Explain the formation of ettringite during a sulfate attack to concrete. 2. What is the alkali-aggregate reaction?
1. what are some potential risks during technical support activities?
1. what are some potential risks during technical support activities?2. he described how do you apply a person-centered approach to all interactions with people living with dementia3. Describe 2 instances when you used reality orientation to gain cooperation
USING USA IBC CH.9 1.            Name the standard which governs all aspects of concrete; materials...
USING USA IBC CH.9 1.            Name the standard which governs all aspects of concrete; materials used to produce concrete, concrete itself                 and testing thereof.                 What other standards are also permitted to be used in compliance tests for concrete? 2.            There are many documents for structural concrete construction using steel as reinforcement. List five such documents. 3.           For Group R-3 buildings not more than three stories above grade plane, the specified compressive strength of concrete in vertical...
The following transactions took place in the town of Burchette during 20X3: 1. A bond issue...
The following transactions took place in the town of Burchette during 20X3: 1. A bond issue of $12,000,000 was authorized for the construction of a library, and the estimated bond proceeds and related appropriations were recorded in the General Ledger accounts of a new Capital Projects Fund. 2. The bonds were sold at a premium of $90,000. 3.The cost of issuing the bonds, $80,000, was paid. 4. An order was placed for material estimated to cost $6,500,000. 5. Salaries and...
During June, the following changes in inventory item A took place:    June 1   Balance   800...
During June, the following changes in inventory item A took place:    June 1   Balance   800 units @ $20 June 8   Sold       600 units @ $50 June 10   Purchased   800 units @ $21 June  14   Sold       700 units @ $50 June 24   Purchased   600 units @ $22            Instructions What is the cost of goods sold and the ending inventory for item A under the following methods? (Show calculations.) A. Periodic (a)   FIFO (b)   LIFO (c) Average...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT