In: Operations Management
Your firm MS Ankomadu has won a project of €1,785,000 to build a
161kV/33kV sub-station. You have been selected as the project
manager to lead the project team for the successful execution of
the project. You are the project manager, there are a total of
8,400 hours of work schedule on the project. You made your checks
with the accounting department, and they told you that you have
spent a total of €1,144,000. According to the schedule, your team
should have worked 5000 hours, but your foreman says that the team
was allowed to work some overtime, and they have actually put in
5000 hours of work.
Question 1
A. Produce the works breakdown structure (WBS) for the project in
the CASE STUDY. (EV 7mark)