Question

In: Accounting

The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project...

  1. The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project will last 10 years and will generate free cash flows (FCFs) of £100 million per year for 10-years. These FCFs are after-tax but before financing costs. The unlevered (i.e., all equity) cost of capital for the project is 10% and BRC’s tax rate is 40%.

    BRC will finance the project with a combination of debt and equity and is considering three alternatives as regards borrowing. The (pre-tax) interest rate in each case would be 5%. (Note: there are no tax consequences when the firm repays principal – as opposed to interest – on a loan).

    1. “ConstantD/V”:Adjustingtheamountofborrowingeachyearsothattheratio of the amount of debt to the total value of the project is maintained at 40%; OR

    2. “Constantamountofdebt”:Takingoutaconventional10-yearloan(i.e.,theloan will be repaid in year 10) with the amount of the loan equal to 40% of the unlevered value of the project; OR

    3. “Amortizing Loan”: Taking out a 10-year amortizing loan, i.e., one in which equal payments are made each year so that the loan – including interest – is finally repaid in year 10. The amount of the loan will be equal to 40% of the unlevered value of the project.

    Questions

    1. What is the PV of the FCFs if the project is all equity financed?

    2. What is the present value of the tax shields for borrowing scenario #1 (Constant D/V)?

    3. What is the present value of the tax shields for borrowing scenario#2 (Constant amount of debt)?

    4. What is the present value of the tax shields for borrowing scenario #3 (Amortizing Loan)?

    5. Are these tax shields the same? If not, why not?

    6. Suppose that BRC plans that all after-tax project cash flows each year, net of any loan interest payments and loan repayments due to lenders in that year, will be paid out to shareholders as a dividend. If you were a bank considering lending to BRC for this project, how would BRC’s dividend plan affect your view of each of the three borrowing alternatives?

Solutions

Expert Solution

PV of the FCFs if Project is all Equity Financed Amount in GBP Millions
Free Cash Flows for 10 years 100 Million GBP Per Year
Cost of Equity 10%
Tax Rate 40%
Present Value of Cash Flows = PV(rate,nper,pmt)
= PV(0.1,10,-100)
= 614.46 GBP Million
Present Value of Tax Sheilds in Scenario #2 Constant Amount of Debt
Year 1 2 3 4 5 6 7 8 9 10
Free Cash Flows Before Finance Cost 100 100 100 100 100 100 100 100 100 100
Amount Borrowed 245.78 245.78 245.78 245.78 245.78 245.78 245.78 245.78 245.78 245.78
(614.46*40%)
Interest @ 5% 12.289 12.289 12.289 12.289 12.289 12.289 12.289 12.289 12.289 12.289
Tax Saving @ 40% 4.9156 4.9156 4.9156 4.9156 4.9156 4.9156 4.9156 4.9156 4.9156 4.9156
(12.289*40%)
WACC = Cost of debt * weight of Debt + Cost of Equity * Weight of Equity
= 5*0.4+10*0.6
= 8%
Present Value of Tax Sheild = PV(rate,nper,pmt)
= PV(0.08,10,-4.9156)
= 32.98 GBP Million

Related Solutions

The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project will last 10 years and will generate free cash flows (FCFs) of £100 million per year for 10-years. These FCFs are after-tax but before financing costs. The unlevered (i.e., all equity) cost of capital for the project is 10% and BRC’s tax rate is 40%. BRC will finance the project with a combination of debt and equity and is considering three alternatives as regards...
Section 2. Question 1 Al Hassan Engineering has won a tender to build an oil field...
Section 2. Question 1 Al Hassan Engineering has won a tender to build an oil field in the Sea of Oman. In order to transport the workers to the site, Al Hassan Engineering has identified the following two options with related cost: Option1: To buy a ship for OMR 15,000,000. Annual fixed costs will be OMR 300,000 the variable cost per journey is OMR 2,000. At the end of the 3-year project, the ship can be disposed of for OMR...
The NCO Corporation has won a tender to drill an oil field in the Oman Sea....
The NCO Corporation has won a tender to drill an oil field in the Oman Sea. In order to transport the workers to the site, NCO has the following two options with related cost: Option1:To buy a ship for O.R 20,000,000. Annual fixed operating costs will be O.R 500,000 the variable cost per journey is O.R 1,000. At the end of the four-year project, the ship can be disposed of for O.R 12,000,000. Option2:To buy a helicopter for O.R 12,000,000....
AZRB is a road bridge construction company. The company plan to build a major road bridge...
AZRB is a road bridge construction company. The company plan to build a major road bridge for its new project. Table shows the process sequence and other related data for the major road bridge development. Table :Activities to construct the bridge, estimated time and crashing cost. Activity Predecessor Time Estimates (Days) Cost (RM per day) Crash cost (RM per day) Optimistic Most Likely Pessimistic Maximum crash time (days) a m b A - 65 73 90 100 150 6 B...
Economics verses civics The World Bank supported a project in Cairo to build a highway to...
Economics verses civics The World Bank supported a project in Cairo to build a highway to rural agricultural communities so that they would be able to sell their produce in the city. The smog from the highway is deleterious to the sphinx, resulting in protests. What are the issues – would you support the highway’s construction ?
Your firm MS Ankomadu has won a project of €1,785,000 to build a 161kV/33kV sub-station. You...
Your firm MS Ankomadu has won a project of €1,785,000 to build a 161kV/33kV sub-station. You have been selected as the project manager to lead the project team for the successful execution of the project. You are the project manager, there are a total of 8,400 hours of work schedule on the project. You made your checks with the accounting department, and they told you that you have spent a total of €1,144,000. According to the schedule, your team should...
Economics vs Civics:The World Bank supported a project in Cairo to build a highway to rural...
Economics vs Civics:The World Bank supported a project in Cairo to build a highway to rural agricultural communities so that they would be able to sell their produce in the city. The smog from the highway is deleterious to the sphinx, resulting in protests. What are the issues – would you support the highway’s construction? Please explain using economic terms to justify your answer.
A highway construction company is under contract to build a new roadway through a scenic area...
A highway construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $18,000,000, with annual upkeep estimated at $150,000 per year. Additional income from tourist (Benefits) of $900,000 per year is estimated. The road is expected to have a useful commercial life of 20 years. Determine if the highway should be constructed at a discount rate of 6% per year, applying the Conventional B/C...
A highway construction company is under contract to build a new roadway through a scenic area...
A highway construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $18,000,000, with annual upkeep estimated at $150,000 per year. Additional income from tourist (Benefits) of $900,000 per year is estimated. The road is expected to have a useful commercial life of 20 years. Determine if the highway should be constructed at a discount rate of 6% per year, applying the Conventional B/C...
Triad Corporation has established a joint venture with Tobacco Road Construction, Inc., to build a toll...
Triad Corporation has established a joint venture with Tobacco Road Construction, Inc., to build a toll road in North Carolina. The initial investment in paving equipment is $81.2 million. The equipment will be fully depreciated using the straight-line method over its economic life of five years. Earnings before interest, taxes, and depreciation collected from the toll road are projected to be $12.3 million per annum for 20 years starting from the end of the first year. The corporate tax rate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT